Silver Star's North American Flight Center Net Present Value (NPV) / MBA Resources

Introduction to Net Present Value (NPV) - What is Net Present Value (NPV) ? How it impacts financial decisions regarding project management?

NPV solution for Silver Star's North American Flight Center case study


At Oak Spring University, we provide corporate level professional Net Present Value (NPV) case study solution. Silver Star's North American Flight Center case study is a Harvard Business School (HBR) case study written by Greg Bevan, James G. Clawson. The Silver Star's North American Flight Center (referred as “Flight North” from here on) case study provides evaluation & decision scenario in field of Leadership & Managing People. It also touches upon business topics such as - Value proposition, Leadership.

The net present value (NPV) of an investment proposal is the present value of the proposal’s net cash flows less the proposal’s initial cash outflow. If a project’s NPV is greater than or equal to zero, the project should be accepted.

NPV = Present Value of Future Cash Flows LESS Project’s Initial Investment






Case Description of Silver Star's North American Flight Center Case Study


The new manager of the North American Flight Center of a global firm faces a number of problems including an opening for the director of flight operations, internal interpersonal strife, resentment against his chief pilot, a senior pilot who seems to be poisoning the culture, and a new computer system. This composite but true case presents common issues faced in managing a North American corporate flight center. Names have been disguised.


Case Authors : Greg Bevan, James G. Clawson

Topic : Leadership & Managing People

Related Areas : Leadership




Calculating Net Present Value (NPV) at 6% for Silver Star's North American Flight Center Case Study


Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 6 %
Discounted
Cash Flows
Year 0 (10003834) -10003834 - -
Year 1 3464649 -6539185 3464649 0.9434 3268537
Year 2 3953664 -2585521 7418313 0.89 3518747
Year 3 3971604 1386083 11389917 0.8396 3334635
Year 4 3240589 4626672 14630506 0.7921 2566850
TOTAL 14630506 12688769




The Net Present Value at 6% discount rate is 2684935

In isolation the NPV number doesn't mean much but put in right context then it is one of the best method to evaluate project returns. In this article we will cover -

Different methods of capital budgeting


What is NPV & Formula of NPV,
How it is calculated,
How to use NPV number for project evaluation, and
Scenario Planning given risks and management priorities.




Capital Budgeting Approaches

Methods of Capital Budgeting


There are four types of capital budgeting techniques that are widely used in the corporate world –

1. Payback Period
2. Profitability Index
3. Net Present Value
4. Internal Rate of Return

Apart from the Payback period method which is an additive method, rest of the methods are based on Discounted Cash Flow technique. Even though cash flow can be calculated based on the nature of the project, for the simplicity of the article we are assuming that all the expected cash flows are realized at the end of the year.

Discounted Cash Flow approaches provide a more objective basis for evaluating and selecting investment projects. They take into consideration both –

1. Timing of the expected cash flows – stockholders of Flight North have higher preference for cash returns over 4-5 years rather than 10-15 years given the nature of the volatility in the industry.
2. Magnitude of both incoming and outgoing cash flows – Projects can be capital intensive, time intensive, or both. Flight North shareholders have preference for diversified projects investment rather than prospective high income from a single capital intensive project.






Formula and Steps to Calculate Net Present Value (NPV) of Silver Star's North American Flight Center

NPV = Net Cash In Flowt1 / (1+r)t1 + Net Cash In Flowt2 / (1+r)t2 + … Net Cash In Flowtn / (1+r)tn
Less Net Cash Out Flowt0 / (1+r)t0

Where t = time period, in this case year 1, year 2 and so on.
r = discount rate or return that could be earned using other safe proposition such as fixed deposit or treasury bond rate. Net Cash In Flow – What the firm will get each year.
Net Cash Out Flow – What the firm needs to invest initially in the project.

Step 1 – Understand the nature of the project and calculate cash flow for each year.
Step 2 – Discount those cash flow based on the discount rate.
Step 3 – Add all the discounted cash flow.
Step 4 – Selection of the project

Why Leadership & Managing People Managers need to know Financial Tools such as Net Present Value (NPV)?

In our daily workplace we often come across people and colleagues who are just focused on their core competency and targets they have to deliver. For example marketing managers at Flight North often design programs whose objective is to drive brand awareness and customer reach. But how that 30 point increase in brand awareness or 10 point increase in customer touch points will result into shareholders’ value is not specified.

To overcome such scenarios managers at Flight North needs to not only know the financial aspect of project management but also needs to have tools to integrate them into part of the project development and monitoring plan.

Calculating Net Present Value (NPV) at 15%

After working through various assumptions we reached a conclusion that risk is far higher than 6%. In a reasonably stable industry with weak competition - 15% discount rate can be a good benchmark.



Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 15 %
Discounted
Cash Flows
Year 0 (10003834) -10003834 - -
Year 1 3464649 -6539185 3464649 0.8696 3012738
Year 2 3953664 -2585521 7418313 0.7561 2989538
Year 3 3971604 1386083 11389917 0.6575 2611394
Year 4 3240589 4626672 14630506 0.5718 1852817
TOTAL 10466488


The Net NPV after 4 years is 462654

(10466488 - 10003834 )








Calculating Net Present Value (NPV) at 20%


If the risk component is high in the industry then we should go for a higher hurdle rate / discount rate of 20%.

Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 20 %
Discounted
Cash Flows
Year 0 (10003834) -10003834 - -
Year 1 3464649 -6539185 3464649 0.8333 2887208
Year 2 3953664 -2585521 7418313 0.6944 2745600
Year 3 3971604 1386083 11389917 0.5787 2298382
Year 4 3240589 4626672 14630506 0.4823 1562784
TOTAL 9493973


The Net NPV after 4 years is -509861

At 20% discount rate the NPV is negative (9493973 - 10003834 ) so ideally we can't select the project if macro and micro factors don't allow financial managers of Flight North to discount cash flow at lower discount rates such as 15%.





Acceptance Criteria of a Project based on NPV

Simplest Approach – If the investment project of Flight North has a NPV value higher than Zero then finance managers at Flight North can ACCEPT the project, otherwise they can reject the project. This means that project will deliver higher returns over the period of time than any alternate investment strategy.

In theory if the required rate of return or discount rate is chosen correctly by finance managers at Flight North, then the stock price of the Flight North should change by same amount of the NPV. In real world we know that share price also reflects various other factors that can be related to both macro and micro environment.

In the same vein – accepting the project with zero NPV should result in stagnant share price. Finance managers use discount rates as a measure of risk components in the project execution process.

Sensitivity Analysis

Project selection is often a far more complex decision than just choosing it based on the NPV number. Finance managers at Flight North should conduct a sensitivity analysis to better understand not only the inherent risk of the projects but also how those risks can be either factored in or mitigated during the project execution. Sensitivity analysis helps in –

What can impact the cash flow of the project.

What are the uncertainties surrounding the project Initial Cash Outlay (ICO’s). ICO’s often have several different components such as land, machinery, building, and other equipment.

Understanding of risks involved in the project.

What will be a multi year spillover effect of various taxation regulations.

What are the key aspects of the projects that need to be monitored, refined, and retuned for continuous delivery of projected cash flows.

Some of the assumptions while using the Discounted Cash Flow Methods –

Projects are assumed to be Mutually Exclusive – This is seldom the came in modern day giant organizations where projects are often inter-related and rejecting a project solely based on NPV can result in sunk cost from a related project.

Independent projects have independent cash flows – As explained in the marketing project – though the project may look independent but in reality it is not as the brand awareness project can be closely associated with the spending on sales promotions and product specific advertising.






Negotiation Strategy of Silver Star's North American Flight Center

References & Further Readings

Greg Bevan, James G. Clawson (2018), "Silver Star's North American Flight Center Harvard Business Review Case Study. Published by HBR Publications.


Strategic Elements Ltd SWOT Analysis / TOWS Matrix

Financial , Misc. Financial Services


MPC Ltd SWOT Analysis / TOWS Matrix

Services , Business Services


Beter Bed SWOT Analysis / TOWS Matrix

Services , Retail (Specialty)


Salasar Techno SWOT Analysis / TOWS Matrix

Capital Goods , Constr. - Supplies & Fixtures


Daikokuya SWOT Analysis / TOWS Matrix

Technology , Electronic Instr. & Controls


DIA SWOT Analysis / TOWS Matrix

Services , Retail (Grocery)


BB Healthcare SWOT Analysis / TOWS Matrix

Financial , Misc. Financial Services


Wirecard AG SWOT Analysis / TOWS Matrix

Services , Business Services


Talmocom SWOT Analysis / TOWS Matrix

Consumer/Non-Cyclical , Personal & Household Prods.


Bj Lier Mat A SWOT Analysis / TOWS Matrix

Capital Goods , Constr. - Supplies & Fixtures