JetBlue Airways: A New Beginning Net Present Value (NPV) / MBA Resources

Introduction to Net Present Value (NPV) - What is Net Present Value (NPV) ? How it impacts financial decisions regarding project management?

NPV solution for JetBlue Airways: A New Beginning case study


At Oak Spring University, we provide corporate level professional Net Present Value (NPV) case study solution. JetBlue Airways: A New Beginning case study is a Harvard Business School (HBR) case study written by David W. Hoyt, Charles A. O'Reilly, Hayagreeva Rao, Kerry J. Sulkowicz. The JetBlue Airways: A New Beginning (referred as “Irop Jetblue” from here on) case study provides evaluation & decision scenario in field of Leadership & Managing People. It also touches upon business topics such as - Value proposition, Change management, Leadership, Leading teams, Motivating people, Organizational culture.

The net present value (NPV) of an investment proposal is the present value of the proposal’s net cash flows less the proposal’s initial cash outflow. If a project’s NPV is greater than or equal to zero, the project should be accepted.

NPV = Present Value of Future Cash Flows LESS Project’s Initial Investment






Case Description of JetBlue Airways: A New Beginning Case Study


JetBlue Airways grew rapidly from its founding in 2000, focusing on providing low-cost service to previously underserved cities, while giving passengers a high-quality experience, ("bringing humanity back to air travel"). An ice storm at JFK airport on February 14, 2007 caused 1,195 flights to be cancelled over a six day period, and stranded several planes on the taxiway for many hours. JetBlue, previously viewed as one of the best airlines (if not the best) for customer service, took extensive criticism from the public, press, and Congress. In addition, the disruptions caused by the storm cost the company over $41 million. The 2007 storm highlighted deficiencies in JetBlue's operational infrastructure. Some top-down changes were made, but disruptions caused by thunderstorms in summer 2008 demonstrated that the airline's ability to deal with irregular operations (IROPs) was woefully inadequate. The company instituted a program (IROP Integrity) that utilized the talents of more than 200 employees, from all levels, and all parts of the airline, to address these problems. This was done through process mapping, root cause analysis, and cross-discipline cooperation working on 100 projects to improve both technology and processes. In February 2010, an ice storm far worse than the 2007 event again disrupted operations at JFK. This time, the airline had to cancel far fewer flights, which were mostly done before passengers arrived at the airport, operations the next day, and the cost was a small fraction of the cost of the 2007 disruption. This case describes the IROP Integrity project-its origins, the role of executive sponsors, project leadership and organization, and the processes used to identify and carry out improvement projects. It also describes the legacy of IROP Integrity on the JetBlue organization and culture.


Case Authors : David W. Hoyt, Charles A. O'Reilly, Hayagreeva Rao, Kerry J. Sulkowicz

Topic : Leadership & Managing People

Related Areas : Change management, Leadership, Leading teams, Motivating people, Organizational culture




Calculating Net Present Value (NPV) at 6% for JetBlue Airways: A New Beginning Case Study


Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 6 %
Discounted
Cash Flows
Year 0 (10015796) -10015796 - -
Year 1 3470831 -6544965 3470831 0.9434 3274369
Year 2 3962608 -2582357 7433439 0.89 3526707
Year 3 3959355 1376998 11392794 0.8396 3324351
Year 4 3249515 4626513 14642309 0.7921 2573920
TOTAL 14642309 12699347




The Net Present Value at 6% discount rate is 2683551

In isolation the NPV number doesn't mean much but put in right context then it is one of the best method to evaluate project returns. In this article we will cover -

Different methods of capital budgeting


What is NPV & Formula of NPV,
How it is calculated,
How to use NPV number for project evaluation, and
Scenario Planning given risks and management priorities.




Capital Budgeting Approaches

Methods of Capital Budgeting


There are four types of capital budgeting techniques that are widely used in the corporate world –

1. Payback Period
2. Profitability Index
3. Net Present Value
4. Internal Rate of Return

Apart from the Payback period method which is an additive method, rest of the methods are based on Discounted Cash Flow technique. Even though cash flow can be calculated based on the nature of the project, for the simplicity of the article we are assuming that all the expected cash flows are realized at the end of the year.

Discounted Cash Flow approaches provide a more objective basis for evaluating and selecting investment projects. They take into consideration both –

1. Magnitude of both incoming and outgoing cash flows – Projects can be capital intensive, time intensive, or both. Irop Jetblue shareholders have preference for diversified projects investment rather than prospective high income from a single capital intensive project.
2. Timing of the expected cash flows – stockholders of Irop Jetblue have higher preference for cash returns over 4-5 years rather than 10-15 years given the nature of the volatility in the industry.






Formula and Steps to Calculate Net Present Value (NPV) of JetBlue Airways: A New Beginning

NPV = Net Cash In Flowt1 / (1+r)t1 + Net Cash In Flowt2 / (1+r)t2 + … Net Cash In Flowtn / (1+r)tn
Less Net Cash Out Flowt0 / (1+r)t0

Where t = time period, in this case year 1, year 2 and so on.
r = discount rate or return that could be earned using other safe proposition such as fixed deposit or treasury bond rate. Net Cash In Flow – What the firm will get each year.
Net Cash Out Flow – What the firm needs to invest initially in the project.

Step 1 – Understand the nature of the project and calculate cash flow for each year.
Step 2 – Discount those cash flow based on the discount rate.
Step 3 – Add all the discounted cash flow.
Step 4 – Selection of the project

Why Leadership & Managing People Managers need to know Financial Tools such as Net Present Value (NPV)?

In our daily workplace we often come across people and colleagues who are just focused on their core competency and targets they have to deliver. For example marketing managers at Irop Jetblue often design programs whose objective is to drive brand awareness and customer reach. But how that 30 point increase in brand awareness or 10 point increase in customer touch points will result into shareholders’ value is not specified.

To overcome such scenarios managers at Irop Jetblue needs to not only know the financial aspect of project management but also needs to have tools to integrate them into part of the project development and monitoring plan.

Calculating Net Present Value (NPV) at 15%

After working through various assumptions we reached a conclusion that risk is far higher than 6%. In a reasonably stable industry with weak competition - 15% discount rate can be a good benchmark.



Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 15 %
Discounted
Cash Flows
Year 0 (10015796) -10015796 - -
Year 1 3470831 -6544965 3470831 0.8696 3018114
Year 2 3962608 -2582357 7433439 0.7561 2996301
Year 3 3959355 1376998 11392794 0.6575 2603340
Year 4 3249515 4626513 14642309 0.5718 1857921
TOTAL 10475676


The Net NPV after 4 years is 459880

(10475676 - 10015796 )








Calculating Net Present Value (NPV) at 20%


If the risk component is high in the industry then we should go for a higher hurdle rate / discount rate of 20%.

Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 20 %
Discounted
Cash Flows
Year 0 (10015796) -10015796 - -
Year 1 3470831 -6544965 3470831 0.8333 2892359
Year 2 3962608 -2582357 7433439 0.6944 2751811
Year 3 3959355 1376998 11392794 0.5787 2291293
Year 4 3249515 4626513 14642309 0.4823 1567089
TOTAL 9502552


The Net NPV after 4 years is -513244

At 20% discount rate the NPV is negative (9502552 - 10015796 ) so ideally we can't select the project if macro and micro factors don't allow financial managers of Irop Jetblue to discount cash flow at lower discount rates such as 15%.





Acceptance Criteria of a Project based on NPV

Simplest Approach – If the investment project of Irop Jetblue has a NPV value higher than Zero then finance managers at Irop Jetblue can ACCEPT the project, otherwise they can reject the project. This means that project will deliver higher returns over the period of time than any alternate investment strategy.

In theory if the required rate of return or discount rate is chosen correctly by finance managers at Irop Jetblue, then the stock price of the Irop Jetblue should change by same amount of the NPV. In real world we know that share price also reflects various other factors that can be related to both macro and micro environment.

In the same vein – accepting the project with zero NPV should result in stagnant share price. Finance managers use discount rates as a measure of risk components in the project execution process.

Sensitivity Analysis

Project selection is often a far more complex decision than just choosing it based on the NPV number. Finance managers at Irop Jetblue should conduct a sensitivity analysis to better understand not only the inherent risk of the projects but also how those risks can be either factored in or mitigated during the project execution. Sensitivity analysis helps in –

What can impact the cash flow of the project.

What are the key aspects of the projects that need to be monitored, refined, and retuned for continuous delivery of projected cash flows.

What will be a multi year spillover effect of various taxation regulations.

What are the uncertainties surrounding the project Initial Cash Outlay (ICO’s). ICO’s often have several different components such as land, machinery, building, and other equipment.

Understanding of risks involved in the project.

Some of the assumptions while using the Discounted Cash Flow Methods –

Projects are assumed to be Mutually Exclusive – This is seldom the came in modern day giant organizations where projects are often inter-related and rejecting a project solely based on NPV can result in sunk cost from a related project.

Independent projects have independent cash flows – As explained in the marketing project – though the project may look independent but in reality it is not as the brand awareness project can be closely associated with the spending on sales promotions and product specific advertising.






Negotiation Strategy of JetBlue Airways: A New Beginning

References & Further Readings

David W. Hoyt, Charles A. O'Reilly, Hayagreeva Rao, Kerry J. Sulkowicz (2018), "JetBlue Airways: A New Beginning Harvard Business Review Case Study. Published by HBR Publications.


Switch SWOT Analysis / TOWS Matrix

Technology , Computer Services


CPI Card SWOT Analysis / TOWS Matrix

Technology , Software & Programming


SPH REIT SWOT Analysis / TOWS Matrix

Services , Real Estate Operations


Pennsylvania RE SWOT Analysis / TOWS Matrix

Services , Real Estate Operations


Berentzen Gruppe SWOT Analysis / TOWS Matrix

Consumer/Non-Cyclical , Beverages (Alcoholic)


Gulf Resources SWOT Analysis / TOWS Matrix

Basic Materials , Chemical Manufacturing