Introduction to Net Present Value (NPV) - What is Net Present Value (NPV) ? How it impacts financial decisions regarding project management?
At Oak Spring University, we provide corporate level professional Net Present Value (NPV) case study solution. FUTUR-Working towards Social Inclusion, Spanish Version case study is a Harvard Business School (HBR) case study written by Daniel Arenas, Alfred Vernis. The FUTUR-Working towards Social Inclusion, Spanish Version (referred as “Futur Barcelona” from here on) case study provides evaluation & decision scenario in field of Finance & Accounting. It also touches upon business topics such as - Value proposition, .
The net present value (NPV) of an investment proposal is the present value of the proposal’s net cash flows less the proposal’s initial cash outflow. If a project’s NPV is greater than or equal to zero, the project should be accepted.
FUTUR is a small nonprofit organization founded in Barcelona in 1996. Its aim is to create social and labor opportunities for potentially excluded individuals such as ex-convicts, single mothers with no income, battered women, the homeless, people over 45 years old affected by long-term unemployment, drug and alcohol addicts, and immigrants mostly from Latin America and Northern Africa with problems adapting to life in Barcelona. The type of jobs FUTUR has provided these individuals has changed over time. The organization started operating in the textile sector and later shifted its focus entirely to food services. It has also been committed to fair-trade and environmentally-friendly products. FUTUR opened several restaurants and later expanded into catering services and, more recently, to school cafeterias, the latter becoming a very successful venture. They were also ready to launch a new business to supplement these initiatives. It was based on selling organic, fair-trade products on the streets with salespeople riding specially adapted bicycles. However, the organization needed to find new facilities equipped with an industrial kitchen as it had to move from the building it was currently renting for a nominal price. With so many initiatives underway, Manuel Almirall pondered the pros and cons of diversification for an organization like FUTUR and whether it should concentrate on a single venture. Specifically, he wondered what strategy would be more effective to fulfill the organization's mission while maintaining sustainable growth and moving its central kitchen for its restaurants and catering services.
Years | Cash Flow | Net Cash Flow | Cumulative Cash Flow |
Discount Rate @ 6 % |
Discounted Cash Flows |
---|---|---|---|---|---|
Year 0 | (10001637) | -10001637 | - | - | |
Year 1 | 3449636 | -6552001 | 3449636 | 0.9434 | 3254374 |
Year 2 | 3972832 | -2579169 | 7422468 | 0.89 | 3535806 |
Year 3 | 3974740 | 1395571 | 11397208 | 0.8396 | 3337268 |
Year 4 | 3249023 | 4644594 | 14646231 | 0.7921 | 2573531 |
TOTAL | 14646231 | 12700979 |
In isolation the NPV number doesn't mean much but put in right context then it is one of the best method to evaluate project returns. In this article we will cover -
Capital Budgeting Approaches
There are four types of capital budgeting techniques that are widely used in the corporate world –
1. Profitability Index
2. Net Present Value
3. Payback Period
4. Internal Rate of Return
Apart from the Payback period method which is an additive method, rest of the methods are based on
Discounted Cash Flow
technique. Even though cash flow can be calculated based on the nature of the project, for the simplicity of the article we are assuming that all the expected cash flows are realized at the end of the year.
Discounted Cash Flow approaches provide a more objective basis for evaluating and selecting investment projects. They take into consideration both –
1. Magnitude of both incoming and outgoing cash flows – Projects can be capital intensive, time intensive, or both. Futur Barcelona shareholders have preference for diversified projects investment rather than prospective high income from a single capital intensive project.
2. Timing of the expected cash flows – stockholders of Futur Barcelona have higher preference for cash returns over 4-5 years rather than 10-15 years given the nature of the volatility in the industry.
NPV = Net Cash In Flowt1 / (1+r)t1 + Net Cash In Flowt2 / (1+r)t2 + … Net Cash In Flowtn / (1+r)tn
Less Net Cash Out Flowt0 / (1+r)t0
Where t = time period, in this case year 1, year 2 and so on.
r = discount rate or return that could be earned using other safe proposition such as fixed deposit or treasury bond rate.
Net Cash In Flow – What the firm will get each year.
Net Cash Out Flow – What the firm needs to invest initially in the project.
Step 1 – Understand the nature of the project and calculate cash flow for each year.
Step 2 – Discount those cash flow based on the discount rate.
Step 3 – Add all the discounted cash flow.
Step 4 – Selection of the project
In our daily workplace we often come across people and colleagues who are just focused on their core competency and targets they have to deliver. For example marketing managers at Futur Barcelona often design programs whose objective is to drive brand awareness and customer reach. But how that 30 point increase in brand awareness or 10 point increase in customer touch points will result into shareholders’ value is not specified.
To overcome such scenarios managers at Futur Barcelona needs to not only know the financial aspect of project management but also needs to have tools to integrate them into part of the project development and monitoring plan.
After working through various assumptions we reached a conclusion that risk is far higher than 6%. In a reasonably stable industry with weak competition - 15% discount rate can be a good benchmark.
Years | Cash Flow | Net Cash Flow | Cumulative Cash Flow |
Discount Rate @ 15 % |
Discounted Cash Flows |
---|---|---|---|---|---|
Year 0 | (10001637) | -10001637 | - | - | |
Year 1 | 3449636 | -6552001 | 3449636 | 0.8696 | 2999683 |
Year 2 | 3972832 | -2579169 | 7422468 | 0.7561 | 3004032 |
Year 3 | 3974740 | 1395571 | 11397208 | 0.6575 | 2613456 |
Year 4 | 3249023 | 4644594 | 14646231 | 0.5718 | 1857639 |
TOTAL | 10474811 |
(10474811 - 10001637 )
If the risk component is high in the industry then we should go for a higher hurdle rate / discount rate of 20%.
Years | Cash Flow | Net Cash Flow | Cumulative Cash Flow |
Discount Rate @ 20 % |
Discounted Cash Flows |
---|---|---|---|---|---|
Year 0 | (10001637) | -10001637 | - | - | |
Year 1 | 3449636 | -6552001 | 3449636 | 0.8333 | 2874697 |
Year 2 | 3972832 | -2579169 | 7422468 | 0.6944 | 2758911 |
Year 3 | 3974740 | 1395571 | 11397208 | 0.5787 | 2300197 |
Year 4 | 3249023 | 4644594 | 14646231 | 0.4823 | 1566851 |
TOTAL | 9500656 |
At 20% discount rate the NPV is negative (9500656 - 10001637 ) so ideally we can't select the project if macro and micro factors don't allow financial managers of Futur Barcelona to discount cash flow at lower discount rates such as 15%.
Simplest Approach – If the investment project of Futur Barcelona has a NPV value higher than Zero then finance managers at Futur Barcelona can ACCEPT the project, otherwise they can reject the project. This means that project will deliver higher returns over the period of time than any alternate investment strategy.
In theory if the required rate of return or discount rate is chosen correctly by finance managers at Futur Barcelona, then the stock price of the Futur Barcelona should change by same amount of the NPV. In real world we know that share price also reflects various other factors that can be related to both macro and micro environment.
In the same vein – accepting the project with zero NPV should result in stagnant share price. Finance managers use discount rates as a measure of risk components in the project execution process.
Project selection is often a far more complex decision than just choosing it based on the NPV number. Finance managers at Futur Barcelona should conduct a sensitivity analysis to better understand not only the inherent risk of the projects but also how those risks can be either factored in or mitigated during the project execution. Sensitivity analysis helps in –
Understanding of risks involved in the project.
What will be a multi year spillover effect of various taxation regulations.
What are the key aspects of the projects that need to be monitored, refined, and retuned for continuous delivery of projected cash flows.
What are the uncertainties surrounding the project Initial Cash Outlay (ICO’s). ICO’s often have several different components such as land, machinery, building, and other equipment.
What can impact the cash flow of the project.
Projects are assumed to be Mutually Exclusive – This is seldom the came in modern day giant organizations where projects are often inter-related and rejecting a project solely based on NPV can result in sunk cost from a related project.
Independent projects have independent cash flows – As explained in the marketing project – though the project may look independent but in reality it is not as the brand awareness project can be closely associated with the spending on sales promotions and product specific advertising.
Daniel Arenas, Alfred Vernis (2018), "FUTUR-Working towards Social Inclusion, Spanish Version Harvard Business Review Case Study. Published by HBR Publications.
Feel free to connect with us if you need business research.
You can download Excel Template of Case Study Solution & Analysis of FUTUR-Working towards Social Inclusion, Spanish Version
Financial , Regional Banks
Technology , Electronic Instr. & Controls
Services , Casinos & Gaming
Services , Retail (Apparel)
Services , Advertising
Basic Materials , Gold & Silver
Consumer/Non-Cyclical , Beverages (Alcoholic)
Financial , Investment Services
Services , Real Estate Operations
Financial , Consumer Financial Services
Consumer Cyclical , Auto & Truck Manufacturers