Positioning Southwest Airlines Through Employee Branding Net Present Value (NPV) / MBA Resources

Introduction to Net Present Value (NPV) - What is Net Present Value (NPV) ? How it impacts financial decisions regarding project management?

NPV solution for Positioning Southwest Airlines Through Employee Branding case study


At Oak Spring University, we provide corporate level professional Net Present Value (NPV) case study solution. Positioning Southwest Airlines Through Employee Branding case study is a Harvard Business School (HBR) case study written by Sandra Jeanquart Miles, W. Glynn Mangold. The Positioning Southwest Airlines Through Employee Branding (referred as “Branding Southwest” from here on) case study provides evaluation & decision scenario in field of Organizational Development. It also touches upon business topics such as - Value proposition, Competitive strategy, Psychology.

The net present value (NPV) of an investment proposal is the present value of the proposal’s net cash flows less the proposal’s initial cash outflow. If a project’s NPV is greater than or equal to zero, the project should be accepted.

NPV = Present Value of Future Cash Flows LESS Project’s Initial Investment






Case Description of Positioning Southwest Airlines Through Employee Branding Case Study


As the field of employee branding has begun to unfold, more and more executives have become interested in how this process can help them achieve a competitive advantage for their organizations. Explains how employee branding works and how it can be utilized to position the organization in the minds of customers, employees, and other stakeholders. Presents a contextual analysis of its use as a source of sustainable competitive advantage at Southwest Airlines. Also, identifies key success factors.


Case Authors : Sandra Jeanquart Miles, W. Glynn Mangold

Topic : Organizational Development

Related Areas : Competitive strategy, Psychology




Calculating Net Present Value (NPV) at 6% for Positioning Southwest Airlines Through Employee Branding Case Study


Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 6 %
Discounted
Cash Flows
Year 0 (10010159) -10010159 - -
Year 1 3465075 -6545084 3465075 0.9434 3268939
Year 2 3975122 -2569962 7440197 0.89 3537844
Year 3 3948742 1378780 11388939 0.8396 3315440
Year 4 3225399 4604179 14614338 0.7921 2554818
TOTAL 14614338 12677041




The Net Present Value at 6% discount rate is 2666882

In isolation the NPV number doesn't mean much but put in right context then it is one of the best method to evaluate project returns. In this article we will cover -

Different methods of capital budgeting


What is NPV & Formula of NPV,
How it is calculated,
How to use NPV number for project evaluation, and
Scenario Planning given risks and management priorities.




Capital Budgeting Approaches

Methods of Capital Budgeting


There are four types of capital budgeting techniques that are widely used in the corporate world –

1. Internal Rate of Return
2. Profitability Index
3. Net Present Value
4. Payback Period

Apart from the Payback period method which is an additive method, rest of the methods are based on Discounted Cash Flow technique. Even though cash flow can be calculated based on the nature of the project, for the simplicity of the article we are assuming that all the expected cash flows are realized at the end of the year.

Discounted Cash Flow approaches provide a more objective basis for evaluating and selecting investment projects. They take into consideration both –

1. Magnitude of both incoming and outgoing cash flows – Projects can be capital intensive, time intensive, or both. Branding Southwest shareholders have preference for diversified projects investment rather than prospective high income from a single capital intensive project.
2. Timing of the expected cash flows – stockholders of Branding Southwest have higher preference for cash returns over 4-5 years rather than 10-15 years given the nature of the volatility in the industry.






Formula and Steps to Calculate Net Present Value (NPV) of Positioning Southwest Airlines Through Employee Branding

NPV = Net Cash In Flowt1 / (1+r)t1 + Net Cash In Flowt2 / (1+r)t2 + … Net Cash In Flowtn / (1+r)tn
Less Net Cash Out Flowt0 / (1+r)t0

Where t = time period, in this case year 1, year 2 and so on.
r = discount rate or return that could be earned using other safe proposition such as fixed deposit or treasury bond rate. Net Cash In Flow – What the firm will get each year.
Net Cash Out Flow – What the firm needs to invest initially in the project.

Step 1 – Understand the nature of the project and calculate cash flow for each year.
Step 2 – Discount those cash flow based on the discount rate.
Step 3 – Add all the discounted cash flow.
Step 4 – Selection of the project

Why Organizational Development Managers need to know Financial Tools such as Net Present Value (NPV)?

In our daily workplace we often come across people and colleagues who are just focused on their core competency and targets they have to deliver. For example marketing managers at Branding Southwest often design programs whose objective is to drive brand awareness and customer reach. But how that 30 point increase in brand awareness or 10 point increase in customer touch points will result into shareholders’ value is not specified.

To overcome such scenarios managers at Branding Southwest needs to not only know the financial aspect of project management but also needs to have tools to integrate them into part of the project development and monitoring plan.

Calculating Net Present Value (NPV) at 15%

After working through various assumptions we reached a conclusion that risk is far higher than 6%. In a reasonably stable industry with weak competition - 15% discount rate can be a good benchmark.



Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 15 %
Discounted
Cash Flows
Year 0 (10010159) -10010159 - -
Year 1 3465075 -6545084 3465075 0.8696 3013109
Year 2 3975122 -2569962 7440197 0.7561 3005763
Year 3 3948742 1378780 11388939 0.6575 2596362
Year 4 3225399 4604179 14614338 0.5718 1844132
TOTAL 10459366


The Net NPV after 4 years is 449207

(10459366 - 10010159 )








Calculating Net Present Value (NPV) at 20%


If the risk component is high in the industry then we should go for a higher hurdle rate / discount rate of 20%.

Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 20 %
Discounted
Cash Flows
Year 0 (10010159) -10010159 - -
Year 1 3465075 -6545084 3465075 0.8333 2887563
Year 2 3975122 -2569962 7440197 0.6944 2760501
Year 3 3948742 1378780 11388939 0.5787 2285152
Year 4 3225399 4604179 14614338 0.4823 1555459
TOTAL 9488674


The Net NPV after 4 years is -521485

At 20% discount rate the NPV is negative (9488674 - 10010159 ) so ideally we can't select the project if macro and micro factors don't allow financial managers of Branding Southwest to discount cash flow at lower discount rates such as 15%.





Acceptance Criteria of a Project based on NPV

Simplest Approach – If the investment project of Branding Southwest has a NPV value higher than Zero then finance managers at Branding Southwest can ACCEPT the project, otherwise they can reject the project. This means that project will deliver higher returns over the period of time than any alternate investment strategy.

In theory if the required rate of return or discount rate is chosen correctly by finance managers at Branding Southwest, then the stock price of the Branding Southwest should change by same amount of the NPV. In real world we know that share price also reflects various other factors that can be related to both macro and micro environment.

In the same vein – accepting the project with zero NPV should result in stagnant share price. Finance managers use discount rates as a measure of risk components in the project execution process.

Sensitivity Analysis

Project selection is often a far more complex decision than just choosing it based on the NPV number. Finance managers at Branding Southwest should conduct a sensitivity analysis to better understand not only the inherent risk of the projects but also how those risks can be either factored in or mitigated during the project execution. Sensitivity analysis helps in –

What are the key aspects of the projects that need to be monitored, refined, and retuned for continuous delivery of projected cash flows.

What will be a multi year spillover effect of various taxation regulations.

What can impact the cash flow of the project.

Understanding of risks involved in the project.

What are the uncertainties surrounding the project Initial Cash Outlay (ICO’s). ICO’s often have several different components such as land, machinery, building, and other equipment.

Some of the assumptions while using the Discounted Cash Flow Methods –

Projects are assumed to be Mutually Exclusive – This is seldom the came in modern day giant organizations where projects are often inter-related and rejecting a project solely based on NPV can result in sunk cost from a related project.

Independent projects have independent cash flows – As explained in the marketing project – though the project may look independent but in reality it is not as the brand awareness project can be closely associated with the spending on sales promotions and product specific advertising.






Negotiation Strategy of Positioning Southwest Airlines Through Employee Branding

References & Further Readings

Sandra Jeanquart Miles, W. Glynn Mangold (2018), "Positioning Southwest Airlines Through Employee Branding Harvard Business Review Case Study. Published by HBR Publications.


CAR Inc SWOT Analysis / TOWS Matrix

Services , Rental & Leasing


Unet Credit Finance SWOT Analysis / TOWS Matrix

Financial , Consumer Financial Services


Wangfujing SWOT Analysis / TOWS Matrix

Services , Retail (Department & Discount)


Shapir Engineering Industry SWOT Analysis / TOWS Matrix

Capital Goods , Construction - Raw Materials


Haynes SWOT Analysis / TOWS Matrix

Basic Materials , Iron & Steel


AvalonBay SWOT Analysis / TOWS Matrix

Services , Real Estate Operations


Kroger SWOT Analysis / TOWS Matrix

Services , Retail (Grocery)


DPS Resources SWOT Analysis / TOWS Matrix

Capital Goods , Constr. - Supplies & Fixtures


Topdanmark A/S SWOT Analysis / TOWS Matrix

Financial , Insurance (Prop. & Casualty)


Huayu Expressway SWOT Analysis / TOWS Matrix

Transportation , Misc. Transportation


Minsheng Invest A SWOT Analysis / TOWS Matrix

Services , Retail (Department & Discount)


Cityldg SWOT Analysis / TOWS Matrix

Services , Hotels & Motels