Erik Peterson (C) Net Present Value (NPV) / MBA Resources

Introduction to Net Present Value (NPV) - What is Net Present Value (NPV) ? How it impacts financial decisions regarding project management?

NPV solution for Erik Peterson (C) case study


At Oak Spring University, we provide corporate level professional Net Present Value (NPV) case study solution. Erik Peterson (C) case study is a Harvard Business School (HBR) case study written by John J. Gabarro. The Erik Peterson (C) (referred as “Erik Peterson's” from here on) case study provides evaluation & decision scenario in field of Organizational Development. It also touches upon business topics such as - Value proposition, Leadership, Operations management, Organizational culture, Organizational structure.

The net present value (NPV) of an investment proposal is the present value of the proposal’s net cash flows less the proposal’s initial cash outflow. If a project’s NPV is greater than or equal to zero, the project should be accepted.

NPV = Present Value of Future Cash Flows LESS Project’s Initial Investment






Case Description of Erik Peterson (C) Case Study


Describes the outcome of Erik Peterson's one-day meeting with his superior and the events of the subsequent day's meeting with the president and vice president of operations of the parent company. Students should have read the (A) and (B) cases. The (C) case may be assigned with the (D) case. A redisguised version of an earlier case.


Case Authors : John J. Gabarro

Topic : Organizational Development

Related Areas : Leadership, Operations management, Organizational culture, Organizational structure




Calculating Net Present Value (NPV) at 6% for Erik Peterson (C) Case Study


Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 6 %
Discounted
Cash Flows
Year 0 (10003591) -10003591 - -
Year 1 3454957 -6548634 3454957 0.9434 3259393
Year 2 3974876 -2573758 7429833 0.89 3537625
Year 3 3952338 1378580 11382171 0.8396 3318459
Year 4 3239219 4617799 14621390 0.7921 2565765
TOTAL 14621390 12681243




The Net Present Value at 6% discount rate is 2677652

In isolation the NPV number doesn't mean much but put in right context then it is one of the best method to evaluate project returns. In this article we will cover -

Different methods of capital budgeting


What is NPV & Formula of NPV,
How it is calculated,
How to use NPV number for project evaluation, and
Scenario Planning given risks and management priorities.




Capital Budgeting Approaches

Methods of Capital Budgeting


There are four types of capital budgeting techniques that are widely used in the corporate world –

1. Internal Rate of Return
2. Net Present Value
3. Payback Period
4. Profitability Index

Apart from the Payback period method which is an additive method, rest of the methods are based on Discounted Cash Flow technique. Even though cash flow can be calculated based on the nature of the project, for the simplicity of the article we are assuming that all the expected cash flows are realized at the end of the year.

Discounted Cash Flow approaches provide a more objective basis for evaluating and selecting investment projects. They take into consideration both –

1. Timing of the expected cash flows – stockholders of Erik Peterson's have higher preference for cash returns over 4-5 years rather than 10-15 years given the nature of the volatility in the industry.
2. Magnitude of both incoming and outgoing cash flows – Projects can be capital intensive, time intensive, or both. Erik Peterson's shareholders have preference for diversified projects investment rather than prospective high income from a single capital intensive project.






Formula and Steps to Calculate Net Present Value (NPV) of Erik Peterson (C)

NPV = Net Cash In Flowt1 / (1+r)t1 + Net Cash In Flowt2 / (1+r)t2 + … Net Cash In Flowtn / (1+r)tn
Less Net Cash Out Flowt0 / (1+r)t0

Where t = time period, in this case year 1, year 2 and so on.
r = discount rate or return that could be earned using other safe proposition such as fixed deposit or treasury bond rate. Net Cash In Flow – What the firm will get each year.
Net Cash Out Flow – What the firm needs to invest initially in the project.

Step 1 – Understand the nature of the project and calculate cash flow for each year.
Step 2 – Discount those cash flow based on the discount rate.
Step 3 – Add all the discounted cash flow.
Step 4 – Selection of the project

Why Organizational Development Managers need to know Financial Tools such as Net Present Value (NPV)?

In our daily workplace we often come across people and colleagues who are just focused on their core competency and targets they have to deliver. For example marketing managers at Erik Peterson's often design programs whose objective is to drive brand awareness and customer reach. But how that 30 point increase in brand awareness or 10 point increase in customer touch points will result into shareholders’ value is not specified.

To overcome such scenarios managers at Erik Peterson's needs to not only know the financial aspect of project management but also needs to have tools to integrate them into part of the project development and monitoring plan.

Calculating Net Present Value (NPV) at 15%

After working through various assumptions we reached a conclusion that risk is far higher than 6%. In a reasonably stable industry with weak competition - 15% discount rate can be a good benchmark.



Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 15 %
Discounted
Cash Flows
Year 0 (10003591) -10003591 - -
Year 1 3454957 -6548634 3454957 0.8696 3004310
Year 2 3974876 -2573758 7429833 0.7561 3005577
Year 3 3952338 1378580 11382171 0.6575 2598726
Year 4 3239219 4617799 14621390 0.5718 1852034
TOTAL 10460648


The Net NPV after 4 years is 457057

(10460648 - 10003591 )








Calculating Net Present Value (NPV) at 20%


If the risk component is high in the industry then we should go for a higher hurdle rate / discount rate of 20%.

Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 20 %
Discounted
Cash Flows
Year 0 (10003591) -10003591 - -
Year 1 3454957 -6548634 3454957 0.8333 2879131
Year 2 3974876 -2573758 7429833 0.6944 2760331
Year 3 3952338 1378580 11382171 0.5787 2287233
Year 4 3239219 4617799 14621390 0.4823 1562123
TOTAL 9488817


The Net NPV after 4 years is -514774

At 20% discount rate the NPV is negative (9488817 - 10003591 ) so ideally we can't select the project if macro and micro factors don't allow financial managers of Erik Peterson's to discount cash flow at lower discount rates such as 15%.





Acceptance Criteria of a Project based on NPV

Simplest Approach – If the investment project of Erik Peterson's has a NPV value higher than Zero then finance managers at Erik Peterson's can ACCEPT the project, otherwise they can reject the project. This means that project will deliver higher returns over the period of time than any alternate investment strategy.

In theory if the required rate of return or discount rate is chosen correctly by finance managers at Erik Peterson's, then the stock price of the Erik Peterson's should change by same amount of the NPV. In real world we know that share price also reflects various other factors that can be related to both macro and micro environment.

In the same vein – accepting the project with zero NPV should result in stagnant share price. Finance managers use discount rates as a measure of risk components in the project execution process.

Sensitivity Analysis

Project selection is often a far more complex decision than just choosing it based on the NPV number. Finance managers at Erik Peterson's should conduct a sensitivity analysis to better understand not only the inherent risk of the projects but also how those risks can be either factored in or mitigated during the project execution. Sensitivity analysis helps in –

Understanding of risks involved in the project.

What are the key aspects of the projects that need to be monitored, refined, and retuned for continuous delivery of projected cash flows.

What are the uncertainties surrounding the project Initial Cash Outlay (ICO’s). ICO’s often have several different components such as land, machinery, building, and other equipment.

What can impact the cash flow of the project.

What will be a multi year spillover effect of various taxation regulations.

Some of the assumptions while using the Discounted Cash Flow Methods –

Projects are assumed to be Mutually Exclusive – This is seldom the came in modern day giant organizations where projects are often inter-related and rejecting a project solely based on NPV can result in sunk cost from a related project.

Independent projects have independent cash flows – As explained in the marketing project – though the project may look independent but in reality it is not as the brand awareness project can be closely associated with the spending on sales promotions and product specific advertising.






Negotiation Strategy of Erik Peterson (C)

References & Further Readings

John J. Gabarro (2018), "Erik Peterson (C) Harvard Business Review Case Study. Published by HBR Publications.


Media Nusantara Citra SWOT Analysis / TOWS Matrix

Services , Broadcasting & Cable TV


Carlsberg Brewery SWOT Analysis / TOWS Matrix

Consumer/Non-Cyclical , Beverages (Alcoholic)


Value&Income SWOT Analysis / TOWS Matrix

Financial , Misc. Financial Services


Capro SWOT Analysis / TOWS Matrix

Basic Materials , Chemical Manufacturing


BioSpecifics SWOT Analysis / TOWS Matrix

Healthcare , Biotechnology & Drugs


Mail.ru Group SWOT Analysis / TOWS Matrix

Technology , Computer Services


China GengSheng Minerals SWOT Analysis / TOWS Matrix

Capital Goods , Constr. - Supplies & Fixtures


Afterpay Touch SWOT Analysis / TOWS Matrix

Financial , Consumer Financial Services