Cape Wind Net Present Value (NPV) / MBA Resources

Introduction to Net Present Value (NPV) - What is Net Present Value (NPV) ? How it impacts financial decisions regarding project management?

NPV solution for Cape Wind case study


At Oak Spring University, we provide corporate level professional Net Present Value (NPV) case study solution. Cape Wind case study is a Harvard Business School (HBR) case study written by John T. Gourville, Kerry Herman. The Cape Wind (referred as “Wind Farm” from here on) case study provides evaluation & decision scenario in field of Sales & Marketing. It also touches upon business topics such as - Value proposition, Customers, Innovation, Public relations, Sustainability.

The net present value (NPV) of an investment proposal is the present value of the proposal’s net cash flows less the proposal’s initial cash outflow. If a project’s NPV is greater than or equal to zero, the project should be accepted.

NPV = Present Value of Future Cash Flows LESS Project’s Initial Investment






Case Description of Cape Wind Case Study


This case is available in only hard copy format (HBP does not have digital distribution rights to the content). As a result, a digital Educator Copy of the case is not available through this web site.Cape Wind has proposed placing a 170-tower wind farm, with each tower more than 400-feet tall, in Nantucket Sound. Not surprisingly, public reaction is mixed. Some view the wind farm as clean, renewable energy. Others view it as an eyesore and a desecration of a valued public resource. Other attempts at wind farms in the United States have run into similar resistance. Although the public can agree that wind power is a good idea, no one wants a wind farm in their community. How can firms overcome this type of resistance to change?


Case Authors : John T. Gourville, Kerry Herman

Topic : Sales & Marketing

Related Areas : Customers, Innovation, Public relations, Sustainability




Calculating Net Present Value (NPV) at 6% for Cape Wind Case Study


Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 6 %
Discounted
Cash Flows
Year 0 (10016351) -10016351 - -
Year 1 3466618 -6549733 3466618 0.9434 3270394
Year 2 3954340 -2595393 7420958 0.89 3519349
Year 3 3941630 1346237 11362588 0.8396 3309469
Year 4 3245630 4591867 14608218 0.7921 2570843
TOTAL 14608218 12670054




The Net Present Value at 6% discount rate is 2653703

In isolation the NPV number doesn't mean much but put in right context then it is one of the best method to evaluate project returns. In this article we will cover -

Different methods of capital budgeting


What is NPV & Formula of NPV,
How it is calculated,
How to use NPV number for project evaluation, and
Scenario Planning given risks and management priorities.




Capital Budgeting Approaches

Methods of Capital Budgeting


There are four types of capital budgeting techniques that are widely used in the corporate world –

1. Payback Period
2. Net Present Value
3. Internal Rate of Return
4. Profitability Index

Apart from the Payback period method which is an additive method, rest of the methods are based on Discounted Cash Flow technique. Even though cash flow can be calculated based on the nature of the project, for the simplicity of the article we are assuming that all the expected cash flows are realized at the end of the year.

Discounted Cash Flow approaches provide a more objective basis for evaluating and selecting investment projects. They take into consideration both –

1. Timing of the expected cash flows – stockholders of Wind Farm have higher preference for cash returns over 4-5 years rather than 10-15 years given the nature of the volatility in the industry.
2. Magnitude of both incoming and outgoing cash flows – Projects can be capital intensive, time intensive, or both. Wind Farm shareholders have preference for diversified projects investment rather than prospective high income from a single capital intensive project.






Formula and Steps to Calculate Net Present Value (NPV) of Cape Wind

NPV = Net Cash In Flowt1 / (1+r)t1 + Net Cash In Flowt2 / (1+r)t2 + … Net Cash In Flowtn / (1+r)tn
Less Net Cash Out Flowt0 / (1+r)t0

Where t = time period, in this case year 1, year 2 and so on.
r = discount rate or return that could be earned using other safe proposition such as fixed deposit or treasury bond rate. Net Cash In Flow – What the firm will get each year.
Net Cash Out Flow – What the firm needs to invest initially in the project.

Step 1 – Understand the nature of the project and calculate cash flow for each year.
Step 2 – Discount those cash flow based on the discount rate.
Step 3 – Add all the discounted cash flow.
Step 4 – Selection of the project

Why Sales & Marketing Managers need to know Financial Tools such as Net Present Value (NPV)?

In our daily workplace we often come across people and colleagues who are just focused on their core competency and targets they have to deliver. For example marketing managers at Wind Farm often design programs whose objective is to drive brand awareness and customer reach. But how that 30 point increase in brand awareness or 10 point increase in customer touch points will result into shareholders’ value is not specified.

To overcome such scenarios managers at Wind Farm needs to not only know the financial aspect of project management but also needs to have tools to integrate them into part of the project development and monitoring plan.

Calculating Net Present Value (NPV) at 15%

After working through various assumptions we reached a conclusion that risk is far higher than 6%. In a reasonably stable industry with weak competition - 15% discount rate can be a good benchmark.



Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 15 %
Discounted
Cash Flows
Year 0 (10016351) -10016351 - -
Year 1 3466618 -6549733 3466618 0.8696 3014450
Year 2 3954340 -2595393 7420958 0.7561 2990049
Year 3 3941630 1346237 11362588 0.6575 2591686
Year 4 3245630 4591867 14608218 0.5718 1855699
TOTAL 10451885


The Net NPV after 4 years is 435534

(10451885 - 10016351 )








Calculating Net Present Value (NPV) at 20%


If the risk component is high in the industry then we should go for a higher hurdle rate / discount rate of 20%.

Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 20 %
Discounted
Cash Flows
Year 0 (10016351) -10016351 - -
Year 1 3466618 -6549733 3466618 0.8333 2888848
Year 2 3954340 -2595393 7420958 0.6944 2746069
Year 3 3941630 1346237 11362588 0.5787 2281036
Year 4 3245630 4591867 14608218 0.4823 1565215
TOTAL 9481169


The Net NPV after 4 years is -535182

At 20% discount rate the NPV is negative (9481169 - 10016351 ) so ideally we can't select the project if macro and micro factors don't allow financial managers of Wind Farm to discount cash flow at lower discount rates such as 15%.





Acceptance Criteria of a Project based on NPV

Simplest Approach – If the investment project of Wind Farm has a NPV value higher than Zero then finance managers at Wind Farm can ACCEPT the project, otherwise they can reject the project. This means that project will deliver higher returns over the period of time than any alternate investment strategy.

In theory if the required rate of return or discount rate is chosen correctly by finance managers at Wind Farm, then the stock price of the Wind Farm should change by same amount of the NPV. In real world we know that share price also reflects various other factors that can be related to both macro and micro environment.

In the same vein – accepting the project with zero NPV should result in stagnant share price. Finance managers use discount rates as a measure of risk components in the project execution process.

Sensitivity Analysis

Project selection is often a far more complex decision than just choosing it based on the NPV number. Finance managers at Wind Farm should conduct a sensitivity analysis to better understand not only the inherent risk of the projects but also how those risks can be either factored in or mitigated during the project execution. Sensitivity analysis helps in –

What can impact the cash flow of the project.

What are the key aspects of the projects that need to be monitored, refined, and retuned for continuous delivery of projected cash flows.

What are the uncertainties surrounding the project Initial Cash Outlay (ICO’s). ICO’s often have several different components such as land, machinery, building, and other equipment.

Understanding of risks involved in the project.

What will be a multi year spillover effect of various taxation regulations.

Some of the assumptions while using the Discounted Cash Flow Methods –

Projects are assumed to be Mutually Exclusive – This is seldom the came in modern day giant organizations where projects are often inter-related and rejecting a project solely based on NPV can result in sunk cost from a related project.

Independent projects have independent cash flows – As explained in the marketing project – though the project may look independent but in reality it is not as the brand awareness project can be closely associated with the spending on sales promotions and product specific advertising.






Negotiation Strategy of Cape Wind

References & Further Readings

John T. Gourville, Kerry Herman (2018), "Cape Wind Harvard Business Review Case Study. Published by HBR Publications.


Yunnan Metropolitan SWOT Analysis / TOWS Matrix

Capital Goods , Construction Services


Sagami Rubber Industries SWOT Analysis / TOWS Matrix

Consumer/Non-Cyclical , Personal & Household Prods.


Korea Eng Cons SWOT Analysis / TOWS Matrix

Capital Goods , Construction Services


Top Global Ltd SWOT Analysis / TOWS Matrix

Services , Real Estate Operations


Milacron Holdings Corp SWOT Analysis / TOWS Matrix

Capital Goods , Misc. Capital Goods


Tongyang Life SWOT Analysis / TOWS Matrix

Financial , Insurance (Life)


Tai Cheung SWOT Analysis / TOWS Matrix

Capital Goods , Construction Services


Funtastic SWOT Analysis / TOWS Matrix

Consumer Cyclical , Recreational Products


Summit Securities Ltd SWOT Analysis / TOWS Matrix

Financial , Consumer Financial Services