GOME Electrical Appliances Holding Limited: The "Tuangou" Challenge Net Present Value (NPV) / MBA Resources

Introduction to Net Present Value (NPV) - What is Net Present Value (NPV) ? How it impacts financial decisions regarding project management?

NPV solution for GOME Electrical Appliances Holding Limited: The "Tuangou" Challenge case study


At Oak Spring University, we provide corporate level professional Net Present Value (NPV) case study solution. GOME Electrical Appliances Holding Limited: The "Tuangou" Challenge case study is a Harvard Business School (HBR) case study written by Benjamin Yen, Andrew Lee. The GOME Electrical Appliances Holding Limited: The "Tuangou" Challenge (referred as “Gome Tuangou” from here on) case study provides evaluation & decision scenario in field of Sales & Marketing. It also touches upon business topics such as - Value proposition, Supply chain.

The net present value (NPV) of an investment proposal is the present value of the proposal’s net cash flows less the proposal’s initial cash outflow. If a project’s NPV is greater than or equal to zero, the project should be accepted.

NPV = Present Value of Future Cash Flows LESS Project’s Initial Investment






Case Description of GOME Electrical Appliances Holding Limited: The "Tuangou" Challenge Case Study


GOME, founded by Wong Kwongyu, had grown from merely a 100-square-metre store in Beijing in 1987 to the industry leader in electrical and home appliance retailing in China, with 259 traditional stores and 4 digital stores by 2006. Its success stemmed from its low-margin, high-volume strategy, which was complemented by its striving for service quality and innovation. In 2006, GOME faced the new challenge of tuangou, or group purchase. In order to amass bargaining power to demand discounts from retailers, consumers with similar needs in China united through the Internet and showed up en masse at retailers at pre-arranged times and dates. They would put relentless pressure on retailers and would press for greater discounts. This emerging consumer behavior had spread like wildfire in China and retailers had different reactions. Some yielded to the pressure and offered greater discounts, some only entertained tuangou that had been pre-arranged and/or pre-registered, while others refused to give in and maintained a fixed-price policy. It was up to GOME to determine how best it could deal with this new phenomenon.


Case Authors : Benjamin Yen, Andrew Lee

Topic : Sales & Marketing

Related Areas : Supply chain




Calculating Net Present Value (NPV) at 6% for GOME Electrical Appliances Holding Limited: The "Tuangou" Challenge Case Study


Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 6 %
Discounted
Cash Flows
Year 0 (10029134) -10029134 - -
Year 1 3468383 -6560751 3468383 0.9434 3272059
Year 2 3954947 -2605804 7423330 0.89 3519889
Year 3 3957189 1351385 11380519 0.8396 3322532
Year 4 3224193 4575578 14604712 0.7921 2553863
TOTAL 14604712 12668343




The Net Present Value at 6% discount rate is 2639209

In isolation the NPV number doesn't mean much but put in right context then it is one of the best method to evaluate project returns. In this article we will cover -

Different methods of capital budgeting


What is NPV & Formula of NPV,
How it is calculated,
How to use NPV number for project evaluation, and
Scenario Planning given risks and management priorities.




Capital Budgeting Approaches

Methods of Capital Budgeting


There are four types of capital budgeting techniques that are widely used in the corporate world –

1. Internal Rate of Return
2. Profitability Index
3. Net Present Value
4. Payback Period

Apart from the Payback period method which is an additive method, rest of the methods are based on Discounted Cash Flow technique. Even though cash flow can be calculated based on the nature of the project, for the simplicity of the article we are assuming that all the expected cash flows are realized at the end of the year.

Discounted Cash Flow approaches provide a more objective basis for evaluating and selecting investment projects. They take into consideration both –

1. Magnitude of both incoming and outgoing cash flows – Projects can be capital intensive, time intensive, or both. Gome Tuangou shareholders have preference for diversified projects investment rather than prospective high income from a single capital intensive project.
2. Timing of the expected cash flows – stockholders of Gome Tuangou have higher preference for cash returns over 4-5 years rather than 10-15 years given the nature of the volatility in the industry.






Formula and Steps to Calculate Net Present Value (NPV) of GOME Electrical Appliances Holding Limited: The "Tuangou" Challenge

NPV = Net Cash In Flowt1 / (1+r)t1 + Net Cash In Flowt2 / (1+r)t2 + … Net Cash In Flowtn / (1+r)tn
Less Net Cash Out Flowt0 / (1+r)t0

Where t = time period, in this case year 1, year 2 and so on.
r = discount rate or return that could be earned using other safe proposition such as fixed deposit or treasury bond rate. Net Cash In Flow – What the firm will get each year.
Net Cash Out Flow – What the firm needs to invest initially in the project.

Step 1 – Understand the nature of the project and calculate cash flow for each year.
Step 2 – Discount those cash flow based on the discount rate.
Step 3 – Add all the discounted cash flow.
Step 4 – Selection of the project

Why Sales & Marketing Managers need to know Financial Tools such as Net Present Value (NPV)?

In our daily workplace we often come across people and colleagues who are just focused on their core competency and targets they have to deliver. For example marketing managers at Gome Tuangou often design programs whose objective is to drive brand awareness and customer reach. But how that 30 point increase in brand awareness or 10 point increase in customer touch points will result into shareholders’ value is not specified.

To overcome such scenarios managers at Gome Tuangou needs to not only know the financial aspect of project management but also needs to have tools to integrate them into part of the project development and monitoring plan.

Calculating Net Present Value (NPV) at 15%

After working through various assumptions we reached a conclusion that risk is far higher than 6%. In a reasonably stable industry with weak competition - 15% discount rate can be a good benchmark.



Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 15 %
Discounted
Cash Flows
Year 0 (10029134) -10029134 - -
Year 1 3468383 -6560751 3468383 0.8696 3015985
Year 2 3954947 -2605804 7423330 0.7561 2990508
Year 3 3957189 1351385 11380519 0.6575 2601916
Year 4 3224193 4575578 14604712 0.5718 1843443
TOTAL 10451852


The Net NPV after 4 years is 422718

(10451852 - 10029134 )








Calculating Net Present Value (NPV) at 20%


If the risk component is high in the industry then we should go for a higher hurdle rate / discount rate of 20%.

Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 20 %
Discounted
Cash Flows
Year 0 (10029134) -10029134 - -
Year 1 3468383 -6560751 3468383 0.8333 2890319
Year 2 3954947 -2605804 7423330 0.6944 2746491
Year 3 3957189 1351385 11380519 0.5787 2290040
Year 4 3224193 4575578 14604712 0.4823 1554877
TOTAL 9481727


The Net NPV after 4 years is -547407

At 20% discount rate the NPV is negative (9481727 - 10029134 ) so ideally we can't select the project if macro and micro factors don't allow financial managers of Gome Tuangou to discount cash flow at lower discount rates such as 15%.





Acceptance Criteria of a Project based on NPV

Simplest Approach – If the investment project of Gome Tuangou has a NPV value higher than Zero then finance managers at Gome Tuangou can ACCEPT the project, otherwise they can reject the project. This means that project will deliver higher returns over the period of time than any alternate investment strategy.

In theory if the required rate of return or discount rate is chosen correctly by finance managers at Gome Tuangou, then the stock price of the Gome Tuangou should change by same amount of the NPV. In real world we know that share price also reflects various other factors that can be related to both macro and micro environment.

In the same vein – accepting the project with zero NPV should result in stagnant share price. Finance managers use discount rates as a measure of risk components in the project execution process.

Sensitivity Analysis

Project selection is often a far more complex decision than just choosing it based on the NPV number. Finance managers at Gome Tuangou should conduct a sensitivity analysis to better understand not only the inherent risk of the projects but also how those risks can be either factored in or mitigated during the project execution. Sensitivity analysis helps in –

What will be a multi year spillover effect of various taxation regulations.

What can impact the cash flow of the project.

What are the uncertainties surrounding the project Initial Cash Outlay (ICO’s). ICO’s often have several different components such as land, machinery, building, and other equipment.

Understanding of risks involved in the project.

What are the key aspects of the projects that need to be monitored, refined, and retuned for continuous delivery of projected cash flows.

Some of the assumptions while using the Discounted Cash Flow Methods –

Projects are assumed to be Mutually Exclusive – This is seldom the came in modern day giant organizations where projects are often inter-related and rejecting a project solely based on NPV can result in sunk cost from a related project.

Independent projects have independent cash flows – As explained in the marketing project – though the project may look independent but in reality it is not as the brand awareness project can be closely associated with the spending on sales promotions and product specific advertising.






Negotiation Strategy of GOME Electrical Appliances Holding Limited: The "Tuangou" Challenge

References & Further Readings

Benjamin Yen, Andrew Lee (2018), "GOME Electrical Appliances Holding Limited: The "Tuangou" Challenge Harvard Business Review Case Study. Published by HBR Publications.


Intertape Polymer SWOT Analysis / TOWS Matrix

Basic Materials , Containers & Packaging


Regency Mines SWOT Analysis / TOWS Matrix

Basic Materials , Metal Mining


Haier Electronics SWOT Analysis / TOWS Matrix

Consumer Cyclical , Appliance & Tool


Wonderla Holidays Ltd SWOT Analysis / TOWS Matrix

Services , Recreational Activities


Simba Energy SWOT Analysis / TOWS Matrix

Energy , Oil & Gas Operations


Tong Ren Tang Tech SWOT Analysis / TOWS Matrix

Healthcare , Biotechnology & Drugs


Stefstock SWOT Analysis / TOWS Matrix

Capital Goods , Construction Services


ADTechnology SWOT Analysis / TOWS Matrix

Technology , Semiconductors