Hewlett-Packard: Manufacturing Productivity Division (A) Net Present Value (NPV) / MBA Resources

Introduction to Net Present Value (NPV) - What is Net Present Value (NPV) ? How it impacts financial decisions regarding project management?

NPV solution for Hewlett-Packard: Manufacturing Productivity Division (A) case study


At Oak Spring University, we provide corporate level professional Net Present Value (NPV) case study solution. Hewlett-Packard: Manufacturing Productivity Division (A) case study is a Harvard Business School (HBR) case study written by Benson P. Shapiro, Lawrence B. Levine. The Hewlett-Packard: Manufacturing Productivity Division (A) (referred as “Mpd Productivity” from here on) case study provides evaluation & decision scenario in field of Sales & Marketing. It also touches upon business topics such as - Value proposition, Organizational culture, Product development, Technology.

The net present value (NPV) of an investment proposal is the present value of the proposal’s net cash flows less the proposal’s initial cash outflow. If a project’s NPV is greater than or equal to zero, the project should be accepted.

NPV = Present Value of Future Cash Flows LESS Project’s Initial Investment






Case Description of Hewlett-Packard: Manufacturing Productivity Division (A) Case Study


In late summer 1986, the management of the Manufacturing Productivity Division (MPD) of Hewlett-Packard (HP) was in the process of making major market selection and product policy decisions. MPD is a small division which develops and markets manufacturing productivity software (materials management, MRP, etc.). The product policy decisions included degree of product customization and choice of operating systems (UNIX or not?). The relationship between the marketing and research and development functions is a major issue.


Case Authors : Benson P. Shapiro, Lawrence B. Levine

Topic : Sales & Marketing

Related Areas : Organizational culture, Product development, Technology




Calculating Net Present Value (NPV) at 6% for Hewlett-Packard: Manufacturing Productivity Division (A) Case Study


Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 6 %
Discounted
Cash Flows
Year 0 (10002340) -10002340 - -
Year 1 3451739 -6550601 3451739 0.9434 3256358
Year 2 3975339 -2575262 7427078 0.89 3538038
Year 3 3949122 1373860 11376200 0.8396 3315759
Year 4 3223543 4597403 14599743 0.7921 2553348
TOTAL 14599743 12663502




The Net Present Value at 6% discount rate is 2661162

In isolation the NPV number doesn't mean much but put in right context then it is one of the best method to evaluate project returns. In this article we will cover -

Different methods of capital budgeting


What is NPV & Formula of NPV,
How it is calculated,
How to use NPV number for project evaluation, and
Scenario Planning given risks and management priorities.




Capital Budgeting Approaches

Methods of Capital Budgeting


There are four types of capital budgeting techniques that are widely used in the corporate world –

1. Internal Rate of Return
2. Payback Period
3. Net Present Value
4. Profitability Index

Apart from the Payback period method which is an additive method, rest of the methods are based on Discounted Cash Flow technique. Even though cash flow can be calculated based on the nature of the project, for the simplicity of the article we are assuming that all the expected cash flows are realized at the end of the year.

Discounted Cash Flow approaches provide a more objective basis for evaluating and selecting investment projects. They take into consideration both –

1. Timing of the expected cash flows – stockholders of Mpd Productivity have higher preference for cash returns over 4-5 years rather than 10-15 years given the nature of the volatility in the industry.
2. Magnitude of both incoming and outgoing cash flows – Projects can be capital intensive, time intensive, or both. Mpd Productivity shareholders have preference for diversified projects investment rather than prospective high income from a single capital intensive project.






Formula and Steps to Calculate Net Present Value (NPV) of Hewlett-Packard: Manufacturing Productivity Division (A)

NPV = Net Cash In Flowt1 / (1+r)t1 + Net Cash In Flowt2 / (1+r)t2 + … Net Cash In Flowtn / (1+r)tn
Less Net Cash Out Flowt0 / (1+r)t0

Where t = time period, in this case year 1, year 2 and so on.
r = discount rate or return that could be earned using other safe proposition such as fixed deposit or treasury bond rate. Net Cash In Flow – What the firm will get each year.
Net Cash Out Flow – What the firm needs to invest initially in the project.

Step 1 – Understand the nature of the project and calculate cash flow for each year.
Step 2 – Discount those cash flow based on the discount rate.
Step 3 – Add all the discounted cash flow.
Step 4 – Selection of the project

Why Sales & Marketing Managers need to know Financial Tools such as Net Present Value (NPV)?

In our daily workplace we often come across people and colleagues who are just focused on their core competency and targets they have to deliver. For example marketing managers at Mpd Productivity often design programs whose objective is to drive brand awareness and customer reach. But how that 30 point increase in brand awareness or 10 point increase in customer touch points will result into shareholders’ value is not specified.

To overcome such scenarios managers at Mpd Productivity needs to not only know the financial aspect of project management but also needs to have tools to integrate them into part of the project development and monitoring plan.

Calculating Net Present Value (NPV) at 15%

After working through various assumptions we reached a conclusion that risk is far higher than 6%. In a reasonably stable industry with weak competition - 15% discount rate can be a good benchmark.



Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 15 %
Discounted
Cash Flows
Year 0 (10002340) -10002340 - -
Year 1 3451739 -6550601 3451739 0.8696 3001512
Year 2 3975339 -2575262 7427078 0.7561 3005927
Year 3 3949122 1373860 11376200 0.6575 2596612
Year 4 3223543 4597403 14599743 0.5718 1843071
TOTAL 10447123


The Net NPV after 4 years is 444783

(10447123 - 10002340 )








Calculating Net Present Value (NPV) at 20%


If the risk component is high in the industry then we should go for a higher hurdle rate / discount rate of 20%.

Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 20 %
Discounted
Cash Flows
Year 0 (10002340) -10002340 - -
Year 1 3451739 -6550601 3451739 0.8333 2876449
Year 2 3975339 -2575262 7427078 0.6944 2760652
Year 3 3949122 1373860 11376200 0.5787 2285372
Year 4 3223543 4597403 14599743 0.4823 1554564
TOTAL 9477036


The Net NPV after 4 years is -525304

At 20% discount rate the NPV is negative (9477036 - 10002340 ) so ideally we can't select the project if macro and micro factors don't allow financial managers of Mpd Productivity to discount cash flow at lower discount rates such as 15%.





Acceptance Criteria of a Project based on NPV

Simplest Approach – If the investment project of Mpd Productivity has a NPV value higher than Zero then finance managers at Mpd Productivity can ACCEPT the project, otherwise they can reject the project. This means that project will deliver higher returns over the period of time than any alternate investment strategy.

In theory if the required rate of return or discount rate is chosen correctly by finance managers at Mpd Productivity, then the stock price of the Mpd Productivity should change by same amount of the NPV. In real world we know that share price also reflects various other factors that can be related to both macro and micro environment.

In the same vein – accepting the project with zero NPV should result in stagnant share price. Finance managers use discount rates as a measure of risk components in the project execution process.

Sensitivity Analysis

Project selection is often a far more complex decision than just choosing it based on the NPV number. Finance managers at Mpd Productivity should conduct a sensitivity analysis to better understand not only the inherent risk of the projects but also how those risks can be either factored in or mitigated during the project execution. Sensitivity analysis helps in –

What are the key aspects of the projects that need to be monitored, refined, and retuned for continuous delivery of projected cash flows.

What will be a multi year spillover effect of various taxation regulations.

What can impact the cash flow of the project.

Understanding of risks involved in the project.

What are the uncertainties surrounding the project Initial Cash Outlay (ICO’s). ICO’s often have several different components such as land, machinery, building, and other equipment.

Some of the assumptions while using the Discounted Cash Flow Methods –

Projects are assumed to be Mutually Exclusive – This is seldom the came in modern day giant organizations where projects are often inter-related and rejecting a project solely based on NPV can result in sunk cost from a related project.

Independent projects have independent cash flows – As explained in the marketing project – though the project may look independent but in reality it is not as the brand awareness project can be closely associated with the spending on sales promotions and product specific advertising.






Negotiation Strategy of Hewlett-Packard: Manufacturing Productivity Division (A)

References & Further Readings

Benson P. Shapiro, Lawrence B. Levine (2018), "Hewlett-Packard: Manufacturing Productivity Division (A) Harvard Business Review Case Study. Published by HBR Publications.


Lonmin SWOT Analysis / TOWS Matrix

Basic Materials , Metal Mining


Borealis Exploration SWOT Analysis / TOWS Matrix

Technology , Electronic Instr. & Controls


Gazprom Neft ADR SWOT Analysis / TOWS Matrix

Energy , Oil & Gas - Integrated


Rm2 Int SWOT Analysis / TOWS Matrix

Basic Materials , Containers & Packaging


Enlight Ene SWOT Analysis / TOWS Matrix

Capital Goods , Construction Services


Guangdong Tonze Electric SWOT Analysis / TOWS Matrix

Consumer Cyclical , Appliance & Tool


Amanasu Techs Corp SWOT Analysis / TOWS Matrix

Financial , Misc. Financial Services


Hino Motors ADR SWOT Analysis / TOWS Matrix

Consumer Cyclical , Auto & Truck Manufacturers


Tokyo Kikai Seisakusho SWOT Analysis / TOWS Matrix

Capital Goods , Misc. Capital Goods