NPV solution for Vincor: Project Twist case study


At Oak Spring University, we provide corporate level professional Net Present Value (NPV) case study solution. Vincor: Project Twist case study is a Harvard Business School (HBR) case study written by Niraj Dawar, Eric Singer. The Vincor: Project Twist (referred as “Vincor Refreshment” from here on) case study provides evaluation & decision scenario in field of Sales & Marketing. It also touches upon business topics such as - Value proposition, Sales.

The net present value (NPV) of an investment proposal is the present value of the proposal’s net cash flows less the proposal’s initial cash outflow. If a project’s NPV is greater than or equal to zero, the project should be accepted.

NPV = Present Value of Future Cash Flows LESS Project’s Initial Investment






Case Description of Vincor: Project Twist Case Study


The alcohol cooler (refreshment) market in Canada was already crowded, but the marketing manager at Vincor believed there was still room for a new entrant, provided it was sufficiently differentiated. The case provides market research information on which the decision-maker relies to develop a product positioning. Trade-offs need to be made between various positioning options and costs. The case deals with marketing issues from the perspective of the brand manager launching a new product.


Case Authors : Niraj Dawar, Eric Singer

Topic : Sales & Marketing

Related Areas : Sales




Calculating Net Present Value (NPV) at 6% for Vincor: Project Twist Case Study


Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 6 %
Discounted
Cash Flows
Year 0 (10009771) -10009771 - -
Year 1 3460919 -6548852 3460919 0.9434 3265018
Year 2 3960404 -2588448 7421323 0.89 3524745
Year 3 3956093 1367645 11377416 0.8396 3321612
Year 4 3251897 4619542 14629313 0.7921 2575807
TOTAL 14629313 12687182




The Net Present Value at 6% discount rate is 2677411

In isolation the NPV number doesn't mean much but put in right context then it is one of the best method to evaluate project returns. In this article we will cover -

Different methods of capital budgeting


What is NPV & Formula of NPV,
How it is calculated,
How to use NPV number for project evaluation, and
Scenario Planning given risks and management priorities.




Capital Budgeting Approaches

Methods of Capital Budgeting


There are four types of capital budgeting techniques that are widely used in the corporate world –

1. Net Present Value
2. Profitability Index
3. Internal Rate of Return
4. Payback Period

Apart from the Payback period method which is an additive method, rest of the methods are based on Discounted Cash Flow technique. Even though cash flow can be calculated based on the nature of the project, for the simplicity of the article we are assuming that all the expected cash flows are realized at the end of the year.

Discounted Cash Flow approaches provide a more objective basis for evaluating and selecting investment projects. They take into consideration both –

1. Timing of the expected cash flows – stockholders of Vincor Refreshment have higher preference for cash returns over 4-5 years rather than 10-15 years given the nature of the volatility in the industry.
2. Magnitude of both incoming and outgoing cash flows – Projects can be capital intensive, time intensive, or both. Vincor Refreshment shareholders have preference for diversified projects investment rather than prospective high income from a single capital intensive project.






Formula and Steps to Calculate Net Present Value (NPV) of Vincor: Project Twist

NPV = Net Cash In Flowt1 / (1+r)t1 + Net Cash In Flowt2 / (1+r)t2 + … Net Cash In Flowtn / (1+r)tn
Less Net Cash Out Flowt0 / (1+r)t0

Where t = time period, in this case year 1, year 2 and so on.
r = discount rate or return that could be earned using other safe proposition such as fixed deposit or treasury bond rate. Net Cash In Flow – What the firm will get each year.
Net Cash Out Flow – What the firm needs to invest initially in the project.

Step 1 – Understand the nature of the project and calculate cash flow for each year.
Step 2 – Discount those cash flow based on the discount rate.
Step 3 – Add all the discounted cash flow.
Step 4 – Selection of the project

Why Sales & Marketing Managers need to know Financial Tools such as Net Present Value (NPV)?

In our daily workplace we often come across people and colleagues who are just focused on their core competency and targets they have to deliver. For example marketing managers at Vincor Refreshment often design programs whose objective is to drive brand awareness and customer reach. But how that 30 point increase in brand awareness or 10 point increase in customer touch points will result into shareholders’ value is not specified.

To overcome such scenarios managers at Vincor Refreshment needs to not only know the financial aspect of project management but also needs to have tools to integrate them into part of the project development and monitoring plan.

Calculating Net Present Value (NPV) at 15%

After working through various assumptions we reached a conclusion that risk is far higher than 6%. In a reasonably stable industry with weak competition - 15% discount rate can be a good benchmark.



Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 15 %
Discounted
Cash Flows
Year 0 (10009771) -10009771 - -
Year 1 3460919 -6548852 3460919 0.8696 3009495
Year 2 3960404 -2588448 7421323 0.7561 2994634
Year 3 3956093 1367645 11377416 0.6575 2601195
Year 4 3251897 4619542 14629313 0.5718 1859283
TOTAL 10464607


The Net NPV after 4 years is 454836

(10464607 - 10009771 )








Calculating Net Present Value (NPV) at 20%


If the risk component is high in the industry then we should go for a higher hurdle rate / discount rate of 20%.

Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 20 %
Discounted
Cash Flows
Year 0 (10009771) -10009771 - -
Year 1 3460919 -6548852 3460919 0.8333 2884099
Year 2 3960404 -2588448 7421323 0.6944 2750281
Year 3 3956093 1367645 11377416 0.5787 2289406
Year 4 3251897 4619542 14629313 0.4823 1568237
TOTAL 9492023


The Net NPV after 4 years is -517748

At 20% discount rate the NPV is negative (9492023 - 10009771 ) so ideally we can't select the project if macro and micro factors don't allow financial managers of Vincor Refreshment to discount cash flow at lower discount rates such as 15%.





Acceptance Criteria of a Project based on NPV

Simplest Approach – If the investment project of Vincor Refreshment has a NPV value higher than Zero then finance managers at Vincor Refreshment can ACCEPT the project, otherwise they can reject the project. This means that project will deliver higher returns over the period of time than any alternate investment strategy.

In theory if the required rate of return or discount rate is chosen correctly by finance managers at Vincor Refreshment, then the stock price of the Vincor Refreshment should change by same amount of the NPV. In real world we know that share price also reflects various other factors that can be related to both macro and micro environment.

In the same vein – accepting the project with zero NPV should result in stagnant share price. Finance managers use discount rates as a measure of risk components in the project execution process.

Sensitivity Analysis

Project selection is often a far more complex decision than just choosing it based on the NPV number. Finance managers at Vincor Refreshment should conduct a sensitivity analysis to better understand not only the inherent risk of the projects but also how those risks can be either factored in or mitigated during the project execution. Sensitivity analysis helps in –

What can impact the cash flow of the project.

What will be a multi year spillover effect of various taxation regulations.

What are the key aspects of the projects that need to be monitored, refined, and retuned for continuous delivery of projected cash flows.

Understanding of risks involved in the project.

What are the uncertainties surrounding the project Initial Cash Outlay (ICO’s). ICO’s often have several different components such as land, machinery, building, and other equipment.

Some of the assumptions while using the Discounted Cash Flow Methods –

Projects are assumed to be Mutually Exclusive – This is seldom the came in modern day giant organizations where projects are often inter-related and rejecting a project solely based on NPV can result in sunk cost from a related project.

Independent projects have independent cash flows – As explained in the marketing project – though the project may look independent but in reality it is not as the brand awareness project can be closely associated with the spending on sales promotions and product specific advertising.






Negotiation Strategy of Vincor: Project Twist

References & Further Readings

Niraj Dawar, Eric Singer (2018), "Vincor: Project Twist Harvard Business Review Case Study. Published by HBR Publications.


Libental SWOT Analysis / TOWS Matrix

Services , Real Estate Operations


Gem-Year Industrial SWOT Analysis / TOWS Matrix

Basic Materials , Misc. Fabricated Products


Indonesia Prima SWOT Analysis / TOWS Matrix

Capital Goods , Construction Services


Sinotruk Hong Kong SWOT Analysis / TOWS Matrix

Consumer Cyclical , Auto & Truck Manufacturers


Moorim P&P Co SWOT Analysis / TOWS Matrix

Basic Materials , Paper & Paper Products


FactSet Research SWOT Analysis / TOWS Matrix

Technology , Computer Services


SQLi SWOT Analysis / TOWS Matrix

Technology , Software & Programming


Cellectis SWOT Analysis / TOWS Matrix

Healthcare , Biotechnology & Drugs