Madras Cements, Ltd. Net Present Value (NPV) / MBA Resources

Introduction to Net Present Value (NPV) - What is Net Present Value (NPV) ? How it impacts financial decisions regarding project management?

NPV solution for Madras Cements, Ltd. case study


At Oak Spring University, we provide corporate level professional Net Present Value (NPV) case study solution. Madras Cements, Ltd. case study is a Harvard Business School (HBR) case study written by C.K. Prahalad, M.S. Krishnan. The Madras Cements, Ltd. (referred as “Madras Cement” from here on) case study provides evaluation & decision scenario in field of Strategy & Execution. It also touches upon business topics such as - Value proposition, Growth strategy, IT.

The net present value (NPV) of an investment proposal is the present value of the proposal’s net cash flows less the proposal’s initial cash outflow. If a project’s NPV is greater than or equal to zero, the project should be accepted.

NPV = Present Value of Future Cash Flows LESS Project’s Initial Investment






Case Description of Madras Cements, Ltd. Case Study


A leading cement producer in southern India, Madras Cement is having trouble controlling costs due to its disorganized reporting processes. This case documents the company's two attempts to resolve these issues with the implementation of an Enterprise Resource Planning (ERP) system. The company's first attempt fails. After a company leader takes the bold step of admitting he made mistakes during this effort, Madras is ready to dig in and make the necessary changes to make the second attempt a success. The case initially seems to be about software implementation, but it is really a story about change management, transformation through transparency, business centric approaches, and the creation of a new social architecture. The company uses innovation to develop new processes that can ultimately be applied to other organizations, allowing the merger and acquisition process to begin.


Case Authors : C.K. Prahalad, M.S. Krishnan

Topic : Strategy & Execution

Related Areas : Growth strategy, IT




Calculating Net Present Value (NPV) at 6% for Madras Cements, Ltd. Case Study


Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 6 %
Discounted
Cash Flows
Year 0 (10024726) -10024726 - -
Year 1 3455173 -6569553 3455173 0.9434 3259597
Year 2 3964375 -2605178 7419548 0.89 3528280
Year 3 3959102 1353924 11378650 0.8396 3324138
Year 4 3237363 4591287 14616013 0.7921 2564295
TOTAL 14616013 12676310




The Net Present Value at 6% discount rate is 2651584

In isolation the NPV number doesn't mean much but put in right context then it is one of the best method to evaluate project returns. In this article we will cover -

Different methods of capital budgeting


What is NPV & Formula of NPV,
How it is calculated,
How to use NPV number for project evaluation, and
Scenario Planning given risks and management priorities.




Capital Budgeting Approaches

Methods of Capital Budgeting


There are four types of capital budgeting techniques that are widely used in the corporate world –

1. Internal Rate of Return
2. Profitability Index
3. Payback Period
4. Net Present Value

Apart from the Payback period method which is an additive method, rest of the methods are based on Discounted Cash Flow technique. Even though cash flow can be calculated based on the nature of the project, for the simplicity of the article we are assuming that all the expected cash flows are realized at the end of the year.

Discounted Cash Flow approaches provide a more objective basis for evaluating and selecting investment projects. They take into consideration both –

1. Timing of the expected cash flows – stockholders of Madras Cement have higher preference for cash returns over 4-5 years rather than 10-15 years given the nature of the volatility in the industry.
2. Magnitude of both incoming and outgoing cash flows – Projects can be capital intensive, time intensive, or both. Madras Cement shareholders have preference for diversified projects investment rather than prospective high income from a single capital intensive project.






Formula and Steps to Calculate Net Present Value (NPV) of Madras Cements, Ltd.

NPV = Net Cash In Flowt1 / (1+r)t1 + Net Cash In Flowt2 / (1+r)t2 + … Net Cash In Flowtn / (1+r)tn
Less Net Cash Out Flowt0 / (1+r)t0

Where t = time period, in this case year 1, year 2 and so on.
r = discount rate or return that could be earned using other safe proposition such as fixed deposit or treasury bond rate. Net Cash In Flow – What the firm will get each year.
Net Cash Out Flow – What the firm needs to invest initially in the project.

Step 1 – Understand the nature of the project and calculate cash flow for each year.
Step 2 – Discount those cash flow based on the discount rate.
Step 3 – Add all the discounted cash flow.
Step 4 – Selection of the project

Why Strategy & Execution Managers need to know Financial Tools such as Net Present Value (NPV)?

In our daily workplace we often come across people and colleagues who are just focused on their core competency and targets they have to deliver. For example marketing managers at Madras Cement often design programs whose objective is to drive brand awareness and customer reach. But how that 30 point increase in brand awareness or 10 point increase in customer touch points will result into shareholders’ value is not specified.

To overcome such scenarios managers at Madras Cement needs to not only know the financial aspect of project management but also needs to have tools to integrate them into part of the project development and monitoring plan.

Calculating Net Present Value (NPV) at 15%

After working through various assumptions we reached a conclusion that risk is far higher than 6%. In a reasonably stable industry with weak competition - 15% discount rate can be a good benchmark.



Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 15 %
Discounted
Cash Flows
Year 0 (10024726) -10024726 - -
Year 1 3455173 -6569553 3455173 0.8696 3004498
Year 2 3964375 -2605178 7419548 0.7561 2997637
Year 3 3959102 1353924 11378650 0.6575 2603174
Year 4 3237363 4591287 14616013 0.5718 1850973
TOTAL 10456282


The Net NPV after 4 years is 431556

(10456282 - 10024726 )








Calculating Net Present Value (NPV) at 20%


If the risk component is high in the industry then we should go for a higher hurdle rate / discount rate of 20%.

Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 20 %
Discounted
Cash Flows
Year 0 (10024726) -10024726 - -
Year 1 3455173 -6569553 3455173 0.8333 2879311
Year 2 3964375 -2605178 7419548 0.6944 2753038
Year 3 3959102 1353924 11378650 0.5787 2291147
Year 4 3237363 4591287 14616013 0.4823 1561228
TOTAL 9484724


The Net NPV after 4 years is -540002

At 20% discount rate the NPV is negative (9484724 - 10024726 ) so ideally we can't select the project if macro and micro factors don't allow financial managers of Madras Cement to discount cash flow at lower discount rates such as 15%.





Acceptance Criteria of a Project based on NPV

Simplest Approach – If the investment project of Madras Cement has a NPV value higher than Zero then finance managers at Madras Cement can ACCEPT the project, otherwise they can reject the project. This means that project will deliver higher returns over the period of time than any alternate investment strategy.

In theory if the required rate of return or discount rate is chosen correctly by finance managers at Madras Cement, then the stock price of the Madras Cement should change by same amount of the NPV. In real world we know that share price also reflects various other factors that can be related to both macro and micro environment.

In the same vein – accepting the project with zero NPV should result in stagnant share price. Finance managers use discount rates as a measure of risk components in the project execution process.

Sensitivity Analysis

Project selection is often a far more complex decision than just choosing it based on the NPV number. Finance managers at Madras Cement should conduct a sensitivity analysis to better understand not only the inherent risk of the projects but also how those risks can be either factored in or mitigated during the project execution. Sensitivity analysis helps in –

What are the uncertainties surrounding the project Initial Cash Outlay (ICO’s). ICO’s often have several different components such as land, machinery, building, and other equipment.

What will be a multi year spillover effect of various taxation regulations.

What are the key aspects of the projects that need to be monitored, refined, and retuned for continuous delivery of projected cash flows.

What can impact the cash flow of the project.

Understanding of risks involved in the project.

Some of the assumptions while using the Discounted Cash Flow Methods –

Projects are assumed to be Mutually Exclusive – This is seldom the came in modern day giant organizations where projects are often inter-related and rejecting a project solely based on NPV can result in sunk cost from a related project.

Independent projects have independent cash flows – As explained in the marketing project – though the project may look independent but in reality it is not as the brand awareness project can be closely associated with the spending on sales promotions and product specific advertising.






Negotiation Strategy of Madras Cements, Ltd.

References & Further Readings

C.K. Prahalad, M.S. Krishnan (2018), "Madras Cements, Ltd. Harvard Business Review Case Study. Published by HBR Publications.


Qinghai Huzhu Barley Wine A SWOT Analysis / TOWS Matrix

Consumer/Non-Cyclical , Beverages (Alcoholic)


Plastrade Tech SWOT Analysis / TOWS Matrix

Basic Materials , Chemicals - Plastics & Rubber


HNK Machine Tool SWOT Analysis / TOWS Matrix

Capital Goods , Misc. Capital Goods


Ruitai Mat Tech A SWOT Analysis / TOWS Matrix

Capital Goods , Constr. - Supplies & Fixtures


Maxwell SWOT Analysis / TOWS Matrix

Technology , Electronic Instr. & Controls


Silvercorp Metals SWOT Analysis / TOWS Matrix

Basic Materials , Gold & Silver


Wendel SWOT Analysis / TOWS Matrix

Services , Business Services


Tera Probe SWOT Analysis / TOWS Matrix

Services , Business Services


Titan Company SWOT Analysis / TOWS Matrix

Consumer Cyclical , Jewelry & Silverware


Cirque Energy SWOT Analysis / TOWS Matrix

Services , Waste Management Services