Hanson Industries (A) Net Present Value (NPV) / MBA Resources

Introduction to Net Present Value (NPV) - What is Net Present Value (NPV) ? How it impacts financial decisions regarding project management?

NPV solution for Hanson Industries (A) case study


At Oak Spring University, we provide corporate level professional Net Present Value (NPV) case study solution. Hanson Industries (A) case study is a Harvard Business School (HBR) case study written by William J. Bruns Jr., Julie H. Hertenstein. The Hanson Industries (A) (referred as “Hanson Boot” from here on) case study provides evaluation & decision scenario in field of Finance & Accounting. It also touches upon business topics such as - Value proposition, Manufacturing, Marketing, Strategic planning.

The net present value (NPV) of an investment proposal is the present value of the proposal’s net cash flows less the proposal’s initial cash outflow. If a project’s NPV is greater than or equal to zero, the project should be accepted.

NPV = Present Value of Future Cash Flows LESS Project’s Initial Investment






Case Description of Hanson Industries (A) Case Study


Hanson Industries produces and sells an award-winning design ski boot. Describes the company history from founding through July 1978, the product, production processes, marketing strategy, and background information for related cases on budgeting and finance.


Case Authors : William J. Bruns Jr., Julie H. Hertenstein

Topic : Finance & Accounting

Related Areas : Manufacturing, Marketing, Strategic planning




Calculating Net Present Value (NPV) at 6% for Hanson Industries (A) Case Study


Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 6 %
Discounted
Cash Flows
Year 0 (10025867) -10025867 - -
Year 1 3459430 -6566437 3459430 0.9434 3263613
Year 2 3961103 -2605334 7420533 0.89 3525368
Year 3 3946116 1340782 11366649 0.8396 3313235
Year 4 3233523 4574305 14600172 0.7921 2561253
TOTAL 14600172 12663469




The Net Present Value at 6% discount rate is 2637602

In isolation the NPV number doesn't mean much but put in right context then it is one of the best method to evaluate project returns. In this article we will cover -

Different methods of capital budgeting


What is NPV & Formula of NPV,
How it is calculated,
How to use NPV number for project evaluation, and
Scenario Planning given risks and management priorities.




Capital Budgeting Approaches

Methods of Capital Budgeting


There are four types of capital budgeting techniques that are widely used in the corporate world –

1. Net Present Value
2. Internal Rate of Return
3. Profitability Index
4. Payback Period

Apart from the Payback period method which is an additive method, rest of the methods are based on Discounted Cash Flow technique. Even though cash flow can be calculated based on the nature of the project, for the simplicity of the article we are assuming that all the expected cash flows are realized at the end of the year.

Discounted Cash Flow approaches provide a more objective basis for evaluating and selecting investment projects. They take into consideration both –

1. Timing of the expected cash flows – stockholders of Hanson Boot have higher preference for cash returns over 4-5 years rather than 10-15 years given the nature of the volatility in the industry.
2. Magnitude of both incoming and outgoing cash flows – Projects can be capital intensive, time intensive, or both. Hanson Boot shareholders have preference for diversified projects investment rather than prospective high income from a single capital intensive project.






Formula and Steps to Calculate Net Present Value (NPV) of Hanson Industries (A)

NPV = Net Cash In Flowt1 / (1+r)t1 + Net Cash In Flowt2 / (1+r)t2 + … Net Cash In Flowtn / (1+r)tn
Less Net Cash Out Flowt0 / (1+r)t0

Where t = time period, in this case year 1, year 2 and so on.
r = discount rate or return that could be earned using other safe proposition such as fixed deposit or treasury bond rate. Net Cash In Flow – What the firm will get each year.
Net Cash Out Flow – What the firm needs to invest initially in the project.

Step 1 – Understand the nature of the project and calculate cash flow for each year.
Step 2 – Discount those cash flow based on the discount rate.
Step 3 – Add all the discounted cash flow.
Step 4 – Selection of the project

Why Finance & Accounting Managers need to know Financial Tools such as Net Present Value (NPV)?

In our daily workplace we often come across people and colleagues who are just focused on their core competency and targets they have to deliver. For example marketing managers at Hanson Boot often design programs whose objective is to drive brand awareness and customer reach. But how that 30 point increase in brand awareness or 10 point increase in customer touch points will result into shareholders’ value is not specified.

To overcome such scenarios managers at Hanson Boot needs to not only know the financial aspect of project management but also needs to have tools to integrate them into part of the project development and monitoring plan.

Calculating Net Present Value (NPV) at 15%

After working through various assumptions we reached a conclusion that risk is far higher than 6%. In a reasonably stable industry with weak competition - 15% discount rate can be a good benchmark.



Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 15 %
Discounted
Cash Flows
Year 0 (10025867) -10025867 - -
Year 1 3459430 -6566437 3459430 0.8696 3008200
Year 2 3961103 -2605334 7420533 0.7561 2995163
Year 3 3946116 1340782 11366649 0.6575 2594635
Year 4 3233523 4574305 14600172 0.5718 1848777
TOTAL 10446776


The Net NPV after 4 years is 420909

(10446776 - 10025867 )








Calculating Net Present Value (NPV) at 20%


If the risk component is high in the industry then we should go for a higher hurdle rate / discount rate of 20%.

Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 20 %
Discounted
Cash Flows
Year 0 (10025867) -10025867 - -
Year 1 3459430 -6566437 3459430 0.8333 2882858
Year 2 3961103 -2605334 7420533 0.6944 2750766
Year 3 3946116 1340782 11366649 0.5787 2283632
Year 4 3233523 4574305 14600172 0.4823 1559376
TOTAL 9476633


The Net NPV after 4 years is -549234

At 20% discount rate the NPV is negative (9476633 - 10025867 ) so ideally we can't select the project if macro and micro factors don't allow financial managers of Hanson Boot to discount cash flow at lower discount rates such as 15%.





Acceptance Criteria of a Project based on NPV

Simplest Approach – If the investment project of Hanson Boot has a NPV value higher than Zero then finance managers at Hanson Boot can ACCEPT the project, otherwise they can reject the project. This means that project will deliver higher returns over the period of time than any alternate investment strategy.

In theory if the required rate of return or discount rate is chosen correctly by finance managers at Hanson Boot, then the stock price of the Hanson Boot should change by same amount of the NPV. In real world we know that share price also reflects various other factors that can be related to both macro and micro environment.

In the same vein – accepting the project with zero NPV should result in stagnant share price. Finance managers use discount rates as a measure of risk components in the project execution process.

Sensitivity Analysis

Project selection is often a far more complex decision than just choosing it based on the NPV number. Finance managers at Hanson Boot should conduct a sensitivity analysis to better understand not only the inherent risk of the projects but also how those risks can be either factored in or mitigated during the project execution. Sensitivity analysis helps in –

Understanding of risks involved in the project.

What will be a multi year spillover effect of various taxation regulations.

What are the key aspects of the projects that need to be monitored, refined, and retuned for continuous delivery of projected cash flows.

What are the uncertainties surrounding the project Initial Cash Outlay (ICO’s). ICO’s often have several different components such as land, machinery, building, and other equipment.

What can impact the cash flow of the project.

Some of the assumptions while using the Discounted Cash Flow Methods –

Projects are assumed to be Mutually Exclusive – This is seldom the came in modern day giant organizations where projects are often inter-related and rejecting a project solely based on NPV can result in sunk cost from a related project.

Independent projects have independent cash flows – As explained in the marketing project – though the project may look independent but in reality it is not as the brand awareness project can be closely associated with the spending on sales promotions and product specific advertising.






Negotiation Strategy of Hanson Industries (A)

References & Further Readings

William J. Bruns Jr., Julie H. Hertenstein (2018), "Hanson Industries (A) Harvard Business Review Case Study. Published by HBR Publications.


Cuba Beverage Co SWOT Analysis / TOWS Matrix

Consumer/Non-Cyclical , Food Processing


CAPE ES Special SWOT Analysis / TOWS Matrix

Financial , Misc. Financial Services


China Baofeng SWOT Analysis / TOWS Matrix

Consumer/Non-Cyclical , Beverages (Alcoholic)


Clearbridge Health SWOT Analysis / TOWS Matrix

Healthcare , Healthcare Facilities


Neon Capital SWOT Analysis / TOWS Matrix

Energy , Oil & Gas Operations


IF Bancorp SWOT Analysis / TOWS Matrix

Financial , Regional Banks


Dmegc Magnetics A SWOT Analysis / TOWS Matrix

Technology , Electronic Instr. & Controls


NTT Data Corp. SWOT Analysis / TOWS Matrix

Technology , Computer Networks


NIIT Technologies SWOT Analysis / TOWS Matrix

Technology , Software & Programming