Azza Fahmy Jewellery: Expand Locally or Internationally? Net Present Value (NPV) / MBA Resources

Introduction to Net Present Value (NPV) - What is Net Present Value (NPV) ? How it impacts financial decisions regarding project management?

NPV solution for Azza Fahmy Jewellery: Expand Locally or Internationally? case study


At Oak Spring University, we provide corporate level professional Net Present Value (NPV) case study solution. Azza Fahmy Jewellery: Expand Locally or Internationally? case study is a Harvard Business School (HBR) case study written by Marina Apaydin, Hend Mostafa, Mariam Mohamed Sherin, Mariam Ali Mobarak. The Azza Fahmy Jewellery: Expand Locally or Internationally? (referred as “Azza Fahmy” from here on) case study provides evaluation & decision scenario in field of Strategy & Execution. It also touches upon business topics such as - Value proposition, Strategy.

The net present value (NPV) of an investment proposal is the present value of the proposal’s net cash flows less the proposal’s initial cash outflow. If a project’s NPV is greater than or equal to zero, the project should be accepted.

NPV = Present Value of Future Cash Flows LESS Project’s Initial Investment






Case Description of Azza Fahmy Jewellery: Expand Locally or Internationally? Case Study


This is the second case in the Azza Fahmy series. This case and the three others in this series (9B13M097, 9B13M099 and 9B14M023) can be used together or on a standalone basis. This case series features a female Egyptian entrepreneur who faces the challenge of developing her self-titled jewellery brand. In this case, the entrepreneur realizes the importance of having a clear organizational structure with different departments and a clear chain of authority. As a result, she hires her daughter as the managing director to take on the responsibility of developing a mission, vision and explicit organizational structure. This restructuring allows the company to grow further, which leads the entrepreneur to consider her opportunities in the international market. Author Marina Apaydin is affiliated with American University of Beirut. Author Hend Mostafa is affiliated with American University of Cairo.


Case Authors : Marina Apaydin, Hend Mostafa, Mariam Mohamed Sherin, Mariam Ali Mobarak

Topic : Strategy & Execution

Related Areas : Strategy




Calculating Net Present Value (NPV) at 6% for Azza Fahmy Jewellery: Expand Locally or Internationally? Case Study


Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 6 %
Discounted
Cash Flows
Year 0 (10007034) -10007034 - -
Year 1 3462873 -6544161 3462873 0.9434 3266861
Year 2 3975128 -2569033 7438001 0.89 3537850
Year 3 3962370 1393337 11400371 0.8396 3326882
Year 4 3243202 4636539 14643573 0.7921 2568920
TOTAL 14643573 12700513




The Net Present Value at 6% discount rate is 2693479

In isolation the NPV number doesn't mean much but put in right context then it is one of the best method to evaluate project returns. In this article we will cover -

Different methods of capital budgeting


What is NPV & Formula of NPV,
How it is calculated,
How to use NPV number for project evaluation, and
Scenario Planning given risks and management priorities.




Capital Budgeting Approaches

Methods of Capital Budgeting


There are four types of capital budgeting techniques that are widely used in the corporate world –

1. Payback Period
2. Internal Rate of Return
3. Net Present Value
4. Profitability Index

Apart from the Payback period method which is an additive method, rest of the methods are based on Discounted Cash Flow technique. Even though cash flow can be calculated based on the nature of the project, for the simplicity of the article we are assuming that all the expected cash flows are realized at the end of the year.

Discounted Cash Flow approaches provide a more objective basis for evaluating and selecting investment projects. They take into consideration both –

1. Timing of the expected cash flows – stockholders of Azza Fahmy have higher preference for cash returns over 4-5 years rather than 10-15 years given the nature of the volatility in the industry.
2. Magnitude of both incoming and outgoing cash flows – Projects can be capital intensive, time intensive, or both. Azza Fahmy shareholders have preference for diversified projects investment rather than prospective high income from a single capital intensive project.






Formula and Steps to Calculate Net Present Value (NPV) of Azza Fahmy Jewellery: Expand Locally or Internationally?

NPV = Net Cash In Flowt1 / (1+r)t1 + Net Cash In Flowt2 / (1+r)t2 + … Net Cash In Flowtn / (1+r)tn
Less Net Cash Out Flowt0 / (1+r)t0

Where t = time period, in this case year 1, year 2 and so on.
r = discount rate or return that could be earned using other safe proposition such as fixed deposit or treasury bond rate. Net Cash In Flow – What the firm will get each year.
Net Cash Out Flow – What the firm needs to invest initially in the project.

Step 1 – Understand the nature of the project and calculate cash flow for each year.
Step 2 – Discount those cash flow based on the discount rate.
Step 3 – Add all the discounted cash flow.
Step 4 – Selection of the project

Why Strategy & Execution Managers need to know Financial Tools such as Net Present Value (NPV)?

In our daily workplace we often come across people and colleagues who are just focused on their core competency and targets they have to deliver. For example marketing managers at Azza Fahmy often design programs whose objective is to drive brand awareness and customer reach. But how that 30 point increase in brand awareness or 10 point increase in customer touch points will result into shareholders’ value is not specified.

To overcome such scenarios managers at Azza Fahmy needs to not only know the financial aspect of project management but also needs to have tools to integrate them into part of the project development and monitoring plan.

Calculating Net Present Value (NPV) at 15%

After working through various assumptions we reached a conclusion that risk is far higher than 6%. In a reasonably stable industry with weak competition - 15% discount rate can be a good benchmark.



Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 15 %
Discounted
Cash Flows
Year 0 (10007034) -10007034 - -
Year 1 3462873 -6544161 3462873 0.8696 3011194
Year 2 3975128 -2569033 7438001 0.7561 3005768
Year 3 3962370 1393337 11400371 0.6575 2605323
Year 4 3243202 4636539 14643573 0.5718 1854311
TOTAL 10476596


The Net NPV after 4 years is 469562

(10476596 - 10007034 )








Calculating Net Present Value (NPV) at 20%


If the risk component is high in the industry then we should go for a higher hurdle rate / discount rate of 20%.

Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 20 %
Discounted
Cash Flows
Year 0 (10007034) -10007034 - -
Year 1 3462873 -6544161 3462873 0.8333 2885728
Year 2 3975128 -2569033 7438001 0.6944 2760506
Year 3 3962370 1393337 11400371 0.5787 2293038
Year 4 3243202 4636539 14643573 0.4823 1564044
TOTAL 9503315


The Net NPV after 4 years is -503719

At 20% discount rate the NPV is negative (9503315 - 10007034 ) so ideally we can't select the project if macro and micro factors don't allow financial managers of Azza Fahmy to discount cash flow at lower discount rates such as 15%.





Acceptance Criteria of a Project based on NPV

Simplest Approach – If the investment project of Azza Fahmy has a NPV value higher than Zero then finance managers at Azza Fahmy can ACCEPT the project, otherwise they can reject the project. This means that project will deliver higher returns over the period of time than any alternate investment strategy.

In theory if the required rate of return or discount rate is chosen correctly by finance managers at Azza Fahmy, then the stock price of the Azza Fahmy should change by same amount of the NPV. In real world we know that share price also reflects various other factors that can be related to both macro and micro environment.

In the same vein – accepting the project with zero NPV should result in stagnant share price. Finance managers use discount rates as a measure of risk components in the project execution process.

Sensitivity Analysis

Project selection is often a far more complex decision than just choosing it based on the NPV number. Finance managers at Azza Fahmy should conduct a sensitivity analysis to better understand not only the inherent risk of the projects but also how those risks can be either factored in or mitigated during the project execution. Sensitivity analysis helps in –

What are the key aspects of the projects that need to be monitored, refined, and retuned for continuous delivery of projected cash flows.

What can impact the cash flow of the project.

What are the uncertainties surrounding the project Initial Cash Outlay (ICO’s). ICO’s often have several different components such as land, machinery, building, and other equipment.

What will be a multi year spillover effect of various taxation regulations.

Understanding of risks involved in the project.

Some of the assumptions while using the Discounted Cash Flow Methods –

Projects are assumed to be Mutually Exclusive – This is seldom the came in modern day giant organizations where projects are often inter-related and rejecting a project solely based on NPV can result in sunk cost from a related project.

Independent projects have independent cash flows – As explained in the marketing project – though the project may look independent but in reality it is not as the brand awareness project can be closely associated with the spending on sales promotions and product specific advertising.






Negotiation Strategy of Azza Fahmy Jewellery: Expand Locally or Internationally?

References & Further Readings

Marina Apaydin, Hend Mostafa, Mariam Mohamed Sherin, Mariam Ali Mobarak (2018), "Azza Fahmy Jewellery: Expand Locally or Internationally? Harvard Business Review Case Study. Published by HBR Publications.


Nanoom Tech SWOT Analysis / TOWS Matrix

Healthcare , Medical Equipment & Supplies


SOCAM Development SWOT Analysis / TOWS Matrix

Capital Goods , Construction Services


Reclaim Constrcn A SWOT Analysis / TOWS Matrix

Capital Goods , Construction Services


EMCORE SWOT Analysis / TOWS Matrix

Technology , Semiconductors


Dan Hotels SWOT Analysis / TOWS Matrix

Services , Hotels & Motels


N Brown Group SWOT Analysis / TOWS Matrix

Services , Retail (Catalog & Mail Order)


Conduent SWOT Analysis / TOWS Matrix

Technology , Computer Services


DSC Investment SWOT Analysis / TOWS Matrix

Financial , Misc. Financial Services


Suedzucker SWOT Analysis / TOWS Matrix

Consumer/Non-Cyclical , Food Processing