Enterprise: Infrastructure Maintenance Services in the U.K. Net Present Value (NPV) / MBA Resources

Introduction to Net Present Value (NPV) - What is Net Present Value (NPV) ? How it impacts financial decisions regarding project management?

NPV solution for Enterprise: Infrastructure Maintenance Services in the U.K. case study


At Oak Spring University, we provide corporate level professional Net Present Value (NPV) case study solution. Enterprise: Infrastructure Maintenance Services in the U.K. case study is a Harvard Business School (HBR) case study written by James Costantini. The Enterprise: Infrastructure Maintenance Services in the U.K. (referred as “Enterprise Focus” from here on) case study provides evaluation & decision scenario in field of Strategy & Execution. It also touches upon business topics such as - Value proposition, Operations management, Reorganization, Strategy.

The net present value (NPV) of an investment proposal is the present value of the proposal’s net cash flows less the proposal’s initial cash outflow. If a project’s NPV is greater than or equal to zero, the project should be accepted.

NPV = Present Value of Future Cash Flows LESS Project’s Initial Investment






Case Description of Enterprise: Infrastructure Maintenance Services in the U.K. Case Study


The focus of the case is on Enterprise, a firm operating within part of the UK facilities management industry. Set in 2012, the focus is on how Enterprise should respond to changes in market conditions, including the ongoing effects of the 2008 financial crisis, and competitor strategies.


Case Authors : James Costantini

Topic : Strategy & Execution

Related Areas : Operations management, Reorganization, Strategy




Calculating Net Present Value (NPV) at 6% for Enterprise: Infrastructure Maintenance Services in the U.K. Case Study


Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 6 %
Discounted
Cash Flows
Year 0 (10003580) -10003580 - -
Year 1 3448788 -6554792 3448788 0.9434 3253574
Year 2 3973186 -2581606 7421974 0.89 3536121
Year 3 3940774 1359168 11362748 0.8396 3308750
Year 4 3243936 4603104 14606684 0.7921 2569501
TOTAL 14606684 12667946




The Net Present Value at 6% discount rate is 2664366

In isolation the NPV number doesn't mean much but put in right context then it is one of the best method to evaluate project returns. In this article we will cover -

Different methods of capital budgeting


What is NPV & Formula of NPV,
How it is calculated,
How to use NPV number for project evaluation, and
Scenario Planning given risks and management priorities.




Capital Budgeting Approaches

Methods of Capital Budgeting


There are four types of capital budgeting techniques that are widely used in the corporate world –

1. Net Present Value
2. Payback Period
3. Profitability Index
4. Internal Rate of Return

Apart from the Payback period method which is an additive method, rest of the methods are based on Discounted Cash Flow technique. Even though cash flow can be calculated based on the nature of the project, for the simplicity of the article we are assuming that all the expected cash flows are realized at the end of the year.

Discounted Cash Flow approaches provide a more objective basis for evaluating and selecting investment projects. They take into consideration both –

1. Magnitude of both incoming and outgoing cash flows – Projects can be capital intensive, time intensive, or both. Enterprise Focus shareholders have preference for diversified projects investment rather than prospective high income from a single capital intensive project.
2. Timing of the expected cash flows – stockholders of Enterprise Focus have higher preference for cash returns over 4-5 years rather than 10-15 years given the nature of the volatility in the industry.






Formula and Steps to Calculate Net Present Value (NPV) of Enterprise: Infrastructure Maintenance Services in the U.K.

NPV = Net Cash In Flowt1 / (1+r)t1 + Net Cash In Flowt2 / (1+r)t2 + … Net Cash In Flowtn / (1+r)tn
Less Net Cash Out Flowt0 / (1+r)t0

Where t = time period, in this case year 1, year 2 and so on.
r = discount rate or return that could be earned using other safe proposition such as fixed deposit or treasury bond rate. Net Cash In Flow – What the firm will get each year.
Net Cash Out Flow – What the firm needs to invest initially in the project.

Step 1 – Understand the nature of the project and calculate cash flow for each year.
Step 2 – Discount those cash flow based on the discount rate.
Step 3 – Add all the discounted cash flow.
Step 4 – Selection of the project

Why Strategy & Execution Managers need to know Financial Tools such as Net Present Value (NPV)?

In our daily workplace we often come across people and colleagues who are just focused on their core competency and targets they have to deliver. For example marketing managers at Enterprise Focus often design programs whose objective is to drive brand awareness and customer reach. But how that 30 point increase in brand awareness or 10 point increase in customer touch points will result into shareholders’ value is not specified.

To overcome such scenarios managers at Enterprise Focus needs to not only know the financial aspect of project management but also needs to have tools to integrate them into part of the project development and monitoring plan.

Calculating Net Present Value (NPV) at 15%

After working through various assumptions we reached a conclusion that risk is far higher than 6%. In a reasonably stable industry with weak competition - 15% discount rate can be a good benchmark.



Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 15 %
Discounted
Cash Flows
Year 0 (10003580) -10003580 - -
Year 1 3448788 -6554792 3448788 0.8696 2998946
Year 2 3973186 -2581606 7421974 0.7561 3004299
Year 3 3940774 1359168 11362748 0.6575 2591123
Year 4 3243936 4603104 14606684 0.5718 1854731
TOTAL 10449099


The Net NPV after 4 years is 445519

(10449099 - 10003580 )








Calculating Net Present Value (NPV) at 20%


If the risk component is high in the industry then we should go for a higher hurdle rate / discount rate of 20%.

Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 20 %
Discounted
Cash Flows
Year 0 (10003580) -10003580 - -
Year 1 3448788 -6554792 3448788 0.8333 2873990
Year 2 3973186 -2581606 7421974 0.6944 2759157
Year 3 3940774 1359168 11362748 0.5787 2280541
Year 4 3243936 4603104 14606684 0.4823 1564398
TOTAL 9478086


The Net NPV after 4 years is -525494

At 20% discount rate the NPV is negative (9478086 - 10003580 ) so ideally we can't select the project if macro and micro factors don't allow financial managers of Enterprise Focus to discount cash flow at lower discount rates such as 15%.





Acceptance Criteria of a Project based on NPV

Simplest Approach – If the investment project of Enterprise Focus has a NPV value higher than Zero then finance managers at Enterprise Focus can ACCEPT the project, otherwise they can reject the project. This means that project will deliver higher returns over the period of time than any alternate investment strategy.

In theory if the required rate of return or discount rate is chosen correctly by finance managers at Enterprise Focus, then the stock price of the Enterprise Focus should change by same amount of the NPV. In real world we know that share price also reflects various other factors that can be related to both macro and micro environment.

In the same vein – accepting the project with zero NPV should result in stagnant share price. Finance managers use discount rates as a measure of risk components in the project execution process.

Sensitivity Analysis

Project selection is often a far more complex decision than just choosing it based on the NPV number. Finance managers at Enterprise Focus should conduct a sensitivity analysis to better understand not only the inherent risk of the projects but also how those risks can be either factored in or mitigated during the project execution. Sensitivity analysis helps in –

What are the uncertainties surrounding the project Initial Cash Outlay (ICO’s). ICO’s often have several different components such as land, machinery, building, and other equipment.

What will be a multi year spillover effect of various taxation regulations.

What are the key aspects of the projects that need to be monitored, refined, and retuned for continuous delivery of projected cash flows.

What can impact the cash flow of the project.

Understanding of risks involved in the project.

Some of the assumptions while using the Discounted Cash Flow Methods –

Projects are assumed to be Mutually Exclusive – This is seldom the came in modern day giant organizations where projects are often inter-related and rejecting a project solely based on NPV can result in sunk cost from a related project.

Independent projects have independent cash flows – As explained in the marketing project – though the project may look independent but in reality it is not as the brand awareness project can be closely associated with the spending on sales promotions and product specific advertising.






Negotiation Strategy of Enterprise: Infrastructure Maintenance Services in the U.K.

References & Further Readings

James Costantini (2018), "Enterprise: Infrastructure Maintenance Services in the U.K. Harvard Business Review Case Study. Published by HBR Publications.


Beijing Tong Ren Tang SWOT Analysis / TOWS Matrix

Healthcare , Biotechnology & Drugs


Franco-Nevada SWOT Analysis / TOWS Matrix

Financial , Misc. Financial Services


GYG SWOT Analysis / TOWS Matrix

Transportation , Water Transportation


Piedmont Office SWOT Analysis / TOWS Matrix

Services , Real Estate Operations


FSA Group SWOT Analysis / TOWS Matrix

Financial , Consumer Financial Services


JSP Corp SWOT Analysis / TOWS Matrix

Basic Materials , Containers & Packaging


JTI SWOT Analysis / TOWS Matrix

Financial , Misc. Financial Services


Insigma SWOT Analysis / TOWS Matrix

Technology , Communications Equipment