Pushing the Envelope: Engine Development and Procurement for the F-15 Fighter Jet (B) Net Present Value (NPV) / MBA Resources

Introduction to Net Present Value (NPV) - What is Net Present Value (NPV) ? How it impacts financial decisions regarding project management?

NPV solution for Pushing the Envelope: Engine Development and Procurement for the F-15 Fighter Jet (B) case study


At Oak Spring University, we provide corporate level professional Net Present Value (NPV) case study solution. Pushing the Envelope: Engine Development and Procurement for the F-15 Fighter Jet (B) case study is a Harvard Business School (HBR) case study written by Matthias Hild, Keith J. Crocker. The Pushing the Envelope: Engine Development and Procurement for the F-15 Fighter Jet (B) (referred as “Engine Pratt” from here on) case study provides evaluation & decision scenario in field of Strategy & Execution. It also touches upon business topics such as - Value proposition, Negotiations, Risk management, Technology.

The net present value (NPV) of an investment proposal is the present value of the proposal’s net cash flows less the proposal’s initial cash outflow. If a project’s NPV is greater than or equal to zero, the project should be accepted.

NPV = Present Value of Future Cash Flows LESS Project’s Initial Investment






Case Description of Pushing the Envelope: Engine Development and Procurement for the F-15 Fighter Jet (B) Case Study


The B case recounts the events that culminated in the development of an alternative to Pratt and Whitney's F100 jet engine. Following an initial development program, the Air Force announced a split order for 120 engines from General Electric for the F-16 and 40 engines from Pratt and Whitney for the F-15. While this order would only meet the needs for the year 1985, Secretary of the Air Force Verne Orr had decided to hold off on any long-term commitments and to observe contractor performance and field experience during the first year. A few days later, the Navy chose General Electric's F110 engine as a replacement for Pratt's TF30 in the F-14. See also the A (UV3883) and C (UV3886) cases.


Case Authors : Matthias Hild, Keith J. Crocker

Topic : Strategy & Execution

Related Areas : Negotiations, Risk management, Technology




Calculating Net Present Value (NPV) at 6% for Pushing the Envelope: Engine Development and Procurement for the F-15 Fighter Jet (B) Case Study


Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 6 %
Discounted
Cash Flows
Year 0 (10015174) -10015174 - -
Year 1 3455070 -6560104 3455070 0.9434 3259500
Year 2 3972219 -2587885 7427289 0.89 3535261
Year 3 3945868 1357983 11373157 0.8396 3313027
Year 4 3230276 4588259 14603433 0.7921 2558681
TOTAL 14603433 12666469




The Net Present Value at 6% discount rate is 2651295

In isolation the NPV number doesn't mean much but put in right context then it is one of the best method to evaluate project returns. In this article we will cover -

Different methods of capital budgeting


What is NPV & Formula of NPV,
How it is calculated,
How to use NPV number for project evaluation, and
Scenario Planning given risks and management priorities.




Capital Budgeting Approaches

Methods of Capital Budgeting


There are four types of capital budgeting techniques that are widely used in the corporate world –

1. Profitability Index
2. Internal Rate of Return
3. Net Present Value
4. Payback Period

Apart from the Payback period method which is an additive method, rest of the methods are based on Discounted Cash Flow technique. Even though cash flow can be calculated based on the nature of the project, for the simplicity of the article we are assuming that all the expected cash flows are realized at the end of the year.

Discounted Cash Flow approaches provide a more objective basis for evaluating and selecting investment projects. They take into consideration both –

1. Magnitude of both incoming and outgoing cash flows – Projects can be capital intensive, time intensive, or both. Engine Pratt shareholders have preference for diversified projects investment rather than prospective high income from a single capital intensive project.
2. Timing of the expected cash flows – stockholders of Engine Pratt have higher preference for cash returns over 4-5 years rather than 10-15 years given the nature of the volatility in the industry.






Formula and Steps to Calculate Net Present Value (NPV) of Pushing the Envelope: Engine Development and Procurement for the F-15 Fighter Jet (B)

NPV = Net Cash In Flowt1 / (1+r)t1 + Net Cash In Flowt2 / (1+r)t2 + … Net Cash In Flowtn / (1+r)tn
Less Net Cash Out Flowt0 / (1+r)t0

Where t = time period, in this case year 1, year 2 and so on.
r = discount rate or return that could be earned using other safe proposition such as fixed deposit or treasury bond rate. Net Cash In Flow – What the firm will get each year.
Net Cash Out Flow – What the firm needs to invest initially in the project.

Step 1 – Understand the nature of the project and calculate cash flow for each year.
Step 2 – Discount those cash flow based on the discount rate.
Step 3 – Add all the discounted cash flow.
Step 4 – Selection of the project

Why Strategy & Execution Managers need to know Financial Tools such as Net Present Value (NPV)?

In our daily workplace we often come across people and colleagues who are just focused on their core competency and targets they have to deliver. For example marketing managers at Engine Pratt often design programs whose objective is to drive brand awareness and customer reach. But how that 30 point increase in brand awareness or 10 point increase in customer touch points will result into shareholders’ value is not specified.

To overcome such scenarios managers at Engine Pratt needs to not only know the financial aspect of project management but also needs to have tools to integrate them into part of the project development and monitoring plan.

Calculating Net Present Value (NPV) at 15%

After working through various assumptions we reached a conclusion that risk is far higher than 6%. In a reasonably stable industry with weak competition - 15% discount rate can be a good benchmark.



Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 15 %
Discounted
Cash Flows
Year 0 (10015174) -10015174 - -
Year 1 3455070 -6560104 3455070 0.8696 3004409
Year 2 3972219 -2587885 7427289 0.7561 3003568
Year 3 3945868 1357983 11373157 0.6575 2594472
Year 4 3230276 4588259 14603433 0.5718 1846921
TOTAL 10449370


The Net NPV after 4 years is 434196

(10449370 - 10015174 )








Calculating Net Present Value (NPV) at 20%


If the risk component is high in the industry then we should go for a higher hurdle rate / discount rate of 20%.

Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 20 %
Discounted
Cash Flows
Year 0 (10015174) -10015174 - -
Year 1 3455070 -6560104 3455070 0.8333 2879225
Year 2 3972219 -2587885 7427289 0.6944 2758485
Year 3 3945868 1357983 11373157 0.5787 2283488
Year 4 3230276 4588259 14603433 0.4823 1557811
TOTAL 9479009


The Net NPV after 4 years is -536165

At 20% discount rate the NPV is negative (9479009 - 10015174 ) so ideally we can't select the project if macro and micro factors don't allow financial managers of Engine Pratt to discount cash flow at lower discount rates such as 15%.





Acceptance Criteria of a Project based on NPV

Simplest Approach – If the investment project of Engine Pratt has a NPV value higher than Zero then finance managers at Engine Pratt can ACCEPT the project, otherwise they can reject the project. This means that project will deliver higher returns over the period of time than any alternate investment strategy.

In theory if the required rate of return or discount rate is chosen correctly by finance managers at Engine Pratt, then the stock price of the Engine Pratt should change by same amount of the NPV. In real world we know that share price also reflects various other factors that can be related to both macro and micro environment.

In the same vein – accepting the project with zero NPV should result in stagnant share price. Finance managers use discount rates as a measure of risk components in the project execution process.

Sensitivity Analysis

Project selection is often a far more complex decision than just choosing it based on the NPV number. Finance managers at Engine Pratt should conduct a sensitivity analysis to better understand not only the inherent risk of the projects but also how those risks can be either factored in or mitigated during the project execution. Sensitivity analysis helps in –

What are the key aspects of the projects that need to be monitored, refined, and retuned for continuous delivery of projected cash flows.

What will be a multi year spillover effect of various taxation regulations.

What can impact the cash flow of the project.

What are the uncertainties surrounding the project Initial Cash Outlay (ICO’s). ICO’s often have several different components such as land, machinery, building, and other equipment.

Understanding of risks involved in the project.

Some of the assumptions while using the Discounted Cash Flow Methods –

Projects are assumed to be Mutually Exclusive – This is seldom the came in modern day giant organizations where projects are often inter-related and rejecting a project solely based on NPV can result in sunk cost from a related project.

Independent projects have independent cash flows – As explained in the marketing project – though the project may look independent but in reality it is not as the brand awareness project can be closely associated with the spending on sales promotions and product specific advertising.






Negotiation Strategy of Pushing the Envelope: Engine Development and Procurement for the F-15 Fighter Jet (B)

References & Further Readings

Matthias Hild, Keith J. Crocker (2018), "Pushing the Envelope: Engine Development and Procurement for the F-15 Fighter Jet (B) Harvard Business Review Case Study. Published by HBR Publications.


Keisei Electric Railway SWOT Analysis / TOWS Matrix

Transportation , Misc. Transportation


Prosperity Intl HK SWOT Analysis / TOWS Matrix

Basic Materials , Misc. Fabricated Products


Mcpherson'S Ltd SWOT Analysis / TOWS Matrix

Consumer Cyclical , Jewelry & Silverware


Tahoe Resources SWOT Analysis / TOWS Matrix

Basic Materials , Gold & Silver


Indraprastha Gas SWOT Analysis / TOWS Matrix

Utilities , Natural Gas Utilities


Fridenson SWOT Analysis / TOWS Matrix

Transportation , Misc. Transportation


Fireangel Safety Tech SWOT Analysis / TOWS Matrix

Technology , Scientific & Technical Instr.


Provention Bio SWOT Analysis / TOWS Matrix

Healthcare , Biotechnology & Drugs