Vandelay Industries, Inc., Spanish Version Net Present Value (NPV) / MBA Resources

Introduction to Net Present Value (NPV) - What is Net Present Value (NPV) ? How it impacts financial decisions regarding project management?

NPV solution for Vandelay Industries, Inc., Spanish Version case study


At Oak Spring University, we provide corporate level professional Net Present Value (NPV) case study solution. Vandelay Industries, Inc., Spanish Version case study is a Harvard Business School (HBR) case study written by David M. Upton, Andrew McAfee. The Vandelay Industries, Inc., Spanish Version (referred as “Vandelay Ics” from here on) case study provides evaluation & decision scenario in field of Technology & Operations. It also touches upon business topics such as - Value proposition, Change management, Data, IT, Manufacturing.

The net present value (NPV) of an investment proposal is the present value of the proposal’s net cash flows less the proposal’s initial cash outflow. If a project’s NPV is greater than or equal to zero, the project should be accepted.

NPV = Present Value of Future Cash Flows LESS Project’s Initial Investment






Case Description of Vandelay Industries, Inc., Spanish Version Case Study


An ICS consultant considers issues at the start of a full-scale implementation of SAP software for a large client. The enterprise resource planning (ERP) software will integrate previously fragmented business processes and so must be supported by the entire client organization.


Case Authors : David M. Upton, Andrew McAfee

Topic : Technology & Operations

Related Areas : Change management, Data, IT, Manufacturing




Calculating Net Present Value (NPV) at 6% for Vandelay Industries, Inc., Spanish Version Case Study


Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 6 %
Discounted
Cash Flows
Year 0 (10019615) -10019615 - -
Year 1 3454447 -6565168 3454447 0.9434 3258912
Year 2 3960238 -2604930 7414685 0.89 3524598
Year 3 3949839 1344909 11364524 0.8396 3316361
Year 4 3230641 4575550 14595165 0.7921 2558970
TOTAL 14595165 12658841




The Net Present Value at 6% discount rate is 2639226

In isolation the NPV number doesn't mean much but put in right context then it is one of the best method to evaluate project returns. In this article we will cover -

Different methods of capital budgeting


What is NPV & Formula of NPV,
How it is calculated,
How to use NPV number for project evaluation, and
Scenario Planning given risks and management priorities.




Capital Budgeting Approaches

Methods of Capital Budgeting


There are four types of capital budgeting techniques that are widely used in the corporate world –

1. Payback Period
2. Internal Rate of Return
3. Net Present Value
4. Profitability Index

Apart from the Payback period method which is an additive method, rest of the methods are based on Discounted Cash Flow technique. Even though cash flow can be calculated based on the nature of the project, for the simplicity of the article we are assuming that all the expected cash flows are realized at the end of the year.

Discounted Cash Flow approaches provide a more objective basis for evaluating and selecting investment projects. They take into consideration both –

1. Magnitude of both incoming and outgoing cash flows – Projects can be capital intensive, time intensive, or both. Vandelay Ics shareholders have preference for diversified projects investment rather than prospective high income from a single capital intensive project.
2. Timing of the expected cash flows – stockholders of Vandelay Ics have higher preference for cash returns over 4-5 years rather than 10-15 years given the nature of the volatility in the industry.






Formula and Steps to Calculate Net Present Value (NPV) of Vandelay Industries, Inc., Spanish Version

NPV = Net Cash In Flowt1 / (1+r)t1 + Net Cash In Flowt2 / (1+r)t2 + … Net Cash In Flowtn / (1+r)tn
Less Net Cash Out Flowt0 / (1+r)t0

Where t = time period, in this case year 1, year 2 and so on.
r = discount rate or return that could be earned using other safe proposition such as fixed deposit or treasury bond rate. Net Cash In Flow – What the firm will get each year.
Net Cash Out Flow – What the firm needs to invest initially in the project.

Step 1 – Understand the nature of the project and calculate cash flow for each year.
Step 2 – Discount those cash flow based on the discount rate.
Step 3 – Add all the discounted cash flow.
Step 4 – Selection of the project

Why Technology & Operations Managers need to know Financial Tools such as Net Present Value (NPV)?

In our daily workplace we often come across people and colleagues who are just focused on their core competency and targets they have to deliver. For example marketing managers at Vandelay Ics often design programs whose objective is to drive brand awareness and customer reach. But how that 30 point increase in brand awareness or 10 point increase in customer touch points will result into shareholders’ value is not specified.

To overcome such scenarios managers at Vandelay Ics needs to not only know the financial aspect of project management but also needs to have tools to integrate them into part of the project development and monitoring plan.

Calculating Net Present Value (NPV) at 15%

After working through various assumptions we reached a conclusion that risk is far higher than 6%. In a reasonably stable industry with weak competition - 15% discount rate can be a good benchmark.



Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 15 %
Discounted
Cash Flows
Year 0 (10019615) -10019615 - -
Year 1 3454447 -6565168 3454447 0.8696 3003867
Year 2 3960238 -2604930 7414685 0.7561 2994509
Year 3 3949839 1344909 11364524 0.6575 2597083
Year 4 3230641 4575550 14595165 0.5718 1847129
TOTAL 10442589


The Net NPV after 4 years is 422974

(10442589 - 10019615 )








Calculating Net Present Value (NPV) at 20%


If the risk component is high in the industry then we should go for a higher hurdle rate / discount rate of 20%.

Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 20 %
Discounted
Cash Flows
Year 0 (10019615) -10019615 - -
Year 1 3454447 -6565168 3454447 0.8333 2878706
Year 2 3960238 -2604930 7414685 0.6944 2750165
Year 3 3949839 1344909 11364524 0.5787 2285786
Year 4 3230641 4575550 14595165 0.4823 1557987
TOTAL 9472644


The Net NPV after 4 years is -546971

At 20% discount rate the NPV is negative (9472644 - 10019615 ) so ideally we can't select the project if macro and micro factors don't allow financial managers of Vandelay Ics to discount cash flow at lower discount rates such as 15%.





Acceptance Criteria of a Project based on NPV

Simplest Approach – If the investment project of Vandelay Ics has a NPV value higher than Zero then finance managers at Vandelay Ics can ACCEPT the project, otherwise they can reject the project. This means that project will deliver higher returns over the period of time than any alternate investment strategy.

In theory if the required rate of return or discount rate is chosen correctly by finance managers at Vandelay Ics, then the stock price of the Vandelay Ics should change by same amount of the NPV. In real world we know that share price also reflects various other factors that can be related to both macro and micro environment.

In the same vein – accepting the project with zero NPV should result in stagnant share price. Finance managers use discount rates as a measure of risk components in the project execution process.

Sensitivity Analysis

Project selection is often a far more complex decision than just choosing it based on the NPV number. Finance managers at Vandelay Ics should conduct a sensitivity analysis to better understand not only the inherent risk of the projects but also how those risks can be either factored in or mitigated during the project execution. Sensitivity analysis helps in –

What will be a multi year spillover effect of various taxation regulations.

What can impact the cash flow of the project.

What are the uncertainties surrounding the project Initial Cash Outlay (ICO’s). ICO’s often have several different components such as land, machinery, building, and other equipment.

What are the key aspects of the projects that need to be monitored, refined, and retuned for continuous delivery of projected cash flows.

Understanding of risks involved in the project.

Some of the assumptions while using the Discounted Cash Flow Methods –

Projects are assumed to be Mutually Exclusive – This is seldom the came in modern day giant organizations where projects are often inter-related and rejecting a project solely based on NPV can result in sunk cost from a related project.

Independent projects have independent cash flows – As explained in the marketing project – though the project may look independent but in reality it is not as the brand awareness project can be closely associated with the spending on sales promotions and product specific advertising.






Negotiation Strategy of Vandelay Industries, Inc., Spanish Version

References & Further Readings

David M. Upton, Andrew McAfee (2018), "Vandelay Industries, Inc., Spanish Version Harvard Business Review Case Study. Published by HBR Publications.


Fortum ADR SWOT Analysis / TOWS Matrix

Utilities , Electric Utilities


Digitech SWOT Analysis / TOWS Matrix

Technology , Software & Programming


Adherium Ltd SWOT Analysis / TOWS Matrix

Healthcare , Medical Equipment & Supplies


Wong’s Intl SWOT Analysis / TOWS Matrix

Technology , Electronic Instr. & Controls


Posco M-Tech SWOT Analysis / TOWS Matrix

Services , Business Services


Cree SWOT Analysis / TOWS Matrix

Technology , Semiconductors


Valbiotis SWOT Analysis / TOWS Matrix

Healthcare , Biotechnology & Drugs


Pharma Mar SWOT Analysis / TOWS Matrix

Healthcare , Biotechnology & Drugs


Ability SWOT Analysis / TOWS Matrix

Financial , Misc. Financial Services


Kam Hing Intl SWOT Analysis / TOWS Matrix

Consumer Cyclical , Textiles - Non Apparel


Veidekke SWOT Analysis / TOWS Matrix

Capital Goods , Constr. - Supplies & Fixtures