×




407 ETR Highway Extension: Material Procurement Net Present Value (NPV) / MBA Resources

Introduction to Net Present Value (NPV) - What is Net Present Value (NPV) ? How it impacts financial decisions regarding project management?

NPV solution for 407 ETR Highway Extension: Material Procurement case study


At Oak Spring University, we provide corporate level professional Net Present Value (NPV) case study solution. 407 ETR Highway Extension: Material Procurement case study is a Harvard Business School (HBR) case study written by Peter C. Bell, Carlos Planelles, Liana Rintoul, Christoff Boshoff. The 407 ETR Highway Extension: Material Procurement (referred as “Highway 407” from here on) case study provides evaluation & decision scenario in field of Leadership & Managing People. It also touches upon business topics such as - Value proposition, .

The net present value (NPV) of an investment proposal is the present value of the proposal’s net cash flows less the proposal’s initial cash outflow. If a project’s NPV is greater than or equal to zero, the project should be accepted.

NPV = Present Value of Future Cash Flows LESS Project’s Initial Investment






Case Description of 407 ETR Highway Extension: Material Procurement Case Study


In April 2016, the chairman of the partnership charged with building the $1 billion Highway 407 East Extension Phase 2 in Ontario was reviewing an e-mail from the procurement team that recommended allocation of more than $45 million in contracts for the purchase of granular base material for the highway construction. He knew that the procurement team had worked for several weeks to negotiate and analyze the supplier's quotes, but after reviewing the recommendation, the chairman wondered whether the team's recommendation captured the optimal supplier mix and the most cost-effective selection of suppliers. It was certainly a good solution, but was it the optimal solution? Even with an experienced team, this was a difficult optimization problem to solve.


Case Authors : Peter C. Bell, Carlos Planelles, Liana Rintoul, Christoff Boshoff

Topic : Leadership & Managing People

Related Areas :




Calculating Net Present Value (NPV) at 6% for 407 ETR Highway Extension: Material Procurement Case Study


Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 6 %
Discounted
Cash Flows
Year 0 (10029778) -10029778 - -
Year 1 3451935 -6577843 3451935 0.9434 3256542
Year 2 3964225 -2613618 7416160 0.89 3528146
Year 3 3954916 1341298 11371076 0.8396 3320624
Year 4 3223860 4565158 14594936 0.7921 2553599
TOTAL 14594936 12658911




The Net Present Value at 6% discount rate is 2629133

In isolation the NPV number doesn't mean much but put in right context then it is one of the best method to evaluate project returns. In this article we will cover -

Different methods of capital budgeting


What is NPV & Formula of NPV,
How it is calculated,
How to use NPV number for project evaluation, and
Scenario Planning given risks and management priorities.




Capital Budgeting Approaches

Methods of Capital Budgeting


There are four types of capital budgeting techniques that are widely used in the corporate world –

1. Internal Rate of Return
2. Net Present Value
3. Profitability Index
4. Payback Period

Apart from the Payback period method which is an additive method, rest of the methods are based on Discounted Cash Flow technique. Even though cash flow can be calculated based on the nature of the project, for the simplicity of the article we are assuming that all the expected cash flows are realized at the end of the year.

Discounted Cash Flow approaches provide a more objective basis for evaluating and selecting investment projects. They take into consideration both –

1. Magnitude of both incoming and outgoing cash flows – Projects can be capital intensive, time intensive, or both. Highway 407 shareholders have preference for diversified projects investment rather than prospective high income from a single capital intensive project.
2. Timing of the expected cash flows – stockholders of Highway 407 have higher preference for cash returns over 4-5 years rather than 10-15 years given the nature of the volatility in the industry.






Formula and Steps to Calculate Net Present Value (NPV) of 407 ETR Highway Extension: Material Procurement

NPV = Net Cash In Flowt1 / (1+r)t1 + Net Cash In Flowt2 / (1+r)t2 + … Net Cash In Flowtn / (1+r)tn
Less Net Cash Out Flowt0 / (1+r)t0

Where t = time period, in this case year 1, year 2 and so on.
r = discount rate or return that could be earned using other safe proposition such as fixed deposit or treasury bond rate. Net Cash In Flow – What the firm will get each year.
Net Cash Out Flow – What the firm needs to invest initially in the project.

Step 1 – Understand the nature of the project and calculate cash flow for each year.
Step 2 – Discount those cash flow based on the discount rate.
Step 3 – Add all the discounted cash flow.
Step 4 – Selection of the project

Why Leadership & Managing People Managers need to know Financial Tools such as Net Present Value (NPV)?

In our daily workplace we often come across people and colleagues who are just focused on their core competency and targets they have to deliver. For example marketing managers at Highway 407 often design programs whose objective is to drive brand awareness and customer reach. But how that 30 point increase in brand awareness or 10 point increase in customer touch points will result into shareholders’ value is not specified.

To overcome such scenarios managers at Highway 407 needs to not only know the financial aspect of project management but also needs to have tools to integrate them into part of the project development and monitoring plan.

Calculating Net Present Value (NPV) at 15%

After working through various assumptions we reached a conclusion that risk is far higher than 6%. In a reasonably stable industry with weak competition - 15% discount rate can be a good benchmark.



Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 15 %
Discounted
Cash Flows
Year 0 (10029778) -10029778 - -
Year 1 3451935 -6577843 3451935 0.8696 3001683
Year 2 3964225 -2613618 7416160 0.7561 2997524
Year 3 3954916 1341298 11371076 0.6575 2600421
Year 4 3223860 4565158 14594936 0.5718 1843252
TOTAL 10442880


The Net NPV after 4 years is 413102

(10442880 - 10029778 )








Calculating Net Present Value (NPV) at 20%


If the risk component is high in the industry then we should go for a higher hurdle rate / discount rate of 20%.

Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 20 %
Discounted
Cash Flows
Year 0 (10029778) -10029778 - -
Year 1 3451935 -6577843 3451935 0.8333 2876613
Year 2 3964225 -2613618 7416160 0.6944 2752934
Year 3 3954916 1341298 11371076 0.5787 2288725
Year 4 3223860 4565158 14594936 0.4823 1554716
TOTAL 9472988


The Net NPV after 4 years is -556791

At 20% discount rate the NPV is negative (9472988 - 10029778 ) so ideally we can't select the project if macro and micro factors don't allow financial managers of Highway 407 to discount cash flow at lower discount rates such as 15%.





Acceptance Criteria of a Project based on NPV

Simplest Approach – If the investment project of Highway 407 has a NPV value higher than Zero then finance managers at Highway 407 can ACCEPT the project, otherwise they can reject the project. This means that project will deliver higher returns over the period of time than any alternate investment strategy.

In theory if the required rate of return or discount rate is chosen correctly by finance managers at Highway 407, then the stock price of the Highway 407 should change by same amount of the NPV. In real world we know that share price also reflects various other factors that can be related to both macro and micro environment.

In the same vein – accepting the project with zero NPV should result in stagnant share price. Finance managers use discount rates as a measure of risk components in the project execution process.

Sensitivity Analysis

Project selection is often a far more complex decision than just choosing it based on the NPV number. Finance managers at Highway 407 should conduct a sensitivity analysis to better understand not only the inherent risk of the projects but also how those risks can be either factored in or mitigated during the project execution. Sensitivity analysis helps in –

What will be a multi year spillover effect of various taxation regulations.

What are the key aspects of the projects that need to be monitored, refined, and retuned for continuous delivery of projected cash flows.

What can impact the cash flow of the project.

Understanding of risks involved in the project.

What are the uncertainties surrounding the project Initial Cash Outlay (ICO’s). ICO’s often have several different components such as land, machinery, building, and other equipment.

Some of the assumptions while using the Discounted Cash Flow Methods –

Projects are assumed to be Mutually Exclusive – This is seldom the came in modern day giant organizations where projects are often inter-related and rejecting a project solely based on NPV can result in sunk cost from a related project.

Independent projects have independent cash flows – As explained in the marketing project – though the project may look independent but in reality it is not as the brand awareness project can be closely associated with the spending on sales promotions and product specific advertising.






Negotiation Strategy of 407 ETR Highway Extension: Material Procurement

References & Further Readings

Peter C. Bell, Carlos Planelles, Liana Rintoul, Christoff Boshoff (2018), "407 ETR Highway Extension: Material Procurement Harvard Business Review Case Study. Published by HBR Publications.


LendingClub Corp SWOT Analysis / TOWS Matrix

Financial , Consumer Financial Services


Bang&Olufsen SWOT Analysis / TOWS Matrix

Consumer Cyclical , Audio & Video Equipment


Ilyang Pharm SWOT Analysis / TOWS Matrix

Healthcare , Biotechnology & Drugs


Pan-Pacific SWOT Analysis / TOWS Matrix

Consumer Cyclical , Apparel/Accessories


D4t4 Solutions SWOT Analysis / TOWS Matrix

Technology , Software & Programming


Terregra Asia SWOT Analysis / TOWS Matrix

Utilities , Electric Utilities


Immersion Corp SWOT Analysis / TOWS Matrix

Technology , Software & Programming


Ctd Holdings Inc SWOT Analysis / TOWS Matrix

Healthcare , Biotechnology & Drugs


Kubota ADR SWOT Analysis / TOWS Matrix

Capital Goods , Constr. & Agric. Machinery


Conroy SWOT Analysis / TOWS Matrix

Basic Materials , Gold & Silver