Christine Lagarde (A): A French Prime Minister Calls Net Present Value (NPV) / MBA Resources

Introduction to Net Present Value (NPV) - What is Net Present Value (NPV) ? How it impacts financial decisions regarding project management?

NPV solution for Christine Lagarde (A): A French Prime Minister Calls case study


At Oak Spring University, we provide corporate level professional Net Present Value (NPV) case study solution. Christine Lagarde (A): A French Prime Minister Calls case study is a Harvard Business School (HBR) case study written by Julie Battilana, Carin-Isabel Knoop. The Christine Lagarde (A): A French Prime Minister Calls (referred as “Christine Lagarde” from here on) case study provides evaluation & decision scenario in field of Organizational Development. It also touches upon business topics such as - Value proposition, .

The net present value (NPV) of an investment proposal is the present value of the proposal’s net cash flows less the proposal’s initial cash outflow. If a project’s NPV is greater than or equal to zero, the project should be accepted.

NPV = Present Value of Future Cash Flows LESS Project’s Initial Investment






Case Description of Christine Lagarde (A): A French Prime Minister Calls Case Study


This case covers formative events and influences in Christine Lagarde's childhood and her trajectory from studying political science and law to heading the world's largest law firm. As she prepares to transition back to practice in 2005, the new Prime Minister of France calls to offer her a ministerial position in the new Cabinet. She has to decide whether she wants to take on a role in the public sector. For coverage of her career from 2005 to 2011, see Christine Lagarde (B): Being a Public Servant (419018). For coverage of her career from 2011 to 2018, see Christine Lagarde (C): Managing the IMF (419019). For comprehensive coverage of her evolution and career, see Christine Lagarde (419016).


Case Authors : Julie Battilana, Carin-Isabel Knoop

Topic : Organizational Development

Related Areas :




Calculating Net Present Value (NPV) at 6% for Christine Lagarde (A): A French Prime Minister Calls Case Study


Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 6 %
Discounted
Cash Flows
Year 0 (10023609) -10023609 - -
Year 1 3451399 -6572210 3451399 0.9434 3256037
Year 2 3955574 -2616636 7406973 0.89 3520447
Year 3 3960415 1343779 11367388 0.8396 3325241
Year 4 3232787 4576566 14600175 0.7921 2560670
TOTAL 14600175 12662394




The Net Present Value at 6% discount rate is 2638785

In isolation the NPV number doesn't mean much but put in right context then it is one of the best method to evaluate project returns. In this article we will cover -

Different methods of capital budgeting


What is NPV & Formula of NPV,
How it is calculated,
How to use NPV number for project evaluation, and
Scenario Planning given risks and management priorities.




Capital Budgeting Approaches

Methods of Capital Budgeting


There are four types of capital budgeting techniques that are widely used in the corporate world –

1. Internal Rate of Return
2. Payback Period
3. Net Present Value
4. Profitability Index

Apart from the Payback period method which is an additive method, rest of the methods are based on Discounted Cash Flow technique. Even though cash flow can be calculated based on the nature of the project, for the simplicity of the article we are assuming that all the expected cash flows are realized at the end of the year.

Discounted Cash Flow approaches provide a more objective basis for evaluating and selecting investment projects. They take into consideration both –

1. Timing of the expected cash flows – stockholders of Christine Lagarde have higher preference for cash returns over 4-5 years rather than 10-15 years given the nature of the volatility in the industry.
2. Magnitude of both incoming and outgoing cash flows – Projects can be capital intensive, time intensive, or both. Christine Lagarde shareholders have preference for diversified projects investment rather than prospective high income from a single capital intensive project.






Formula and Steps to Calculate Net Present Value (NPV) of Christine Lagarde (A): A French Prime Minister Calls

NPV = Net Cash In Flowt1 / (1+r)t1 + Net Cash In Flowt2 / (1+r)t2 + … Net Cash In Flowtn / (1+r)tn
Less Net Cash Out Flowt0 / (1+r)t0

Where t = time period, in this case year 1, year 2 and so on.
r = discount rate or return that could be earned using other safe proposition such as fixed deposit or treasury bond rate. Net Cash In Flow – What the firm will get each year.
Net Cash Out Flow – What the firm needs to invest initially in the project.

Step 1 – Understand the nature of the project and calculate cash flow for each year.
Step 2 – Discount those cash flow based on the discount rate.
Step 3 – Add all the discounted cash flow.
Step 4 – Selection of the project

Why Organizational Development Managers need to know Financial Tools such as Net Present Value (NPV)?

In our daily workplace we often come across people and colleagues who are just focused on their core competency and targets they have to deliver. For example marketing managers at Christine Lagarde often design programs whose objective is to drive brand awareness and customer reach. But how that 30 point increase in brand awareness or 10 point increase in customer touch points will result into shareholders’ value is not specified.

To overcome such scenarios managers at Christine Lagarde needs to not only know the financial aspect of project management but also needs to have tools to integrate them into part of the project development and monitoring plan.

Calculating Net Present Value (NPV) at 15%

After working through various assumptions we reached a conclusion that risk is far higher than 6%. In a reasonably stable industry with weak competition - 15% discount rate can be a good benchmark.



Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 15 %
Discounted
Cash Flows
Year 0 (10023609) -10023609 - -
Year 1 3451399 -6572210 3451399 0.8696 3001217
Year 2 3955574 -2616636 7406973 0.7561 2990982
Year 3 3960415 1343779 11367388 0.6575 2604037
Year 4 3232787 4576566 14600175 0.5718 1848356
TOTAL 10444592


The Net NPV after 4 years is 420983

(10444592 - 10023609 )








Calculating Net Present Value (NPV) at 20%


If the risk component is high in the industry then we should go for a higher hurdle rate / discount rate of 20%.

Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 20 %
Discounted
Cash Flows
Year 0 (10023609) -10023609 - -
Year 1 3451399 -6572210 3451399 0.8333 2876166
Year 2 3955574 -2616636 7406973 0.6944 2746926
Year 3 3960415 1343779 11367388 0.5787 2291907
Year 4 3232787 4576566 14600175 0.4823 1559022
TOTAL 9474021


The Net NPV after 4 years is -549588

At 20% discount rate the NPV is negative (9474021 - 10023609 ) so ideally we can't select the project if macro and micro factors don't allow financial managers of Christine Lagarde to discount cash flow at lower discount rates such as 15%.





Acceptance Criteria of a Project based on NPV

Simplest Approach – If the investment project of Christine Lagarde has a NPV value higher than Zero then finance managers at Christine Lagarde can ACCEPT the project, otherwise they can reject the project. This means that project will deliver higher returns over the period of time than any alternate investment strategy.

In theory if the required rate of return or discount rate is chosen correctly by finance managers at Christine Lagarde, then the stock price of the Christine Lagarde should change by same amount of the NPV. In real world we know that share price also reflects various other factors that can be related to both macro and micro environment.

In the same vein – accepting the project with zero NPV should result in stagnant share price. Finance managers use discount rates as a measure of risk components in the project execution process.

Sensitivity Analysis

Project selection is often a far more complex decision than just choosing it based on the NPV number. Finance managers at Christine Lagarde should conduct a sensitivity analysis to better understand not only the inherent risk of the projects but also how those risks can be either factored in or mitigated during the project execution. Sensitivity analysis helps in –

What can impact the cash flow of the project.

What are the key aspects of the projects that need to be monitored, refined, and retuned for continuous delivery of projected cash flows.

Understanding of risks involved in the project.

What are the uncertainties surrounding the project Initial Cash Outlay (ICO’s). ICO’s often have several different components such as land, machinery, building, and other equipment.

What will be a multi year spillover effect of various taxation regulations.

Some of the assumptions while using the Discounted Cash Flow Methods –

Projects are assumed to be Mutually Exclusive – This is seldom the came in modern day giant organizations where projects are often inter-related and rejecting a project solely based on NPV can result in sunk cost from a related project.

Independent projects have independent cash flows – As explained in the marketing project – though the project may look independent but in reality it is not as the brand awareness project can be closely associated with the spending on sales promotions and product specific advertising.






Negotiation Strategy of Christine Lagarde (A): A French Prime Minister Calls

References & Further Readings

Julie Battilana, Carin-Isabel Knoop (2018), "Christine Lagarde (A): A French Prime Minister Calls Harvard Business Review Case Study. Published by HBR Publications.


Nishikawa Keisoku SWOT Analysis / TOWS Matrix

Capital Goods , Constr. & Agric. Machinery


Nakamoto Packs Co SWOT Analysis / TOWS Matrix

Basic Materials , Containers & Packaging


Best Pacific Intl SWOT Analysis / TOWS Matrix

Consumer Cyclical , Textiles - Non Apparel


Toscana Energy SWOT Analysis / TOWS Matrix

Energy , Oil & Gas - Integrated


Tokyo Dome Corp. SWOT Analysis / TOWS Matrix

Services , Recreational Activities


JB & ZJMY SWOT Analysis / TOWS Matrix

Consumer Cyclical , Auto & Truck Parts


Cri Middleware SWOT Analysis / TOWS Matrix

Technology , Software & Programming


Sekonic SWOT Analysis / TOWS Matrix

Technology , Office Equipment