Maple Leaf Hardware Limited Net Present Value (NPV) / MBA Resources

Introduction to Net Present Value (NPV) - What is Net Present Value (NPV) ? How it impacts financial decisions regarding project management?

NPV solution for Maple Leaf Hardware Limited case study


At Oak Spring University, we provide corporate level professional Net Present Value (NPV) case study solution. Maple Leaf Hardware Limited case study is a Harvard Business School (HBR) case study written by Stephen R. Foerster, Richard H. Mimick. The Maple Leaf Hardware Limited (referred as “Leaf Maple” from here on) case study provides evaluation & decision scenario in field of Finance & Accounting. It also touches upon business topics such as - Value proposition, .

The net present value (NPV) of an investment proposal is the present value of the proposal’s net cash flows less the proposal’s initial cash outflow. If a project’s NPV is greater than or equal to zero, the project should be accepted.

NPV = Present Value of Future Cash Flows LESS Project’s Initial Investment






Case Description of Maple Leaf Hardware Limited Case Study


Mr. Stuart Foreman, assistant manager of the London, Ontario branch of the Central Canadian Bank, was reviewing information he had received from Maple Leaf Hardware Limited. Mr. Robert Patrick, president and manager of Maple Leaf Hardware Limited had requested an increase in his line of credit with the bank to cover seasonal working capital needs. Mr. Foreman, who had just received a transfer and promotion to the London branch, realized he would have to evaluate the request carefully.


Case Authors : Stephen R. Foerster, Richard H. Mimick

Topic : Finance & Accounting

Related Areas :




Calculating Net Present Value (NPV) at 6% for Maple Leaf Hardware Limited Case Study


Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 6 %
Discounted
Cash Flows
Year 0 (10024041) -10024041 - -
Year 1 3456835 -6567206 3456835 0.9434 3261165
Year 2 3979153 -2588053 7435988 0.89 3541432
Year 3 3943638 1355585 11379626 0.8396 3311155
Year 4 3240567 4596152 14620193 0.7921 2566833
TOTAL 14620193 12680584




The Net Present Value at 6% discount rate is 2656543

In isolation the NPV number doesn't mean much but put in right context then it is one of the best method to evaluate project returns. In this article we will cover -

Different methods of capital budgeting


What is NPV & Formula of NPV,
How it is calculated,
How to use NPV number for project evaluation, and
Scenario Planning given risks and management priorities.




Capital Budgeting Approaches

Methods of Capital Budgeting


There are four types of capital budgeting techniques that are widely used in the corporate world –

1. Internal Rate of Return
2. Net Present Value
3. Payback Period
4. Profitability Index

Apart from the Payback period method which is an additive method, rest of the methods are based on Discounted Cash Flow technique. Even though cash flow can be calculated based on the nature of the project, for the simplicity of the article we are assuming that all the expected cash flows are realized at the end of the year.

Discounted Cash Flow approaches provide a more objective basis for evaluating and selecting investment projects. They take into consideration both –

1. Magnitude of both incoming and outgoing cash flows – Projects can be capital intensive, time intensive, or both. Leaf Maple shareholders have preference for diversified projects investment rather than prospective high income from a single capital intensive project.
2. Timing of the expected cash flows – stockholders of Leaf Maple have higher preference for cash returns over 4-5 years rather than 10-15 years given the nature of the volatility in the industry.






Formula and Steps to Calculate Net Present Value (NPV) of Maple Leaf Hardware Limited

NPV = Net Cash In Flowt1 / (1+r)t1 + Net Cash In Flowt2 / (1+r)t2 + … Net Cash In Flowtn / (1+r)tn
Less Net Cash Out Flowt0 / (1+r)t0

Where t = time period, in this case year 1, year 2 and so on.
r = discount rate or return that could be earned using other safe proposition such as fixed deposit or treasury bond rate. Net Cash In Flow – What the firm will get each year.
Net Cash Out Flow – What the firm needs to invest initially in the project.

Step 1 – Understand the nature of the project and calculate cash flow for each year.
Step 2 – Discount those cash flow based on the discount rate.
Step 3 – Add all the discounted cash flow.
Step 4 – Selection of the project

Why Finance & Accounting Managers need to know Financial Tools such as Net Present Value (NPV)?

In our daily workplace we often come across people and colleagues who are just focused on their core competency and targets they have to deliver. For example marketing managers at Leaf Maple often design programs whose objective is to drive brand awareness and customer reach. But how that 30 point increase in brand awareness or 10 point increase in customer touch points will result into shareholders’ value is not specified.

To overcome such scenarios managers at Leaf Maple needs to not only know the financial aspect of project management but also needs to have tools to integrate them into part of the project development and monitoring plan.

Calculating Net Present Value (NPV) at 15%

After working through various assumptions we reached a conclusion that risk is far higher than 6%. In a reasonably stable industry with weak competition - 15% discount rate can be a good benchmark.



Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 15 %
Discounted
Cash Flows
Year 0 (10024041) -10024041 - -
Year 1 3456835 -6567206 3456835 0.8696 3005943
Year 2 3979153 -2588053 7435988 0.7561 3008811
Year 3 3943638 1355585 11379626 0.6575 2593006
Year 4 3240567 4596152 14620193 0.5718 1852805
TOTAL 10460566


The Net NPV after 4 years is 436525

(10460566 - 10024041 )








Calculating Net Present Value (NPV) at 20%


If the risk component is high in the industry then we should go for a higher hurdle rate / discount rate of 20%.

Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 20 %
Discounted
Cash Flows
Year 0 (10024041) -10024041 - -
Year 1 3456835 -6567206 3456835 0.8333 2880696
Year 2 3979153 -2588053 7435988 0.6944 2763301
Year 3 3943638 1355585 11379626 0.5787 2282198
Year 4 3240567 4596152 14620193 0.4823 1562773
TOTAL 9488968


The Net NPV after 4 years is -535073

At 20% discount rate the NPV is negative (9488968 - 10024041 ) so ideally we can't select the project if macro and micro factors don't allow financial managers of Leaf Maple to discount cash flow at lower discount rates such as 15%.





Acceptance Criteria of a Project based on NPV

Simplest Approach – If the investment project of Leaf Maple has a NPV value higher than Zero then finance managers at Leaf Maple can ACCEPT the project, otherwise they can reject the project. This means that project will deliver higher returns over the period of time than any alternate investment strategy.

In theory if the required rate of return or discount rate is chosen correctly by finance managers at Leaf Maple, then the stock price of the Leaf Maple should change by same amount of the NPV. In real world we know that share price also reflects various other factors that can be related to both macro and micro environment.

In the same vein – accepting the project with zero NPV should result in stagnant share price. Finance managers use discount rates as a measure of risk components in the project execution process.

Sensitivity Analysis

Project selection is often a far more complex decision than just choosing it based on the NPV number. Finance managers at Leaf Maple should conduct a sensitivity analysis to better understand not only the inherent risk of the projects but also how those risks can be either factored in or mitigated during the project execution. Sensitivity analysis helps in –

What are the key aspects of the projects that need to be monitored, refined, and retuned for continuous delivery of projected cash flows.

What will be a multi year spillover effect of various taxation regulations.

Understanding of risks involved in the project.

What are the uncertainties surrounding the project Initial Cash Outlay (ICO’s). ICO’s often have several different components such as land, machinery, building, and other equipment.

What can impact the cash flow of the project.

Some of the assumptions while using the Discounted Cash Flow Methods –

Projects are assumed to be Mutually Exclusive – This is seldom the came in modern day giant organizations where projects are often inter-related and rejecting a project solely based on NPV can result in sunk cost from a related project.

Independent projects have independent cash flows – As explained in the marketing project – though the project may look independent but in reality it is not as the brand awareness project can be closely associated with the spending on sales promotions and product specific advertising.






Negotiation Strategy of Maple Leaf Hardware Limited

References & Further Readings

Stephen R. Foerster, Richard H. Mimick (2018), "Maple Leaf Hardware Limited Harvard Business Review Case Study. Published by HBR Publications.


MPLX LP SWOT Analysis / TOWS Matrix

Energy , Oil Well Services & Equipment


Trimetals Mining SWOT Analysis / TOWS Matrix

Basic Materials , Gold & Silver


Buymyplace Com SWOT Analysis / TOWS Matrix

Services , Real Estate Operations


LC SWOT Analysis / TOWS Matrix

Services , Real Estate Operations


Alam Maritim Res SWOT Analysis / TOWS Matrix

Energy , Oil Well Services & Equipment


Samyung ENC SWOT Analysis / TOWS Matrix

Technology , Communications Equipment


Hingtex SWOT Analysis / TOWS Matrix

Consumer Cyclical , Textiles - Non Apparel


Deoleo SWOT Analysis / TOWS Matrix

Consumer/Non-Cyclical , Food Processing