Valjibhai Stones Net Present Value (NPV) / MBA Resources

Introduction to Net Present Value (NPV) - What is Net Present Value (NPV) ? How it impacts financial decisions regarding project management?

NPV solution for Valjibhai Stones case study


At Oak Spring University, we provide corporate level professional Net Present Value (NPV) case study solution. Valjibhai Stones case study is a Harvard Business School (HBR) case study written by Debashis Sanyal, Smita Mazumdar. The Valjibhai Stones (referred as “Valjibhai Stones” from here on) case study provides evaluation & decision scenario in field of Finance & Accounting. It also touches upon business topics such as - Value proposition, Competitive strategy, Costs, Entrepreneurship, International business.

The net present value (NPV) of an investment proposal is the present value of the proposal’s net cash flows less the proposal’s initial cash outflow. If a project’s NPV is greater than or equal to zero, the project should be accepted.

NPV = Present Value of Future Cash Flows LESS Project’s Initial Investment






Case Description of Valjibhai Stones Case Study


Valjibhai Stones, a supplier of quality stone chips in India, has been approached by a multinational company that needs a reliable supplier of quality stone chips for the next eight years. Accepting the order would require a capacity expansion to produce high-quality aggregate solely for the multinational company and at the cost of foregoing all of its existing business. If the offer is accepted, the company would earn substantial revenue for eight years, but would then need to seek fresh business in a highly competitive market.


Case Authors : Debashis Sanyal, Smita Mazumdar

Topic : Finance & Accounting

Related Areas : Competitive strategy, Costs, Entrepreneurship, International business




Calculating Net Present Value (NPV) at 6% for Valjibhai Stones Case Study


Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 6 %
Discounted
Cash Flows
Year 0 (10011649) -10011649 - -
Year 1 3455682 -6555967 3455682 0.9434 3260077
Year 2 3970630 -2585337 7426312 0.89 3533847
Year 3 3959944 1374607 11386256 0.8396 3324845
Year 4 3226698 4601305 14612954 0.7921 2555847
TOTAL 14612954 12674616




The Net Present Value at 6% discount rate is 2662967

In isolation the NPV number doesn't mean much but put in right context then it is one of the best method to evaluate project returns. In this article we will cover -

Different methods of capital budgeting


What is NPV & Formula of NPV,
How it is calculated,
How to use NPV number for project evaluation, and
Scenario Planning given risks and management priorities.




Capital Budgeting Approaches

Methods of Capital Budgeting


There are four types of capital budgeting techniques that are widely used in the corporate world –

1. Internal Rate of Return
2. Payback Period
3. Net Present Value
4. Profitability Index

Apart from the Payback period method which is an additive method, rest of the methods are based on Discounted Cash Flow technique. Even though cash flow can be calculated based on the nature of the project, for the simplicity of the article we are assuming that all the expected cash flows are realized at the end of the year.

Discounted Cash Flow approaches provide a more objective basis for evaluating and selecting investment projects. They take into consideration both –

1. Timing of the expected cash flows – stockholders of Valjibhai Stones have higher preference for cash returns over 4-5 years rather than 10-15 years given the nature of the volatility in the industry.
2. Magnitude of both incoming and outgoing cash flows – Projects can be capital intensive, time intensive, or both. Valjibhai Stones shareholders have preference for diversified projects investment rather than prospective high income from a single capital intensive project.






Formula and Steps to Calculate Net Present Value (NPV) of Valjibhai Stones

NPV = Net Cash In Flowt1 / (1+r)t1 + Net Cash In Flowt2 / (1+r)t2 + … Net Cash In Flowtn / (1+r)tn
Less Net Cash Out Flowt0 / (1+r)t0

Where t = time period, in this case year 1, year 2 and so on.
r = discount rate or return that could be earned using other safe proposition such as fixed deposit or treasury bond rate. Net Cash In Flow – What the firm will get each year.
Net Cash Out Flow – What the firm needs to invest initially in the project.

Step 1 – Understand the nature of the project and calculate cash flow for each year.
Step 2 – Discount those cash flow based on the discount rate.
Step 3 – Add all the discounted cash flow.
Step 4 – Selection of the project

Why Finance & Accounting Managers need to know Financial Tools such as Net Present Value (NPV)?

In our daily workplace we often come across people and colleagues who are just focused on their core competency and targets they have to deliver. For example marketing managers at Valjibhai Stones often design programs whose objective is to drive brand awareness and customer reach. But how that 30 point increase in brand awareness or 10 point increase in customer touch points will result into shareholders’ value is not specified.

To overcome such scenarios managers at Valjibhai Stones needs to not only know the financial aspect of project management but also needs to have tools to integrate them into part of the project development and monitoring plan.

Calculating Net Present Value (NPV) at 15%

After working through various assumptions we reached a conclusion that risk is far higher than 6%. In a reasonably stable industry with weak competition - 15% discount rate can be a good benchmark.



Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 15 %
Discounted
Cash Flows
Year 0 (10011649) -10011649 - -
Year 1 3455682 -6555967 3455682 0.8696 3004941
Year 2 3970630 -2585337 7426312 0.7561 3002367
Year 3 3959944 1374607 11386256 0.6575 2603727
Year 4 3226698 4601305 14612954 0.5718 1844875
TOTAL 10455910


The Net NPV after 4 years is 444261

(10455910 - 10011649 )








Calculating Net Present Value (NPV) at 20%


If the risk component is high in the industry then we should go for a higher hurdle rate / discount rate of 20%.

Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 20 %
Discounted
Cash Flows
Year 0 (10011649) -10011649 - -
Year 1 3455682 -6555967 3455682 0.8333 2879735
Year 2 3970630 -2585337 7426312 0.6944 2757382
Year 3 3959944 1374607 11386256 0.5787 2291634
Year 4 3226698 4601305 14612954 0.4823 1556085
TOTAL 9484836


The Net NPV after 4 years is -526813

At 20% discount rate the NPV is negative (9484836 - 10011649 ) so ideally we can't select the project if macro and micro factors don't allow financial managers of Valjibhai Stones to discount cash flow at lower discount rates such as 15%.





Acceptance Criteria of a Project based on NPV

Simplest Approach – If the investment project of Valjibhai Stones has a NPV value higher than Zero then finance managers at Valjibhai Stones can ACCEPT the project, otherwise they can reject the project. This means that project will deliver higher returns over the period of time than any alternate investment strategy.

In theory if the required rate of return or discount rate is chosen correctly by finance managers at Valjibhai Stones, then the stock price of the Valjibhai Stones should change by same amount of the NPV. In real world we know that share price also reflects various other factors that can be related to both macro and micro environment.

In the same vein – accepting the project with zero NPV should result in stagnant share price. Finance managers use discount rates as a measure of risk components in the project execution process.

Sensitivity Analysis

Project selection is often a far more complex decision than just choosing it based on the NPV number. Finance managers at Valjibhai Stones should conduct a sensitivity analysis to better understand not only the inherent risk of the projects but also how those risks can be either factored in or mitigated during the project execution. Sensitivity analysis helps in –

What can impact the cash flow of the project.

What are the key aspects of the projects that need to be monitored, refined, and retuned for continuous delivery of projected cash flows.

What are the uncertainties surrounding the project Initial Cash Outlay (ICO’s). ICO’s often have several different components such as land, machinery, building, and other equipment.

Understanding of risks involved in the project.

What will be a multi year spillover effect of various taxation regulations.

Some of the assumptions while using the Discounted Cash Flow Methods –

Projects are assumed to be Mutually Exclusive – This is seldom the came in modern day giant organizations where projects are often inter-related and rejecting a project solely based on NPV can result in sunk cost from a related project.

Independent projects have independent cash flows – As explained in the marketing project – though the project may look independent but in reality it is not as the brand awareness project can be closely associated with the spending on sales promotions and product specific advertising.






Negotiation Strategy of Valjibhai Stones

References & Further Readings

Debashis Sanyal, Smita Mazumdar (2018), "Valjibhai Stones Harvard Business Review Case Study. Published by HBR Publications.


Changchun Gas SWOT Analysis / TOWS Matrix

Utilities , Natural Gas Utilities


Kaneka Corp SWOT Analysis / TOWS Matrix

Basic Materials , Chemical Manufacturing


Rorze SWOT Analysis / TOWS Matrix

Capital Goods , Misc. Capital Goods


Horizontal Software SWOT Analysis / TOWS Matrix

Technology , Software & Programming


Sirius RE SWOT Analysis / TOWS Matrix

Services , Real Estate Operations


Oeneo SWOT Analysis / TOWS Matrix

Capital Goods , Constr. - Supplies & Fixtures