Introduction to Net Present Value (NPV) - What is Net Present Value (NPV) ? How it impacts financial decisions regarding project management?

NPV solution for Continental Media Group: Business Highlights case study


At Oak Spring University, we provide corporate level professional Net Present Value (NPV) case study solution. Continental Media Group: Business Highlights case study is a Harvard Business School (HBR) case study written by Robert L. Simons, Kathryn Rosenberg. The Continental Media Group: Business Highlights (referred as “Continental Interactive” from here on) case study provides evaluation & decision scenario in field of Finance & Accounting. It also touches upon business topics such as - Value proposition, Strategy.

The net present value (NPV) of an investment proposal is the present value of the proposal’s net cash flows less the proposal’s initial cash outflow. If a project’s NPV is greater than or equal to zero, the project should be accepted.

NPV = Present Value of Future Cash Flows LESS Project’s Initial Investment






Case Description of Continental Media Group: Business Highlights Case Study


Continental Media Group has a series of business reviews struggling to achieve profitability. This case focuses on the use of management control systems to identify emerging opportunities and the formulation of new strategies. The interactive system used by top managers-the Friday Packet-is described and illustrated in exhibits. Top managers use this system to focus organizational attention on the critical uncertainties of the business. Provides examples of how new strategies emerge from the dialogue that is generated by the interactive control system.


Case Authors : Robert L. Simons, Kathryn Rosenberg

Topic : Finance & Accounting

Related Areas : Strategy




Calculating Net Present Value (NPV) at 6% for Continental Media Group: Business Highlights Case Study


Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 6 %
Discounted
Cash Flows
Year 0 (10013907) -10013907 - -
Year 1 3446856 -6567051 3446856 0.9434 3251751
Year 2 3979069 -2587982 7425925 0.89 3541357
Year 3 3973300 1385318 11399225 0.8396 3336059
Year 4 3233719 4619037 14632944 0.7921 2561408
TOTAL 14632944 12690576




The Net Present Value at 6% discount rate is 2676669

In isolation the NPV number doesn't mean much but put in right context then it is one of the best method to evaluate project returns. In this article we will cover -

Different methods of capital budgeting


What is NPV & Formula of NPV,
How it is calculated,
How to use NPV number for project evaluation, and
Scenario Planning given risks and management priorities.




Capital Budgeting Approaches

Methods of Capital Budgeting


There are four types of capital budgeting techniques that are widely used in the corporate world –

1. Net Present Value
2. Internal Rate of Return
3. Payback Period
4. Profitability Index

Apart from the Payback period method which is an additive method, rest of the methods are based on Discounted Cash Flow technique. Even though cash flow can be calculated based on the nature of the project, for the simplicity of the article we are assuming that all the expected cash flows are realized at the end of the year.

Discounted Cash Flow approaches provide a more objective basis for evaluating and selecting investment projects. They take into consideration both –

1. Timing of the expected cash flows – stockholders of Continental Interactive have higher preference for cash returns over 4-5 years rather than 10-15 years given the nature of the volatility in the industry.
2. Magnitude of both incoming and outgoing cash flows – Projects can be capital intensive, time intensive, or both. Continental Interactive shareholders have preference for diversified projects investment rather than prospective high income from a single capital intensive project.






Formula and Steps to Calculate Net Present Value (NPV) of Continental Media Group: Business Highlights

NPV = Net Cash In Flowt1 / (1+r)t1 + Net Cash In Flowt2 / (1+r)t2 + … Net Cash In Flowtn / (1+r)tn
Less Net Cash Out Flowt0 / (1+r)t0

Where t = time period, in this case year 1, year 2 and so on.
r = discount rate or return that could be earned using other safe proposition such as fixed deposit or treasury bond rate. Net Cash In Flow – What the firm will get each year.
Net Cash Out Flow – What the firm needs to invest initially in the project.

Step 1 – Understand the nature of the project and calculate cash flow for each year.
Step 2 – Discount those cash flow based on the discount rate.
Step 3 – Add all the discounted cash flow.
Step 4 – Selection of the project

Why Finance & Accounting Managers need to know Financial Tools such as Net Present Value (NPV)?

In our daily workplace we often come across people and colleagues who are just focused on their core competency and targets they have to deliver. For example marketing managers at Continental Interactive often design programs whose objective is to drive brand awareness and customer reach. But how that 30 point increase in brand awareness or 10 point increase in customer touch points will result into shareholders’ value is not specified.

To overcome such scenarios managers at Continental Interactive needs to not only know the financial aspect of project management but also needs to have tools to integrate them into part of the project development and monitoring plan.

Calculating Net Present Value (NPV) at 15%

After working through various assumptions we reached a conclusion that risk is far higher than 6%. In a reasonably stable industry with weak competition - 15% discount rate can be a good benchmark.



Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 15 %
Discounted
Cash Flows
Year 0 (10013907) -10013907 - -
Year 1 3446856 -6567051 3446856 0.8696 2997266
Year 2 3979069 -2587982 7425925 0.7561 3008748
Year 3 3973300 1385318 11399225 0.6575 2612509
Year 4 3233719 4619037 14632944 0.5718 1848889
TOTAL 10467412


The Net NPV after 4 years is 453505

(10467412 - 10013907 )








Calculating Net Present Value (NPV) at 20%


If the risk component is high in the industry then we should go for a higher hurdle rate / discount rate of 20%.

Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 20 %
Discounted
Cash Flows
Year 0 (10013907) -10013907 - -
Year 1 3446856 -6567051 3446856 0.8333 2872380
Year 2 3979069 -2587982 7425925 0.6944 2763242
Year 3 3973300 1385318 11399225 0.5787 2299363
Year 4 3233719 4619037 14632944 0.4823 1559471
TOTAL 9494457


The Net NPV after 4 years is -519450

At 20% discount rate the NPV is negative (9494457 - 10013907 ) so ideally we can't select the project if macro and micro factors don't allow financial managers of Continental Interactive to discount cash flow at lower discount rates such as 15%.





Acceptance Criteria of a Project based on NPV

Simplest Approach – If the investment project of Continental Interactive has a NPV value higher than Zero then finance managers at Continental Interactive can ACCEPT the project, otherwise they can reject the project. This means that project will deliver higher returns over the period of time than any alternate investment strategy.

In theory if the required rate of return or discount rate is chosen correctly by finance managers at Continental Interactive, then the stock price of the Continental Interactive should change by same amount of the NPV. In real world we know that share price also reflects various other factors that can be related to both macro and micro environment.

In the same vein – accepting the project with zero NPV should result in stagnant share price. Finance managers use discount rates as a measure of risk components in the project execution process.

Sensitivity Analysis

Project selection is often a far more complex decision than just choosing it based on the NPV number. Finance managers at Continental Interactive should conduct a sensitivity analysis to better understand not only the inherent risk of the projects but also how those risks can be either factored in or mitigated during the project execution. Sensitivity analysis helps in –

Understanding of risks involved in the project.

What can impact the cash flow of the project.

What will be a multi year spillover effect of various taxation regulations.

What are the uncertainties surrounding the project Initial Cash Outlay (ICO’s). ICO’s often have several different components such as land, machinery, building, and other equipment.

What are the key aspects of the projects that need to be monitored, refined, and retuned for continuous delivery of projected cash flows.

Some of the assumptions while using the Discounted Cash Flow Methods –

Projects are assumed to be Mutually Exclusive – This is seldom the came in modern day giant organizations where projects are often inter-related and rejecting a project solely based on NPV can result in sunk cost from a related project.

Independent projects have independent cash flows – As explained in the marketing project – though the project may look independent but in reality it is not as the brand awareness project can be closely associated with the spending on sales promotions and product specific advertising.






Negotiation Strategy of Continental Media Group: Business Highlights

References & Further Readings

Robert L. Simons, Kathryn Rosenberg (2018), "Continental Media Group: Business Highlights Harvard Business Review Case Study. Published by HBR Publications.


BHP Group SWOT Analysis / TOWS Matrix

Basic Materials , Metal Mining


EMCORE SWOT Analysis / TOWS Matrix

Technology , Semiconductors


Benefit Japan Co SWOT Analysis / TOWS Matrix

Services , Communications Services


Halliburton SWOT Analysis / TOWS Matrix

Energy , Oil Well Services & Equipment


Sekisui House Reit SWOT Analysis / TOWS Matrix

Financial , Misc. Financial Services


JPMorgan Indian SWOT Analysis / TOWS Matrix

Financial , Misc. Financial Services