White Mountain Health Care Net Present Value (NPV) / MBA Resources

Introduction to Net Present Value (NPV) - What is Net Present Value (NPV) ? How it impacts financial decisions regarding project management?

NPV solution for White Mountain Health Care case study


At Oak Spring University, we provide corporate level professional Net Present Value (NPV) case study solution. White Mountain Health Care case study is a Harvard Business School (HBR) case study written by David W. Young. The White Mountain Health Care (referred as “Academic Clinical” from here on) case study provides evaluation & decision scenario in field of Finance & Accounting. It also touches upon business topics such as - Value proposition, Change management.

The net present value (NPV) of an investment proposal is the present value of the proposal’s net cash flows less the proposal’s initial cash outflow. If a project’s NPV is greater than or equal to zero, the project should be accepted.

NPV = Present Value of Future Cash Flows LESS Project’s Initial Investment






Case Description of White Mountain Health Care Case Study


This case is useful in bringing together several different disciplines: strategy, management control, and change management. The organization was a newly formed integrated clinical enterprise that included an academic medical center, a community hospital, and a academic practice plan. It also was tied strategically and financially to a college of medicine. It was attempting to achieve clinical and financial integration between its physician practices and its provider institutions, mainly the medical center, but the effort had been compromised by a budget crisis that had had a detrimental effect on the organization, and had led to mistrust among the physicians, some of whom were considering leaving the organization.


Case Authors : David W. Young

Topic : Finance & Accounting

Related Areas : Change management




Calculating Net Present Value (NPV) at 6% for White Mountain Health Care Case Study


Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 6 %
Discounted
Cash Flows
Year 0 (10024974) -10024974 - -
Year 1 3451259 -6573715 3451259 0.9434 3255905
Year 2 3977542 -2596173 7428801 0.89 3539998
Year 3 3964751 1368578 11393552 0.8396 3328881
Year 4 3251392 4619970 14644944 0.7921 2575407
TOTAL 14644944 12700191




The Net Present Value at 6% discount rate is 2675217

In isolation the NPV number doesn't mean much but put in right context then it is one of the best method to evaluate project returns. In this article we will cover -

Different methods of capital budgeting


What is NPV & Formula of NPV,
How it is calculated,
How to use NPV number for project evaluation, and
Scenario Planning given risks and management priorities.




Capital Budgeting Approaches

Methods of Capital Budgeting


There are four types of capital budgeting techniques that are widely used in the corporate world –

1. Net Present Value
2. Payback Period
3. Profitability Index
4. Internal Rate of Return

Apart from the Payback period method which is an additive method, rest of the methods are based on Discounted Cash Flow technique. Even though cash flow can be calculated based on the nature of the project, for the simplicity of the article we are assuming that all the expected cash flows are realized at the end of the year.

Discounted Cash Flow approaches provide a more objective basis for evaluating and selecting investment projects. They take into consideration both –

1. Magnitude of both incoming and outgoing cash flows – Projects can be capital intensive, time intensive, or both. Academic Clinical shareholders have preference for diversified projects investment rather than prospective high income from a single capital intensive project.
2. Timing of the expected cash flows – stockholders of Academic Clinical have higher preference for cash returns over 4-5 years rather than 10-15 years given the nature of the volatility in the industry.






Formula and Steps to Calculate Net Present Value (NPV) of White Mountain Health Care

NPV = Net Cash In Flowt1 / (1+r)t1 + Net Cash In Flowt2 / (1+r)t2 + … Net Cash In Flowtn / (1+r)tn
Less Net Cash Out Flowt0 / (1+r)t0

Where t = time period, in this case year 1, year 2 and so on.
r = discount rate or return that could be earned using other safe proposition such as fixed deposit or treasury bond rate. Net Cash In Flow – What the firm will get each year.
Net Cash Out Flow – What the firm needs to invest initially in the project.

Step 1 – Understand the nature of the project and calculate cash flow for each year.
Step 2 – Discount those cash flow based on the discount rate.
Step 3 – Add all the discounted cash flow.
Step 4 – Selection of the project

Why Finance & Accounting Managers need to know Financial Tools such as Net Present Value (NPV)?

In our daily workplace we often come across people and colleagues who are just focused on their core competency and targets they have to deliver. For example marketing managers at Academic Clinical often design programs whose objective is to drive brand awareness and customer reach. But how that 30 point increase in brand awareness or 10 point increase in customer touch points will result into shareholders’ value is not specified.

To overcome such scenarios managers at Academic Clinical needs to not only know the financial aspect of project management but also needs to have tools to integrate them into part of the project development and monitoring plan.

Calculating Net Present Value (NPV) at 15%

After working through various assumptions we reached a conclusion that risk is far higher than 6%. In a reasonably stable industry with weak competition - 15% discount rate can be a good benchmark.



Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 15 %
Discounted
Cash Flows
Year 0 (10024974) -10024974 - -
Year 1 3451259 -6573715 3451259 0.8696 3001095
Year 2 3977542 -2596173 7428801 0.7561 3007593
Year 3 3964751 1368578 11393552 0.6575 2606888
Year 4 3251392 4619970 14644944 0.5718 1858994
TOTAL 10474570


The Net NPV after 4 years is 449596

(10474570 - 10024974 )








Calculating Net Present Value (NPV) at 20%


If the risk component is high in the industry then we should go for a higher hurdle rate / discount rate of 20%.

Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 20 %
Discounted
Cash Flows
Year 0 (10024974) -10024974 - -
Year 1 3451259 -6573715 3451259 0.8333 2876049
Year 2 3977542 -2596173 7428801 0.6944 2762182
Year 3 3964751 1368578 11393552 0.5787 2294416
Year 4 3251392 4619970 14644944 0.4823 1567994
TOTAL 9500641


The Net NPV after 4 years is -524333

At 20% discount rate the NPV is negative (9500641 - 10024974 ) so ideally we can't select the project if macro and micro factors don't allow financial managers of Academic Clinical to discount cash flow at lower discount rates such as 15%.





Acceptance Criteria of a Project based on NPV

Simplest Approach – If the investment project of Academic Clinical has a NPV value higher than Zero then finance managers at Academic Clinical can ACCEPT the project, otherwise they can reject the project. This means that project will deliver higher returns over the period of time than any alternate investment strategy.

In theory if the required rate of return or discount rate is chosen correctly by finance managers at Academic Clinical, then the stock price of the Academic Clinical should change by same amount of the NPV. In real world we know that share price also reflects various other factors that can be related to both macro and micro environment.

In the same vein – accepting the project with zero NPV should result in stagnant share price. Finance managers use discount rates as a measure of risk components in the project execution process.

Sensitivity Analysis

Project selection is often a far more complex decision than just choosing it based on the NPV number. Finance managers at Academic Clinical should conduct a sensitivity analysis to better understand not only the inherent risk of the projects but also how those risks can be either factored in or mitigated during the project execution. Sensitivity analysis helps in –

What are the key aspects of the projects that need to be monitored, refined, and retuned for continuous delivery of projected cash flows.

What can impact the cash flow of the project.

What will be a multi year spillover effect of various taxation regulations.

Understanding of risks involved in the project.

What are the uncertainties surrounding the project Initial Cash Outlay (ICO’s). ICO’s often have several different components such as land, machinery, building, and other equipment.

Some of the assumptions while using the Discounted Cash Flow Methods –

Projects are assumed to be Mutually Exclusive – This is seldom the came in modern day giant organizations where projects are often inter-related and rejecting a project solely based on NPV can result in sunk cost from a related project.

Independent projects have independent cash flows – As explained in the marketing project – though the project may look independent but in reality it is not as the brand awareness project can be closely associated with the spending on sales promotions and product specific advertising.






Negotiation Strategy of White Mountain Health Care

References & Further Readings

David W. Young (2018), "White Mountain Health Care Harvard Business Review Case Study. Published by HBR Publications.


Ballantyne Strong SWOT Analysis / TOWS Matrix

Consumer Cyclical , Photography


Valecha Engineering Ltd SWOT Analysis / TOWS Matrix

Capital Goods , Construction Services


AP Eagers SWOT Analysis / TOWS Matrix

Services , Retail (Specialty)


GB Sciences SWOT Analysis / TOWS Matrix

Healthcare , Biotechnology & Drugs


Kingswood SWOT Analysis / TOWS Matrix

Financial , Misc. Financial Services


Molson Coors Brewing B SWOT Analysis / TOWS Matrix

Consumer/Non-Cyclical , Beverages (Alcoholic)


Hyundai Mar&Fi SWOT Analysis / TOWS Matrix

Financial , Insurance (Prop. & Casualty)


Teo Seng Capital SWOT Analysis / TOWS Matrix

Consumer/Non-Cyclical , Fish/Livestock


Primero SWOT Analysis / TOWS Matrix

Capital Goods , Construction Services