Colby General Hospital (A) Net Present Value (NPV) / MBA Resources

Introduction to Net Present Value (NPV) - What is Net Present Value (NPV) ? How it impacts financial decisions regarding project management?

NPV solution for Colby General Hospital (A) case study


At Oak Spring University, we provide corporate level professional Net Present Value (NPV) case study solution. Colby General Hospital (A) case study is a Harvard Business School (HBR) case study written by Robert D. Landel, Derrick Moreira. The Colby General Hospital (A) (referred as “Improvement Systems” from here on) case study provides evaluation & decision scenario in field of Communication. It also touches upon business topics such as - Value proposition, Health.

The net present value (NPV) of an investment proposal is the present value of the proposal’s net cash flows less the proposal’s initial cash outflow. If a project’s NPV is greater than or equal to zero, the project should be accepted.

NPV = Present Value of Future Cash Flows LESS Project’s Initial Investment






Case Description of Colby General Hospital (A) Case Study


This case presents an operating challenge: how does an organization sustain the initial progress achieved through its new quality-improvement system. Nurses and other clinical staff feel that the culture does not support the acknowledgment of mistakes, and the operations manager is trying to ascertain whether this "blame-game" environment is the cause of the improvement slowdown or whether there are other factors. Students are asked to apply systems-thinking tools to reveal their hypotheses of the causes of the improvement problem and to create a stock-flow map of the system structure. A systems-dynamics model can be used in class or as a preparation assignment. The simulation model enables students to develop a deeper understanding of the systems-dynamics behavior. The subsequent cases in the series UV3506 and UV3507; UV3508 is an abridgment of the A, B, and C cases) provide students with opportunities to practice the quantification of systems relationships (dominated by soft variables) and to develop a simulation model.


Case Authors : Robert D. Landel, Derrick Moreira

Topic : Communication

Related Areas : Health




Calculating Net Present Value (NPV) at 6% for Colby General Hospital (A) Case Study


Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 6 %
Discounted
Cash Flows
Year 0 (10008412) -10008412 - -
Year 1 3453671 -6554741 3453671 0.9434 3258180
Year 2 3973661 -2581080 7427332 0.89 3536544
Year 3 3936458 1355378 11363790 0.8396 3305126
Year 4 3239519 4594897 14603309 0.7921 2566002
TOTAL 14603309 12665853




The Net Present Value at 6% discount rate is 2657441

In isolation the NPV number doesn't mean much but put in right context then it is one of the best method to evaluate project returns. In this article we will cover -

Different methods of capital budgeting


What is NPV & Formula of NPV,
How it is calculated,
How to use NPV number for project evaluation, and
Scenario Planning given risks and management priorities.




Capital Budgeting Approaches

Methods of Capital Budgeting


There are four types of capital budgeting techniques that are widely used in the corporate world –

1. Payback Period
2. Profitability Index
3. Net Present Value
4. Internal Rate of Return

Apart from the Payback period method which is an additive method, rest of the methods are based on Discounted Cash Flow technique. Even though cash flow can be calculated based on the nature of the project, for the simplicity of the article we are assuming that all the expected cash flows are realized at the end of the year.

Discounted Cash Flow approaches provide a more objective basis for evaluating and selecting investment projects. They take into consideration both –

1. Magnitude of both incoming and outgoing cash flows – Projects can be capital intensive, time intensive, or both. Improvement Systems shareholders have preference for diversified projects investment rather than prospective high income from a single capital intensive project.
2. Timing of the expected cash flows – stockholders of Improvement Systems have higher preference for cash returns over 4-5 years rather than 10-15 years given the nature of the volatility in the industry.






Formula and Steps to Calculate Net Present Value (NPV) of Colby General Hospital (A)

NPV = Net Cash In Flowt1 / (1+r)t1 + Net Cash In Flowt2 / (1+r)t2 + … Net Cash In Flowtn / (1+r)tn
Less Net Cash Out Flowt0 / (1+r)t0

Where t = time period, in this case year 1, year 2 and so on.
r = discount rate or return that could be earned using other safe proposition such as fixed deposit or treasury bond rate. Net Cash In Flow – What the firm will get each year.
Net Cash Out Flow – What the firm needs to invest initially in the project.

Step 1 – Understand the nature of the project and calculate cash flow for each year.
Step 2 – Discount those cash flow based on the discount rate.
Step 3 – Add all the discounted cash flow.
Step 4 – Selection of the project

Why Communication Managers need to know Financial Tools such as Net Present Value (NPV)?

In our daily workplace we often come across people and colleagues who are just focused on their core competency and targets they have to deliver. For example marketing managers at Improvement Systems often design programs whose objective is to drive brand awareness and customer reach. But how that 30 point increase in brand awareness or 10 point increase in customer touch points will result into shareholders’ value is not specified.

To overcome such scenarios managers at Improvement Systems needs to not only know the financial aspect of project management but also needs to have tools to integrate them into part of the project development and monitoring plan.

Calculating Net Present Value (NPV) at 15%

After working through various assumptions we reached a conclusion that risk is far higher than 6%. In a reasonably stable industry with weak competition - 15% discount rate can be a good benchmark.



Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 15 %
Discounted
Cash Flows
Year 0 (10008412) -10008412 - -
Year 1 3453671 -6554741 3453671 0.8696 3003192
Year 2 3973661 -2581080 7427332 0.7561 3004659
Year 3 3936458 1355378 11363790 0.6575 2588285
Year 4 3239519 4594897 14603309 0.5718 1852206
TOTAL 10448341


The Net NPV after 4 years is 439929

(10448341 - 10008412 )








Calculating Net Present Value (NPV) at 20%


If the risk component is high in the industry then we should go for a higher hurdle rate / discount rate of 20%.

Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 20 %
Discounted
Cash Flows
Year 0 (10008412) -10008412 - -
Year 1 3453671 -6554741 3453671 0.8333 2878059
Year 2 3973661 -2581080 7427332 0.6944 2759487
Year 3 3936458 1355378 11363790 0.5787 2278043
Year 4 3239519 4594897 14603309 0.4823 1562268
TOTAL 9477857


The Net NPV after 4 years is -530555

At 20% discount rate the NPV is negative (9477857 - 10008412 ) so ideally we can't select the project if macro and micro factors don't allow financial managers of Improvement Systems to discount cash flow at lower discount rates such as 15%.





Acceptance Criteria of a Project based on NPV

Simplest Approach – If the investment project of Improvement Systems has a NPV value higher than Zero then finance managers at Improvement Systems can ACCEPT the project, otherwise they can reject the project. This means that project will deliver higher returns over the period of time than any alternate investment strategy.

In theory if the required rate of return or discount rate is chosen correctly by finance managers at Improvement Systems, then the stock price of the Improvement Systems should change by same amount of the NPV. In real world we know that share price also reflects various other factors that can be related to both macro and micro environment.

In the same vein – accepting the project with zero NPV should result in stagnant share price. Finance managers use discount rates as a measure of risk components in the project execution process.

Sensitivity Analysis

Project selection is often a far more complex decision than just choosing it based on the NPV number. Finance managers at Improvement Systems should conduct a sensitivity analysis to better understand not only the inherent risk of the projects but also how those risks can be either factored in or mitigated during the project execution. Sensitivity analysis helps in –

What are the uncertainties surrounding the project Initial Cash Outlay (ICO’s). ICO’s often have several different components such as land, machinery, building, and other equipment.

Understanding of risks involved in the project.

What can impact the cash flow of the project.

What will be a multi year spillover effect of various taxation regulations.

What are the key aspects of the projects that need to be monitored, refined, and retuned for continuous delivery of projected cash flows.

Some of the assumptions while using the Discounted Cash Flow Methods –

Projects are assumed to be Mutually Exclusive – This is seldom the came in modern day giant organizations where projects are often inter-related and rejecting a project solely based on NPV can result in sunk cost from a related project.

Independent projects have independent cash flows – As explained in the marketing project – though the project may look independent but in reality it is not as the brand awareness project can be closely associated with the spending on sales promotions and product specific advertising.






Negotiation Strategy of Colby General Hospital (A)

References & Further Readings

Robert D. Landel, Derrick Moreira (2018), "Colby General Hospital (A) Harvard Business Review Case Study. Published by HBR Publications.


tv2u SWOT Analysis / TOWS Matrix

Technology , Software & Programming


Valirx SWOT Analysis / TOWS Matrix

Healthcare , Biotechnology & Drugs


Guangdong Xiongsu SWOT Analysis / TOWS Matrix

Basic Materials , Fabricated Plastic & Rubber


China Railway SWOT Analysis / TOWS Matrix

Capital Goods , Construction Services


Joyful Honda Co Ltd SWOT Analysis / TOWS Matrix

Services , Retail (Home Improvement)


Astaldi SWOT Analysis / TOWS Matrix

Capital Goods , Construction Services


RUMO ON NM SWOT Analysis / TOWS Matrix

Transportation , Railroads


Sime Darby Plantation SWOT Analysis / TOWS Matrix

Consumer/Non-Cyclical , Food Processing


Ocean Bio-Chem SWOT Analysis / TOWS Matrix

Consumer/Non-Cyclical , Personal & Household Prods.


Daiman Develop SWOT Analysis / TOWS Matrix

Capital Goods , Construction Services