Congoleum Corp. (Abridged) Net Present Value (NPV) / MBA Resources

Introduction to Net Present Value (NPV) - What is Net Present Value (NPV) ? How it impacts financial decisions regarding project management?

NPV solution for Congoleum Corp. (Abridged) case study


At Oak Spring University, we provide corporate level professional Net Present Value (NPV) case study solution. Congoleum Corp. (Abridged) case study is a Harvard Business School (HBR) case study written by William E. Fruhan. The Congoleum Corp. (Abridged) (referred as “D.w Mullins” from here on) case study provides evaluation & decision scenario in field of Finance & Accounting. It also touches upon business topics such as - Value proposition, Financial analysis, Financial management, Mergers & acquisitions, Negotiations.

The net present value (NPV) of an investment proposal is the present value of the proposal’s net cash flows less the proposal’s initial cash outflow. If a project’s NPV is greater than or equal to zero, the project should be accepted.

NPV = Present Value of Future Cash Flows LESS Project’s Initial Investment






Case Description of Congoleum Corp. (Abridged) Case Study


Describes the development and terms of the largest leveraged buyout up to the date of the case. The main problem is to value the positions of the various participants: lenders, equity holders, investment bankers, and management. This is an abridged version of an earlier case by D.W. Mullins, Jr.


Case Authors : William E. Fruhan

Topic : Finance & Accounting

Related Areas : Financial analysis, Financial management, Mergers & acquisitions, Negotiations




Calculating Net Present Value (NPV) at 6% for Congoleum Corp. (Abridged) Case Study


Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 6 %
Discounted
Cash Flows
Year 0 (10023313) -10023313 - -
Year 1 3464819 -6558494 3464819 0.9434 3268697
Year 2 3966684 -2591810 7431503 0.89 3530335
Year 3 3941865 1350055 11373368 0.8396 3309666
Year 4 3250704 4600759 14624072 0.7921 2574862
TOTAL 14624072 12683560




The Net Present Value at 6% discount rate is 2660247

In isolation the NPV number doesn't mean much but put in right context then it is one of the best method to evaluate project returns. In this article we will cover -

Different methods of capital budgeting


What is NPV & Formula of NPV,
How it is calculated,
How to use NPV number for project evaluation, and
Scenario Planning given risks and management priorities.




Capital Budgeting Approaches

Methods of Capital Budgeting


There are four types of capital budgeting techniques that are widely used in the corporate world –

1. Net Present Value
2. Profitability Index
3. Internal Rate of Return
4. Payback Period

Apart from the Payback period method which is an additive method, rest of the methods are based on Discounted Cash Flow technique. Even though cash flow can be calculated based on the nature of the project, for the simplicity of the article we are assuming that all the expected cash flows are realized at the end of the year.

Discounted Cash Flow approaches provide a more objective basis for evaluating and selecting investment projects. They take into consideration both –

1. Timing of the expected cash flows – stockholders of D.w Mullins have higher preference for cash returns over 4-5 years rather than 10-15 years given the nature of the volatility in the industry.
2. Magnitude of both incoming and outgoing cash flows – Projects can be capital intensive, time intensive, or both. D.w Mullins shareholders have preference for diversified projects investment rather than prospective high income from a single capital intensive project.






Formula and Steps to Calculate Net Present Value (NPV) of Congoleum Corp. (Abridged)

NPV = Net Cash In Flowt1 / (1+r)t1 + Net Cash In Flowt2 / (1+r)t2 + … Net Cash In Flowtn / (1+r)tn
Less Net Cash Out Flowt0 / (1+r)t0

Where t = time period, in this case year 1, year 2 and so on.
r = discount rate or return that could be earned using other safe proposition such as fixed deposit or treasury bond rate. Net Cash In Flow – What the firm will get each year.
Net Cash Out Flow – What the firm needs to invest initially in the project.

Step 1 – Understand the nature of the project and calculate cash flow for each year.
Step 2 – Discount those cash flow based on the discount rate.
Step 3 – Add all the discounted cash flow.
Step 4 – Selection of the project

Why Finance & Accounting Managers need to know Financial Tools such as Net Present Value (NPV)?

In our daily workplace we often come across people and colleagues who are just focused on their core competency and targets they have to deliver. For example marketing managers at D.w Mullins often design programs whose objective is to drive brand awareness and customer reach. But how that 30 point increase in brand awareness or 10 point increase in customer touch points will result into shareholders’ value is not specified.

To overcome such scenarios managers at D.w Mullins needs to not only know the financial aspect of project management but also needs to have tools to integrate them into part of the project development and monitoring plan.

Calculating Net Present Value (NPV) at 15%

After working through various assumptions we reached a conclusion that risk is far higher than 6%. In a reasonably stable industry with weak competition - 15% discount rate can be a good benchmark.



Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 15 %
Discounted
Cash Flows
Year 0 (10023313) -10023313 - -
Year 1 3464819 -6558494 3464819 0.8696 3012886
Year 2 3966684 -2591810 7431503 0.7561 2999383
Year 3 3941865 1350055 11373368 0.6575 2591840
Year 4 3250704 4600759 14624072 0.5718 1858601
TOTAL 10462710


The Net NPV after 4 years is 439397

(10462710 - 10023313 )








Calculating Net Present Value (NPV) at 20%


If the risk component is high in the industry then we should go for a higher hurdle rate / discount rate of 20%.

Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 20 %
Discounted
Cash Flows
Year 0 (10023313) -10023313 - -
Year 1 3464819 -6558494 3464819 0.8333 2887349
Year 2 3966684 -2591810 7431503 0.6944 2754642
Year 3 3941865 1350055 11373368 0.5787 2281172
Year 4 3250704 4600759 14624072 0.4823 1567662
TOTAL 9490825


The Net NPV after 4 years is -532488

At 20% discount rate the NPV is negative (9490825 - 10023313 ) so ideally we can't select the project if macro and micro factors don't allow financial managers of D.w Mullins to discount cash flow at lower discount rates such as 15%.





Acceptance Criteria of a Project based on NPV

Simplest Approach – If the investment project of D.w Mullins has a NPV value higher than Zero then finance managers at D.w Mullins can ACCEPT the project, otherwise they can reject the project. This means that project will deliver higher returns over the period of time than any alternate investment strategy.

In theory if the required rate of return or discount rate is chosen correctly by finance managers at D.w Mullins, then the stock price of the D.w Mullins should change by same amount of the NPV. In real world we know that share price also reflects various other factors that can be related to both macro and micro environment.

In the same vein – accepting the project with zero NPV should result in stagnant share price. Finance managers use discount rates as a measure of risk components in the project execution process.

Sensitivity Analysis

Project selection is often a far more complex decision than just choosing it based on the NPV number. Finance managers at D.w Mullins should conduct a sensitivity analysis to better understand not only the inherent risk of the projects but also how those risks can be either factored in or mitigated during the project execution. Sensitivity analysis helps in –

What are the key aspects of the projects that need to be monitored, refined, and retuned for continuous delivery of projected cash flows.

What are the uncertainties surrounding the project Initial Cash Outlay (ICO’s). ICO’s often have several different components such as land, machinery, building, and other equipment.

What can impact the cash flow of the project.

What will be a multi year spillover effect of various taxation regulations.

Understanding of risks involved in the project.

Some of the assumptions while using the Discounted Cash Flow Methods –

Projects are assumed to be Mutually Exclusive – This is seldom the came in modern day giant organizations where projects are often inter-related and rejecting a project solely based on NPV can result in sunk cost from a related project.

Independent projects have independent cash flows – As explained in the marketing project – though the project may look independent but in reality it is not as the brand awareness project can be closely associated with the spending on sales promotions and product specific advertising.






Negotiation Strategy of Congoleum Corp. (Abridged)

References & Further Readings

William E. Fruhan (2018), "Congoleum Corp. (Abridged) Harvard Business Review Case Study. Published by HBR Publications.


Hangzhou Huning SWOT Analysis / TOWS Matrix

Capital Goods , Misc. Capital Goods


Zhejiang Kanglongda Special SWOT Analysis / TOWS Matrix

Consumer Cyclical , Apparel/Accessories


EPIRUS Biopharma SWOT Analysis / TOWS Matrix

Healthcare , Biotechnology & Drugs


Raontec SWOT Analysis / TOWS Matrix

Technology , Electronic Instr. & Controls


Tibet Mineral A SWOT Analysis / TOWS Matrix

Basic Materials , Metal Mining


3Dx Industries Inc SWOT Analysis / TOWS Matrix

Technology , Scientific & Technical Instr.


Asahi Kagaku Kogyo SWOT Analysis / TOWS Matrix

Basic Materials , Fabricated Plastic & Rubber


Zhejiang XinAn Chemical SWOT Analysis / TOWS Matrix

Basic Materials , Chemical Manufacturing


Piaggio&C SWOT Analysis / TOWS Matrix

Consumer Cyclical , Recreational Products


Alam Sutera Realty SWOT Analysis / TOWS Matrix

Capital Goods , Construction Services