Introduction to Net Present Value (NPV) - What is Net Present Value (NPV) ? How it impacts financial decisions regarding project management?
At Oak Spring University, we provide corporate level professional Net Present Value (NPV) case study solution. ChatChat (VC Version) case study is a Harvard Business School (HBR) case study written by Lara Tiedens, Davina Drabkin. The ChatChat (VC Version) (referred as “Capitalists Playing” from here on) case study provides evaluation & decision scenario in field of Leadership & Managing People. It also touches upon business topics such as - Value proposition, Leadership, Negotiations, Venture capital.
The net present value (NPV) of an investment proposal is the present value of the proposal’s net cash flows less the proposal’s initial cash outflow. If a project’s NPV is greater than or equal to zero, the project should be accepted.
This is a role-play case, intended for use in a leadership development course for MBA students. The case has four roles: two for students playing the co-founders of a startup and two for students/coaches playing the venture capitalists deciding whether or not to provide seed funding. There are two versions of the case, one for students playing the co-founders (L-25CF), and one for those playing the venture capitalists (L-25VC). While both versions of the case contain identical background information for the role-play, L-25CF includes additional information that is available only to the co-founders and L-25VC contains additional information that is available only to the venture capitalists. The role-play objectives stated in the case can be accomplished if the students playing the co-founders successfully identify and address the questions and concerns of those playing the venture capitalists. The co-founders must solicit and grasp the underlining concerns of the venture capitalists, decide how to react and address those concerns, and reassure the venture capitalists that a seed investment is worthwhile. All students have the opportunity to demonstrate active listening, inquiry, and feedback regarding the concerns and proposals to address them. All four individuals in the role play have varying objectives and interests and need to manage the expectations and perceptions of the others in a manner that may be assertive, collaborative, or both.
Years | Cash Flow | Net Cash Flow | Cumulative Cash Flow |
Discount Rate @ 6 % |
Discounted Cash Flows |
---|---|---|---|---|---|
Year 0 | (10010178) | -10010178 | - | - | |
Year 1 | 3452108 | -6558070 | 3452108 | 0.9434 | 3256706 |
Year 2 | 3963262 | -2594808 | 7415370 | 0.89 | 3527289 |
Year 3 | 3956757 | 1361949 | 11372127 | 0.8396 | 3322169 |
Year 4 | 3240866 | 4602815 | 14612993 | 0.7921 | 2567069 |
TOTAL | 14612993 | 12673234 |
In isolation the NPV number doesn't mean much but put in right context then it is one of the best method to evaluate project returns. In this article we will cover -
Capital Budgeting Approaches
There are four types of capital budgeting techniques that are widely used in the corporate world –
1. Payback Period
2. Internal Rate of Return
3. Profitability Index
4. Net Present Value
Apart from the Payback period method which is an additive method, rest of the methods are based on
Discounted Cash Flow
technique. Even though cash flow can be calculated based on the nature of the project, for the simplicity of the article we are assuming that all the expected cash flows are realized at the end of the year.
Discounted Cash Flow approaches provide a more objective basis for evaluating and selecting investment projects. They take into consideration both –
1. Timing of the expected cash flows – stockholders of Capitalists Playing have higher preference for cash returns over 4-5 years rather than 10-15 years given the nature of the volatility in the industry.
2. Magnitude of both incoming and outgoing cash flows – Projects can be capital intensive, time intensive, or both. Capitalists Playing shareholders have preference for diversified projects investment rather than prospective high income from a single capital intensive project.
NPV = Net Cash In Flowt1 / (1+r)t1 + Net Cash In Flowt2 / (1+r)t2 + … Net Cash In Flowtn / (1+r)tn
Less Net Cash Out Flowt0 / (1+r)t0
Where t = time period, in this case year 1, year 2 and so on.
r = discount rate or return that could be earned using other safe proposition such as fixed deposit or treasury bond rate.
Net Cash In Flow – What the firm will get each year.
Net Cash Out Flow – What the firm needs to invest initially in the project.
Step 1 – Understand the nature of the project and calculate cash flow for each year.
Step 2 – Discount those cash flow based on the discount rate.
Step 3 – Add all the discounted cash flow.
Step 4 – Selection of the project
In our daily workplace we often come across people and colleagues who are just focused on their core competency and targets they have to deliver. For example marketing managers at Capitalists Playing often design programs whose objective is to drive brand awareness and customer reach. But how that 30 point increase in brand awareness or 10 point increase in customer touch points will result into shareholders’ value is not specified.
To overcome such scenarios managers at Capitalists Playing needs to not only know the financial aspect of project management but also needs to have tools to integrate them into part of the project development and monitoring plan.
After working through various assumptions we reached a conclusion that risk is far higher than 6%. In a reasonably stable industry with weak competition - 15% discount rate can be a good benchmark.
Years | Cash Flow | Net Cash Flow | Cumulative Cash Flow |
Discount Rate @ 15 % |
Discounted Cash Flows |
---|---|---|---|---|---|
Year 0 | (10010178) | -10010178 | - | - | |
Year 1 | 3452108 | -6558070 | 3452108 | 0.8696 | 3001833 |
Year 2 | 3963262 | -2594808 | 7415370 | 0.7561 | 2996795 |
Year 3 | 3956757 | 1361949 | 11372127 | 0.6575 | 2601632 |
Year 4 | 3240866 | 4602815 | 14612993 | 0.5718 | 1852976 |
TOTAL | 10453236 |
(10453236 - 10010178 )
If the risk component is high in the industry then we should go for a higher hurdle rate / discount rate of 20%.
Years | Cash Flow | Net Cash Flow | Cumulative Cash Flow |
Discount Rate @ 20 % |
Discounted Cash Flows |
---|---|---|---|---|---|
Year 0 | (10010178) | -10010178 | - | - | |
Year 1 | 3452108 | -6558070 | 3452108 | 0.8333 | 2876757 |
Year 2 | 3963262 | -2594808 | 7415370 | 0.6944 | 2752265 |
Year 3 | 3956757 | 1361949 | 11372127 | 0.5787 | 2289790 |
Year 4 | 3240866 | 4602815 | 14612993 | 0.4823 | 1562918 |
TOTAL | 9481730 |
At 20% discount rate the NPV is negative (9481730 - 10010178 ) so ideally we can't select the project if macro and micro factors don't allow financial managers of Capitalists Playing to discount cash flow at lower discount rates such as 15%.
Simplest Approach – If the investment project of Capitalists Playing has a NPV value higher than Zero then finance managers at Capitalists Playing can ACCEPT the project, otherwise they can reject the project. This means that project will deliver higher returns over the period of time than any alternate investment strategy.
In theory if the required rate of return or discount rate is chosen correctly by finance managers at Capitalists Playing, then the stock price of the Capitalists Playing should change by same amount of the NPV. In real world we know that share price also reflects various other factors that can be related to both macro and micro environment.
In the same vein – accepting the project with zero NPV should result in stagnant share price. Finance managers use discount rates as a measure of risk components in the project execution process.
Project selection is often a far more complex decision than just choosing it based on the NPV number. Finance managers at Capitalists Playing should conduct a sensitivity analysis to better understand not only the inherent risk of the projects but also how those risks can be either factored in or mitigated during the project execution. Sensitivity analysis helps in –
Understanding of risks involved in the project.
What can impact the cash flow of the project.
What are the uncertainties surrounding the project Initial Cash Outlay (ICO’s). ICO’s often have several different components such as land, machinery, building, and other equipment.
What are the key aspects of the projects that need to be monitored, refined, and retuned for continuous delivery of projected cash flows.
What will be a multi year spillover effect of various taxation regulations.
Projects are assumed to be Mutually Exclusive – This is seldom the came in modern day giant organizations where projects are often inter-related and rejecting a project solely based on NPV can result in sunk cost from a related project.
Independent projects have independent cash flows – As explained in the marketing project – though the project may look independent but in reality it is not as the brand awareness project can be closely associated with the spending on sales promotions and product specific advertising.
Lara Tiedens, Davina Drabkin (2018), "ChatChat (VC Version) Harvard Business Review Case Study. Published by HBR Publications.
Feel free to connect with us if you need business research.
You can download Excel Template of Case Study Solution & Analysis of ChatChat (VC Version)
Services , Business Services
Healthcare , Major Drugs
Consumer/Non-Cyclical , Food Processing
Financial , Investment Services
Healthcare , Biotechnology & Drugs
Technology , Software & Programming
Technology , Computer Services
Basic Materials , Gold & Silver
Services , Business Services
Capital Goods , Construction Services
Utilities , Electric Utilities