Reson: Making Development Teams Accountable for Short Project Cycles Net Present Value (NPV) / MBA Resources

Introduction to Net Present Value (NPV) - What is Net Present Value (NPV) ? How it impacts financial decisions regarding project management?

NPV solution for Reson: Making Development Teams Accountable for Short Project Cycles case study


At Oak Spring University, we provide corporate level professional Net Present Value (NPV) case study solution. Reson: Making Development Teams Accountable for Short Project Cycles case study is a Harvard Business School (HBR) case study written by Thomas E. Vollmann, Jussi Heikkila. The Reson: Making Development Teams Accountable for Short Project Cycles (referred as “Reson's Rethink” from here on) case study provides evaluation & decision scenario in field of Leadership & Managing People. It also touches upon business topics such as - Value proposition, Product development, Project management, Time management.

The net present value (NPV) of an investment proposal is the present value of the proposal’s net cash flows less the proposal’s initial cash outflow. If a project’s NPV is greater than or equal to zero, the project should be accepted.

NPV = Present Value of Future Cash Flows LESS Project’s Initial Investment






Case Description of Reson: Making Development Teams Accountable for Short Project Cycles Case Study


A/S, a Danish company specializing in underwater acoustics and ultrasonics, needs to rethink how it manages new product development. Reson's R&D is working with proprietary basic technologies with development times up to three years. To realize the company's global growth potential, Reson's management must expand its customer base, rethink how to apply proprietary technologies in innovative ways, and bring new customer-specific solutions fast to market. The focus for project management is time, i.e., meeting project deadlines. This sets completely new requirements for project planning and company cooperation.


Case Authors : Thomas E. Vollmann, Jussi Heikkila

Topic : Leadership & Managing People

Related Areas : Product development, Project management, Time management




Calculating Net Present Value (NPV) at 6% for Reson: Making Development Teams Accountable for Short Project Cycles Case Study


Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 6 %
Discounted
Cash Flows
Year 0 (10019879) -10019879 - -
Year 1 3465727 -6554152 3465727 0.9434 3269554
Year 2 3959426 -2594726 7425153 0.89 3523875
Year 3 3950690 1355964 11375843 0.8396 3317076
Year 4 3223871 4579835 14599714 0.7921 2553608
TOTAL 14599714 12664112




The Net Present Value at 6% discount rate is 2644233

In isolation the NPV number doesn't mean much but put in right context then it is one of the best method to evaluate project returns. In this article we will cover -

Different methods of capital budgeting


What is NPV & Formula of NPV,
How it is calculated,
How to use NPV number for project evaluation, and
Scenario Planning given risks and management priorities.




Capital Budgeting Approaches

Methods of Capital Budgeting


There are four types of capital budgeting techniques that are widely used in the corporate world –

1. Payback Period
2. Net Present Value
3. Profitability Index
4. Internal Rate of Return

Apart from the Payback period method which is an additive method, rest of the methods are based on Discounted Cash Flow technique. Even though cash flow can be calculated based on the nature of the project, for the simplicity of the article we are assuming that all the expected cash flows are realized at the end of the year.

Discounted Cash Flow approaches provide a more objective basis for evaluating and selecting investment projects. They take into consideration both –

1. Timing of the expected cash flows – stockholders of Reson's Rethink have higher preference for cash returns over 4-5 years rather than 10-15 years given the nature of the volatility in the industry.
2. Magnitude of both incoming and outgoing cash flows – Projects can be capital intensive, time intensive, or both. Reson's Rethink shareholders have preference for diversified projects investment rather than prospective high income from a single capital intensive project.






Formula and Steps to Calculate Net Present Value (NPV) of Reson: Making Development Teams Accountable for Short Project Cycles

NPV = Net Cash In Flowt1 / (1+r)t1 + Net Cash In Flowt2 / (1+r)t2 + … Net Cash In Flowtn / (1+r)tn
Less Net Cash Out Flowt0 / (1+r)t0

Where t = time period, in this case year 1, year 2 and so on.
r = discount rate or return that could be earned using other safe proposition such as fixed deposit or treasury bond rate. Net Cash In Flow – What the firm will get each year.
Net Cash Out Flow – What the firm needs to invest initially in the project.

Step 1 – Understand the nature of the project and calculate cash flow for each year.
Step 2 – Discount those cash flow based on the discount rate.
Step 3 – Add all the discounted cash flow.
Step 4 – Selection of the project

Why Leadership & Managing People Managers need to know Financial Tools such as Net Present Value (NPV)?

In our daily workplace we often come across people and colleagues who are just focused on their core competency and targets they have to deliver. For example marketing managers at Reson's Rethink often design programs whose objective is to drive brand awareness and customer reach. But how that 30 point increase in brand awareness or 10 point increase in customer touch points will result into shareholders’ value is not specified.

To overcome such scenarios managers at Reson's Rethink needs to not only know the financial aspect of project management but also needs to have tools to integrate them into part of the project development and monitoring plan.

Calculating Net Present Value (NPV) at 15%

After working through various assumptions we reached a conclusion that risk is far higher than 6%. In a reasonably stable industry with weak competition - 15% discount rate can be a good benchmark.



Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 15 %
Discounted
Cash Flows
Year 0 (10019879) -10019879 - -
Year 1 3465727 -6554152 3465727 0.8696 3013676
Year 2 3959426 -2594726 7425153 0.7561 2993895
Year 3 3950690 1355964 11375843 0.6575 2597643
Year 4 3223871 4579835 14599714 0.5718 1843259
TOTAL 10448472


The Net NPV after 4 years is 428593

(10448472 - 10019879 )








Calculating Net Present Value (NPV) at 20%


If the risk component is high in the industry then we should go for a higher hurdle rate / discount rate of 20%.

Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 20 %
Discounted
Cash Flows
Year 0 (10019879) -10019879 - -
Year 1 3465727 -6554152 3465727 0.8333 2888106
Year 2 3959426 -2594726 7425153 0.6944 2749601
Year 3 3950690 1355964 11375843 0.5787 2286279
Year 4 3223871 4579835 14599714 0.4823 1554722
TOTAL 9478708


The Net NPV after 4 years is -541171

At 20% discount rate the NPV is negative (9478708 - 10019879 ) so ideally we can't select the project if macro and micro factors don't allow financial managers of Reson's Rethink to discount cash flow at lower discount rates such as 15%.





Acceptance Criteria of a Project based on NPV

Simplest Approach – If the investment project of Reson's Rethink has a NPV value higher than Zero then finance managers at Reson's Rethink can ACCEPT the project, otherwise they can reject the project. This means that project will deliver higher returns over the period of time than any alternate investment strategy.

In theory if the required rate of return or discount rate is chosen correctly by finance managers at Reson's Rethink, then the stock price of the Reson's Rethink should change by same amount of the NPV. In real world we know that share price also reflects various other factors that can be related to both macro and micro environment.

In the same vein – accepting the project with zero NPV should result in stagnant share price. Finance managers use discount rates as a measure of risk components in the project execution process.

Sensitivity Analysis

Project selection is often a far more complex decision than just choosing it based on the NPV number. Finance managers at Reson's Rethink should conduct a sensitivity analysis to better understand not only the inherent risk of the projects but also how those risks can be either factored in or mitigated during the project execution. Sensitivity analysis helps in –

What can impact the cash flow of the project.

What will be a multi year spillover effect of various taxation regulations.

Understanding of risks involved in the project.

What are the key aspects of the projects that need to be monitored, refined, and retuned for continuous delivery of projected cash flows.

What are the uncertainties surrounding the project Initial Cash Outlay (ICO’s). ICO’s often have several different components such as land, machinery, building, and other equipment.

Some of the assumptions while using the Discounted Cash Flow Methods –

Projects are assumed to be Mutually Exclusive – This is seldom the came in modern day giant organizations where projects are often inter-related and rejecting a project solely based on NPV can result in sunk cost from a related project.

Independent projects have independent cash flows – As explained in the marketing project – though the project may look independent but in reality it is not as the brand awareness project can be closely associated with the spending on sales promotions and product specific advertising.






Negotiation Strategy of Reson: Making Development Teams Accountable for Short Project Cycles

References & Further Readings

Thomas E. Vollmann, Jussi Heikkila (2018), "Reson: Making Development Teams Accountable for Short Project Cycles Harvard Business Review Case Study. Published by HBR Publications.


ASE Industrial ADR SWOT Analysis / TOWS Matrix

Capital Goods , Misc. Capital Goods


CTS Corp SWOT Analysis / TOWS Matrix

Technology , Electronic Instr. & Controls


Pelita Samudera SWOT Analysis / TOWS Matrix

Transportation , Water Transportation


Shiva Texyarn SWOT Analysis / TOWS Matrix

Consumer Cyclical , Apparel/Accessories


Cipherloc SWOT Analysis / TOWS Matrix

Technology , Software & Programming


Fantasia Holdings Group SWOT Analysis / TOWS Matrix

Capital Goods , Construction Services


Aichi Corp SWOT Analysis / TOWS Matrix

Capital Goods , Constr. & Agric. Machinery


Nippon Concept SWOT Analysis / TOWS Matrix

Transportation , Water Transportation


ANI Pharma SWOT Analysis / TOWS Matrix

Healthcare , Biotechnology & Drugs


IPS Inc SWOT Analysis / TOWS Matrix

Services , Communications Services