Tom Baker Cancer Centre Net Present Value (NPV) / MBA Resources

Introduction to Net Present Value (NPV) - What is Net Present Value (NPV) ? How it impacts financial decisions regarding project management?

NPV solution for Tom Baker Cancer Centre case study


At Oak Spring University, we provide corporate level professional Net Present Value (NPV) case study solution. Tom Baker Cancer Centre case study is a Harvard Business School (HBR) case study written by Murray J. Bryant, Eileen Pepler. The Tom Baker Cancer Centre (referred as “Cancer Acb” from here on) case study provides evaluation & decision scenario in field of Leadership & Managing People. It also touches upon business topics such as - Value proposition, Decision making.

The net present value (NPV) of an investment proposal is the present value of the proposal’s net cash flows less the proposal’s initial cash outflow. If a project’s NPV is greater than or equal to zero, the project should be accepted.

NPV = Present Value of Future Cash Flows LESS Project’s Initial Investment






Case Description of Tom Baker Cancer Centre Case Study


The director for the Tom Baker Cancer Centre (TBCC) and vice-president of the Alberta Cancer Board (ACB) took a moment to reflect on the past six months. He had assumed the leadership of the TBCC in December 2006. Alberta Health & Wellness had created an ambitious provincial vision for cancer in which the director would play a key role. The director recognized that it would be difficult to gain buy-in from the different stakeholders because they were used to a different way of operating. Before moving forward, the director wanted to have several discussions with ACB, his management team and the front-line staff, and present to them some preliminary objectives.


Case Authors : Murray J. Bryant, Eileen Pepler

Topic : Leadership & Managing People

Related Areas : Decision making




Calculating Net Present Value (NPV) at 6% for Tom Baker Cancer Centre Case Study


Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 6 %
Discounted
Cash Flows
Year 0 (10027856) -10027856 - -
Year 1 3457603 -6570253 3457603 0.9434 3261890
Year 2 3979826 -2590427 7437429 0.89 3542031
Year 3 3943508 1353081 11380937 0.8396 3311045
Year 4 3238760 4591841 14619697 0.7921 2565401
TOTAL 14619697 12680367




The Net Present Value at 6% discount rate is 2652511

In isolation the NPV number doesn't mean much but put in right context then it is one of the best method to evaluate project returns. In this article we will cover -

Different methods of capital budgeting


What is NPV & Formula of NPV,
How it is calculated,
How to use NPV number for project evaluation, and
Scenario Planning given risks and management priorities.




Capital Budgeting Approaches

Methods of Capital Budgeting


There are four types of capital budgeting techniques that are widely used in the corporate world –

1. Profitability Index
2. Net Present Value
3. Internal Rate of Return
4. Payback Period

Apart from the Payback period method which is an additive method, rest of the methods are based on Discounted Cash Flow technique. Even though cash flow can be calculated based on the nature of the project, for the simplicity of the article we are assuming that all the expected cash flows are realized at the end of the year.

Discounted Cash Flow approaches provide a more objective basis for evaluating and selecting investment projects. They take into consideration both –

1. Magnitude of both incoming and outgoing cash flows – Projects can be capital intensive, time intensive, or both. Cancer Acb shareholders have preference for diversified projects investment rather than prospective high income from a single capital intensive project.
2. Timing of the expected cash flows – stockholders of Cancer Acb have higher preference for cash returns over 4-5 years rather than 10-15 years given the nature of the volatility in the industry.






Formula and Steps to Calculate Net Present Value (NPV) of Tom Baker Cancer Centre

NPV = Net Cash In Flowt1 / (1+r)t1 + Net Cash In Flowt2 / (1+r)t2 + … Net Cash In Flowtn / (1+r)tn
Less Net Cash Out Flowt0 / (1+r)t0

Where t = time period, in this case year 1, year 2 and so on.
r = discount rate or return that could be earned using other safe proposition such as fixed deposit or treasury bond rate. Net Cash In Flow – What the firm will get each year.
Net Cash Out Flow – What the firm needs to invest initially in the project.

Step 1 – Understand the nature of the project and calculate cash flow for each year.
Step 2 – Discount those cash flow based on the discount rate.
Step 3 – Add all the discounted cash flow.
Step 4 – Selection of the project

Why Leadership & Managing People Managers need to know Financial Tools such as Net Present Value (NPV)?

In our daily workplace we often come across people and colleagues who are just focused on their core competency and targets they have to deliver. For example marketing managers at Cancer Acb often design programs whose objective is to drive brand awareness and customer reach. But how that 30 point increase in brand awareness or 10 point increase in customer touch points will result into shareholders’ value is not specified.

To overcome such scenarios managers at Cancer Acb needs to not only know the financial aspect of project management but also needs to have tools to integrate them into part of the project development and monitoring plan.

Calculating Net Present Value (NPV) at 15%

After working through various assumptions we reached a conclusion that risk is far higher than 6%. In a reasonably stable industry with weak competition - 15% discount rate can be a good benchmark.



Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 15 %
Discounted
Cash Flows
Year 0 (10027856) -10027856 - -
Year 1 3457603 -6570253 3457603 0.8696 3006611
Year 2 3979826 -2590427 7437429 0.7561 3009320
Year 3 3943508 1353081 11380937 0.6575 2592921
Year 4 3238760 4591841 14619697 0.5718 1851772
TOTAL 10460624


The Net NPV after 4 years is 432768

(10460624 - 10027856 )








Calculating Net Present Value (NPV) at 20%


If the risk component is high in the industry then we should go for a higher hurdle rate / discount rate of 20%.

Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 20 %
Discounted
Cash Flows
Year 0 (10027856) -10027856 - -
Year 1 3457603 -6570253 3457603 0.8333 2881336
Year 2 3979826 -2590427 7437429 0.6944 2763768
Year 3 3943508 1353081 11380937 0.5787 2282123
Year 4 3238760 4591841 14619697 0.4823 1561902
TOTAL 9489129


The Net NPV after 4 years is -538727

At 20% discount rate the NPV is negative (9489129 - 10027856 ) so ideally we can't select the project if macro and micro factors don't allow financial managers of Cancer Acb to discount cash flow at lower discount rates such as 15%.





Acceptance Criteria of a Project based on NPV

Simplest Approach – If the investment project of Cancer Acb has a NPV value higher than Zero then finance managers at Cancer Acb can ACCEPT the project, otherwise they can reject the project. This means that project will deliver higher returns over the period of time than any alternate investment strategy.

In theory if the required rate of return or discount rate is chosen correctly by finance managers at Cancer Acb, then the stock price of the Cancer Acb should change by same amount of the NPV. In real world we know that share price also reflects various other factors that can be related to both macro and micro environment.

In the same vein – accepting the project with zero NPV should result in stagnant share price. Finance managers use discount rates as a measure of risk components in the project execution process.

Sensitivity Analysis

Project selection is often a far more complex decision than just choosing it based on the NPV number. Finance managers at Cancer Acb should conduct a sensitivity analysis to better understand not only the inherent risk of the projects but also how those risks can be either factored in or mitigated during the project execution. Sensitivity analysis helps in –

What are the key aspects of the projects that need to be monitored, refined, and retuned for continuous delivery of projected cash flows.

What can impact the cash flow of the project.

What are the uncertainties surrounding the project Initial Cash Outlay (ICO’s). ICO’s often have several different components such as land, machinery, building, and other equipment.

Understanding of risks involved in the project.

What will be a multi year spillover effect of various taxation regulations.

Some of the assumptions while using the Discounted Cash Flow Methods –

Projects are assumed to be Mutually Exclusive – This is seldom the came in modern day giant organizations where projects are often inter-related and rejecting a project solely based on NPV can result in sunk cost from a related project.

Independent projects have independent cash flows – As explained in the marketing project – though the project may look independent but in reality it is not as the brand awareness project can be closely associated with the spending on sales promotions and product specific advertising.






Negotiation Strategy of Tom Baker Cancer Centre

References & Further Readings

Murray J. Bryant, Eileen Pepler (2018), "Tom Baker Cancer Centre Harvard Business Review Case Study. Published by HBR Publications.


MS Industrie SWOT Analysis / TOWS Matrix

Consumer Cyclical , Auto & Truck Parts


Citra Marga SWOT Analysis / TOWS Matrix

Transportation , Misc. Transportation


Visioneering Tech SWOT Analysis / TOWS Matrix

Healthcare , Medical Equipment & Supplies


Sanshin Electronics SWOT Analysis / TOWS Matrix

Technology , Electronic Instr. & Controls


Europa Oil & Gas SWOT Analysis / TOWS Matrix

Energy , Oil & Gas - Integrated


Hiap Teck Venture SWOT Analysis / TOWS Matrix

Basic Materials , Misc. Fabricated Products


Jiangsu Canlon Building SWOT Analysis / TOWS Matrix

Capital Goods , Constr. - Supplies & Fixtures


Yamatane Corp SWOT Analysis / TOWS Matrix

Consumer/Non-Cyclical , Food Processing


Shanghai Guangdian Electric SWOT Analysis / TOWS Matrix

Technology , Electronic Instr. & Controls