×




Michael Lester at Lachlan Consulting Net Present Value (NPV) / MBA Resources

Introduction to Net Present Value (NPV) - What is Net Present Value (NPV) ? How it impacts financial decisions regarding project management?

NPV solution for Michael Lester at Lachlan Consulting case study


At Oak Spring University, we provide corporate level professional Net Present Value (NPV) case study solution. Michael Lester at Lachlan Consulting case study is a Harvard Business School (HBR) case study written by Anthony J. Mayo, Joshua D. Margolis. The Michael Lester at Lachlan Consulting (referred as “Lester Lachlan” from here on) case study provides evaluation & decision scenario in field of Leadership & Managing People. It also touches upon business topics such as - Value proposition, Collaboration, Conflict, Difficult conversations, Leadership, Organizational culture.

The net present value (NPV) of an investment proposal is the present value of the proposal’s net cash flows less the proposal’s initial cash outflow. If a project’s NPV is greater than or equal to zero, the project should be accepted.

NPV = Present Value of Future Cash Flows LESS Project’s Initial Investment






Case Description of Michael Lester at Lachlan Consulting Case Study


Michael Lester, a consultant with Lachlan, was frustrated by his client's unwillingness to provide key data for an important presentation. Lester must decide how best to confront Nadine Robert, his client, knowing that his personal success and the reputation of his consulting firm hinge on his ability to build and sustain a strong relationship. How firm should he be with the client? What type of feedback would help this situation?


Case Authors : Anthony J. Mayo, Joshua D. Margolis

Topic : Leadership & Managing People

Related Areas : Collaboration, Conflict, Difficult conversations, Leadership, Organizational culture




Calculating Net Present Value (NPV) at 6% for Michael Lester at Lachlan Consulting Case Study


Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 6 %
Discounted
Cash Flows
Year 0 (10021086) -10021086 - -
Year 1 3466011 -6555075 3466011 0.9434 3269822
Year 2 3963571 -2591504 7429582 0.89 3527564
Year 3 3938708 1347204 11368290 0.8396 3307015
Year 4 3225374 4572578 14593664 0.7921 2554798
TOTAL 14593664 12659199




The Net Present Value at 6% discount rate is 2638113

In isolation the NPV number doesn't mean much but put in right context then it is one of the best method to evaluate project returns. In this article we will cover -

Different methods of capital budgeting


What is NPV & Formula of NPV,
How it is calculated,
How to use NPV number for project evaluation, and
Scenario Planning given risks and management priorities.




Capital Budgeting Approaches

Methods of Capital Budgeting


There are four types of capital budgeting techniques that are widely used in the corporate world –

1. Payback Period
2. Net Present Value
3. Internal Rate of Return
4. Profitability Index

Apart from the Payback period method which is an additive method, rest of the methods are based on Discounted Cash Flow technique. Even though cash flow can be calculated based on the nature of the project, for the simplicity of the article we are assuming that all the expected cash flows are realized at the end of the year.

Discounted Cash Flow approaches provide a more objective basis for evaluating and selecting investment projects. They take into consideration both –

1. Timing of the expected cash flows – stockholders of Lester Lachlan have higher preference for cash returns over 4-5 years rather than 10-15 years given the nature of the volatility in the industry.
2. Magnitude of both incoming and outgoing cash flows – Projects can be capital intensive, time intensive, or both. Lester Lachlan shareholders have preference for diversified projects investment rather than prospective high income from a single capital intensive project.






Formula and Steps to Calculate Net Present Value (NPV) of Michael Lester at Lachlan Consulting

NPV = Net Cash In Flowt1 / (1+r)t1 + Net Cash In Flowt2 / (1+r)t2 + … Net Cash In Flowtn / (1+r)tn
Less Net Cash Out Flowt0 / (1+r)t0

Where t = time period, in this case year 1, year 2 and so on.
r = discount rate or return that could be earned using other safe proposition such as fixed deposit or treasury bond rate. Net Cash In Flow – What the firm will get each year.
Net Cash Out Flow – What the firm needs to invest initially in the project.

Step 1 – Understand the nature of the project and calculate cash flow for each year.
Step 2 – Discount those cash flow based on the discount rate.
Step 3 – Add all the discounted cash flow.
Step 4 – Selection of the project

Why Leadership & Managing People Managers need to know Financial Tools such as Net Present Value (NPV)?

In our daily workplace we often come across people and colleagues who are just focused on their core competency and targets they have to deliver. For example marketing managers at Lester Lachlan often design programs whose objective is to drive brand awareness and customer reach. But how that 30 point increase in brand awareness or 10 point increase in customer touch points will result into shareholders’ value is not specified.

To overcome such scenarios managers at Lester Lachlan needs to not only know the financial aspect of project management but also needs to have tools to integrate them into part of the project development and monitoring plan.

Calculating Net Present Value (NPV) at 15%

After working through various assumptions we reached a conclusion that risk is far higher than 6%. In a reasonably stable industry with weak competition - 15% discount rate can be a good benchmark.



Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 15 %
Discounted
Cash Flows
Year 0 (10021086) -10021086 - -
Year 1 3466011 -6555075 3466011 0.8696 3013923
Year 2 3963571 -2591504 7429582 0.7561 2997029
Year 3 3938708 1347204 11368290 0.6575 2589764
Year 4 3225374 4572578 14593664 0.5718 1844118
TOTAL 10444834


The Net NPV after 4 years is 423748

(10444834 - 10021086 )








Calculating Net Present Value (NPV) at 20%


If the risk component is high in the industry then we should go for a higher hurdle rate / discount rate of 20%.

Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 20 %
Discounted
Cash Flows
Year 0 (10021086) -10021086 - -
Year 1 3466011 -6555075 3466011 0.8333 2888343
Year 2 3963571 -2591504 7429582 0.6944 2752480
Year 3 3938708 1347204 11368290 0.5787 2279345
Year 4 3225374 4572578 14593664 0.4823 1555447
TOTAL 9475614


The Net NPV after 4 years is -545472

At 20% discount rate the NPV is negative (9475614 - 10021086 ) so ideally we can't select the project if macro and micro factors don't allow financial managers of Lester Lachlan to discount cash flow at lower discount rates such as 15%.





Acceptance Criteria of a Project based on NPV

Simplest Approach – If the investment project of Lester Lachlan has a NPV value higher than Zero then finance managers at Lester Lachlan can ACCEPT the project, otherwise they can reject the project. This means that project will deliver higher returns over the period of time than any alternate investment strategy.

In theory if the required rate of return or discount rate is chosen correctly by finance managers at Lester Lachlan, then the stock price of the Lester Lachlan should change by same amount of the NPV. In real world we know that share price also reflects various other factors that can be related to both macro and micro environment.

In the same vein – accepting the project with zero NPV should result in stagnant share price. Finance managers use discount rates as a measure of risk components in the project execution process.

Sensitivity Analysis

Project selection is often a far more complex decision than just choosing it based on the NPV number. Finance managers at Lester Lachlan should conduct a sensitivity analysis to better understand not only the inherent risk of the projects but also how those risks can be either factored in or mitigated during the project execution. Sensitivity analysis helps in –

Understanding of risks involved in the project.

What can impact the cash flow of the project.

What are the uncertainties surrounding the project Initial Cash Outlay (ICO’s). ICO’s often have several different components such as land, machinery, building, and other equipment.

What are the key aspects of the projects that need to be monitored, refined, and retuned for continuous delivery of projected cash flows.

What will be a multi year spillover effect of various taxation regulations.

Some of the assumptions while using the Discounted Cash Flow Methods –

Projects are assumed to be Mutually Exclusive – This is seldom the came in modern day giant organizations where projects are often inter-related and rejecting a project solely based on NPV can result in sunk cost from a related project.

Independent projects have independent cash flows – As explained in the marketing project – though the project may look independent but in reality it is not as the brand awareness project can be closely associated with the spending on sales promotions and product specific advertising.






Negotiation Strategy of Michael Lester at Lachlan Consulting

References & Further Readings

Anthony J. Mayo, Joshua D. Margolis (2018), "Michael Lester at Lachlan Consulting Harvard Business Review Case Study. Published by HBR Publications.


Solid State SWOT Analysis / TOWS Matrix

Technology , Electronic Instr. & Controls


ESSO SWOT Analysis / TOWS Matrix

Energy , Oil & Gas Operations


Valor Resources SWOT Analysis / TOWS Matrix

Basic Materials , Gold & Silver


Net 1 UEPS SWOT Analysis / TOWS Matrix

Financial , Consumer Financial Services


IGD SWOT Analysis / TOWS Matrix

Services , Real Estate Operations


APA Group SWOT Analysis / TOWS Matrix

Utilities , Natural Gas Utilities


Geo SWOT Analysis / TOWS Matrix

Services , Real Estate Operations


PetroQuest Energy SWOT Analysis / TOWS Matrix

Energy , Oil & Gas - Integrated