Richard Jenkins Net Present Value (NPV) / MBA Resources

Introduction to Net Present Value (NPV) - What is Net Present Value (NPV) ? How it impacts financial decisions regarding project management?

NPV solution for Richard Jenkins case study


At Oak Spring University, we provide corporate level professional Net Present Value (NPV) case study solution. Richard Jenkins case study is a Harvard Business School (HBR) case study written by John J. Gabarro, Andrew Burtis. The Richard Jenkins (referred as “Jenkins Richard” from here on) case study provides evaluation & decision scenario in field of Leadership & Managing People. It also touches upon business topics such as - Value proposition, Communication, Leadership, Organizational culture, Organizational structure, Professional transitions.

The net present value (NPV) of an investment proposal is the present value of the proposal’s net cash flows less the proposal’s initial cash outflow. If a project’s NPV is greater than or equal to zero, the project should be accepted.

NPV = Present Value of Future Cash Flows LESS Project’s Initial Investment






Case Description of Richard Jenkins Case Study


Written from the point of view of Richard Jenkins, the president of CelluComm. Presents his reflections on the series of events leading to the firing of one of CelluComm's general managers, Erik Peterson. A rewritten version of an earlier case.


Case Authors : John J. Gabarro, Andrew Burtis

Topic : Leadership & Managing People

Related Areas : Communication, Leadership, Organizational culture, Organizational structure, Professional transitions




Calculating Net Present Value (NPV) at 6% for Richard Jenkins Case Study


Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 6 %
Discounted
Cash Flows
Year 0 (10017268) -10017268 - -
Year 1 3456498 -6560770 3456498 0.9434 3260847
Year 2 3955930 -2604840 7412428 0.89 3520764
Year 3 3975181 1370341 11387609 0.8396 3337639
Year 4 3227469 4597810 14615078 0.7921 2556458
TOTAL 14615078 12675707




The Net Present Value at 6% discount rate is 2658439

In isolation the NPV number doesn't mean much but put in right context then it is one of the best method to evaluate project returns. In this article we will cover -

Different methods of capital budgeting


What is NPV & Formula of NPV,
How it is calculated,
How to use NPV number for project evaluation, and
Scenario Planning given risks and management priorities.




Capital Budgeting Approaches

Methods of Capital Budgeting


There are four types of capital budgeting techniques that are widely used in the corporate world –

1. Profitability Index
2. Internal Rate of Return
3. Payback Period
4. Net Present Value

Apart from the Payback period method which is an additive method, rest of the methods are based on Discounted Cash Flow technique. Even though cash flow can be calculated based on the nature of the project, for the simplicity of the article we are assuming that all the expected cash flows are realized at the end of the year.

Discounted Cash Flow approaches provide a more objective basis for evaluating and selecting investment projects. They take into consideration both –

1. Magnitude of both incoming and outgoing cash flows – Projects can be capital intensive, time intensive, or both. Jenkins Richard shareholders have preference for diversified projects investment rather than prospective high income from a single capital intensive project.
2. Timing of the expected cash flows – stockholders of Jenkins Richard have higher preference for cash returns over 4-5 years rather than 10-15 years given the nature of the volatility in the industry.






Formula and Steps to Calculate Net Present Value (NPV) of Richard Jenkins

NPV = Net Cash In Flowt1 / (1+r)t1 + Net Cash In Flowt2 / (1+r)t2 + … Net Cash In Flowtn / (1+r)tn
Less Net Cash Out Flowt0 / (1+r)t0

Where t = time period, in this case year 1, year 2 and so on.
r = discount rate or return that could be earned using other safe proposition such as fixed deposit or treasury bond rate. Net Cash In Flow – What the firm will get each year.
Net Cash Out Flow – What the firm needs to invest initially in the project.

Step 1 – Understand the nature of the project and calculate cash flow for each year.
Step 2 – Discount those cash flow based on the discount rate.
Step 3 – Add all the discounted cash flow.
Step 4 – Selection of the project

Why Leadership & Managing People Managers need to know Financial Tools such as Net Present Value (NPV)?

In our daily workplace we often come across people and colleagues who are just focused on their core competency and targets they have to deliver. For example marketing managers at Jenkins Richard often design programs whose objective is to drive brand awareness and customer reach. But how that 30 point increase in brand awareness or 10 point increase in customer touch points will result into shareholders’ value is not specified.

To overcome such scenarios managers at Jenkins Richard needs to not only know the financial aspect of project management but also needs to have tools to integrate them into part of the project development and monitoring plan.

Calculating Net Present Value (NPV) at 15%

After working through various assumptions we reached a conclusion that risk is far higher than 6%. In a reasonably stable industry with weak competition - 15% discount rate can be a good benchmark.



Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 15 %
Discounted
Cash Flows
Year 0 (10017268) -10017268 - -
Year 1 3456498 -6560770 3456498 0.8696 3005650
Year 2 3955930 -2604840 7412428 0.7561 2991251
Year 3 3975181 1370341 11387609 0.6575 2613746
Year 4 3227469 4597810 14615078 0.5718 1845316
TOTAL 10455964


The Net NPV after 4 years is 438696

(10455964 - 10017268 )








Calculating Net Present Value (NPV) at 20%


If the risk component is high in the industry then we should go for a higher hurdle rate / discount rate of 20%.

Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 20 %
Discounted
Cash Flows
Year 0 (10017268) -10017268 - -
Year 1 3456498 -6560770 3456498 0.8333 2880415
Year 2 3955930 -2604840 7412428 0.6944 2747174
Year 3 3975181 1370341 11387609 0.5787 2300452
Year 4 3227469 4597810 14615078 0.4823 1556457
TOTAL 9484497


The Net NPV after 4 years is -532771

At 20% discount rate the NPV is negative (9484497 - 10017268 ) so ideally we can't select the project if macro and micro factors don't allow financial managers of Jenkins Richard to discount cash flow at lower discount rates such as 15%.





Acceptance Criteria of a Project based on NPV

Simplest Approach – If the investment project of Jenkins Richard has a NPV value higher than Zero then finance managers at Jenkins Richard can ACCEPT the project, otherwise they can reject the project. This means that project will deliver higher returns over the period of time than any alternate investment strategy.

In theory if the required rate of return or discount rate is chosen correctly by finance managers at Jenkins Richard, then the stock price of the Jenkins Richard should change by same amount of the NPV. In real world we know that share price also reflects various other factors that can be related to both macro and micro environment.

In the same vein – accepting the project with zero NPV should result in stagnant share price. Finance managers use discount rates as a measure of risk components in the project execution process.

Sensitivity Analysis

Project selection is often a far more complex decision than just choosing it based on the NPV number. Finance managers at Jenkins Richard should conduct a sensitivity analysis to better understand not only the inherent risk of the projects but also how those risks can be either factored in or mitigated during the project execution. Sensitivity analysis helps in –

Understanding of risks involved in the project.

What are the uncertainties surrounding the project Initial Cash Outlay (ICO’s). ICO’s often have several different components such as land, machinery, building, and other equipment.

What can impact the cash flow of the project.

What will be a multi year spillover effect of various taxation regulations.

What are the key aspects of the projects that need to be monitored, refined, and retuned for continuous delivery of projected cash flows.

Some of the assumptions while using the Discounted Cash Flow Methods –

Projects are assumed to be Mutually Exclusive – This is seldom the came in modern day giant organizations where projects are often inter-related and rejecting a project solely based on NPV can result in sunk cost from a related project.

Independent projects have independent cash flows – As explained in the marketing project – though the project may look independent but in reality it is not as the brand awareness project can be closely associated with the spending on sales promotions and product specific advertising.






Negotiation Strategy of Richard Jenkins

References & Further Readings

John J. Gabarro, Andrew Burtis (2018), "Richard Jenkins Harvard Business Review Case Study. Published by HBR Publications.


Herman Miller SWOT Analysis / TOWS Matrix

Capital Goods , Constr. - Supplies & Fixtures


Proteome SWOT Analysis / TOWS Matrix

Healthcare , Biotechnology & Drugs


DaChan Food Asia SWOT Analysis / TOWS Matrix

Consumer/Non-Cyclical , Food Processing


Hengxing Gold SWOT Analysis / TOWS Matrix

Basic Materials , Gold & Silver


Nissan Shatai SWOT Analysis / TOWS Matrix

Consumer Cyclical , Auto & Truck Manufacturers


HALCYON Agri Corp Ltd SWOT Analysis / TOWS Matrix

Basic Materials , Chemicals - Plastics & Rubber


Tianye Tolian A SWOT Analysis / TOWS Matrix

Capital Goods , Constr. & Agric. Machinery


Fukuda Denshi SWOT Analysis / TOWS Matrix

Healthcare , Medical Equipment & Supplies