Southpointe Corporation-Key Experiences Net Present Value (NPV) / MBA Resources

Introduction to Net Present Value (NPV) - What is Net Present Value (NPV) ? How it impacts financial decisions regarding project management?

NPV solution for Southpointe Corporation-Key Experiences case study


At Oak Spring University, we provide corporate level professional Net Present Value (NPV) case study solution. Southpointe Corporation-Key Experiences case study is a Harvard Business School (HBR) case study written by Mark E. Haskins. The Southpointe Corporation-Key Experiences (referred as “Southpointe Ldp” from here on) case study provides evaluation & decision scenario in field of Leadership & Managing People. It also touches upon business topics such as - Value proposition, Leadership development.

The net present value (NPV) of an investment proposal is the present value of the proposal’s net cash flows less the proposal’s initial cash outflow. If a project’s NPV is greater than or equal to zero, the project should be accepted.

NPV = Present Value of Future Cash Flows LESS Project’s Initial Investment






Case Description of Southpointe Corporation-Key Experiences Case Study


"During the five years Southpointe Corporation had used its custom Leadership Development Program (LDP), a significant number of existing and high-potential managers from all the company's functional areas and geographic regions had been through the LDP. Now in response to some ongoing leadership development concerns, Southpointe's CEO, wants to develop a "key experiences" program for a handful of managers viewed as viable executive team candidates. "


Case Authors : Mark E. Haskins

Topic : Leadership & Managing People

Related Areas : Leadership development




Calculating Net Present Value (NPV) at 6% for Southpointe Corporation-Key Experiences Case Study


Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 6 %
Discounted
Cash Flows
Year 0 (10012970) -10012970 - -
Year 1 3447989 -6564981 3447989 0.9434 3252820
Year 2 3975707 -2589274 7423696 0.89 3538365
Year 3 3947675 1358401 11371371 0.8396 3314544
Year 4 3235056 4593457 14606427 0.7921 2562467
TOTAL 14606427 12668196




The Net Present Value at 6% discount rate is 2655226

In isolation the NPV number doesn't mean much but put in right context then it is one of the best method to evaluate project returns. In this article we will cover -

Different methods of capital budgeting


What is NPV & Formula of NPV,
How it is calculated,
How to use NPV number for project evaluation, and
Scenario Planning given risks and management priorities.




Capital Budgeting Approaches

Methods of Capital Budgeting


There are four types of capital budgeting techniques that are widely used in the corporate world –

1. Profitability Index
2. Internal Rate of Return
3. Payback Period
4. Net Present Value

Apart from the Payback period method which is an additive method, rest of the methods are based on Discounted Cash Flow technique. Even though cash flow can be calculated based on the nature of the project, for the simplicity of the article we are assuming that all the expected cash flows are realized at the end of the year.

Discounted Cash Flow approaches provide a more objective basis for evaluating and selecting investment projects. They take into consideration both –

1. Timing of the expected cash flows – stockholders of Southpointe Ldp have higher preference for cash returns over 4-5 years rather than 10-15 years given the nature of the volatility in the industry.
2. Magnitude of both incoming and outgoing cash flows – Projects can be capital intensive, time intensive, or both. Southpointe Ldp shareholders have preference for diversified projects investment rather than prospective high income from a single capital intensive project.






Formula and Steps to Calculate Net Present Value (NPV) of Southpointe Corporation-Key Experiences

NPV = Net Cash In Flowt1 / (1+r)t1 + Net Cash In Flowt2 / (1+r)t2 + … Net Cash In Flowtn / (1+r)tn
Less Net Cash Out Flowt0 / (1+r)t0

Where t = time period, in this case year 1, year 2 and so on.
r = discount rate or return that could be earned using other safe proposition such as fixed deposit or treasury bond rate. Net Cash In Flow – What the firm will get each year.
Net Cash Out Flow – What the firm needs to invest initially in the project.

Step 1 – Understand the nature of the project and calculate cash flow for each year.
Step 2 – Discount those cash flow based on the discount rate.
Step 3 – Add all the discounted cash flow.
Step 4 – Selection of the project

Why Leadership & Managing People Managers need to know Financial Tools such as Net Present Value (NPV)?

In our daily workplace we often come across people and colleagues who are just focused on their core competency and targets they have to deliver. For example marketing managers at Southpointe Ldp often design programs whose objective is to drive brand awareness and customer reach. But how that 30 point increase in brand awareness or 10 point increase in customer touch points will result into shareholders’ value is not specified.

To overcome such scenarios managers at Southpointe Ldp needs to not only know the financial aspect of project management but also needs to have tools to integrate them into part of the project development and monitoring plan.

Calculating Net Present Value (NPV) at 15%

After working through various assumptions we reached a conclusion that risk is far higher than 6%. In a reasonably stable industry with weak competition - 15% discount rate can be a good benchmark.



Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 15 %
Discounted
Cash Flows
Year 0 (10012970) -10012970 - -
Year 1 3447989 -6564981 3447989 0.8696 2998251
Year 2 3975707 -2589274 7423696 0.7561 3006206
Year 3 3947675 1358401 11371371 0.6575 2595660
Year 4 3235056 4593457 14606427 0.5718 1849654
TOTAL 10449771


The Net NPV after 4 years is 436801

(10449771 - 10012970 )








Calculating Net Present Value (NPV) at 20%


If the risk component is high in the industry then we should go for a higher hurdle rate / discount rate of 20%.

Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 20 %
Discounted
Cash Flows
Year 0 (10012970) -10012970 - -
Year 1 3447989 -6564981 3447989 0.8333 2873324
Year 2 3975707 -2589274 7423696 0.6944 2760908
Year 3 3947675 1358401 11371371 0.5787 2284534
Year 4 3235056 4593457 14606427 0.4823 1560116
TOTAL 9478882


The Net NPV after 4 years is -534088

At 20% discount rate the NPV is negative (9478882 - 10012970 ) so ideally we can't select the project if macro and micro factors don't allow financial managers of Southpointe Ldp to discount cash flow at lower discount rates such as 15%.





Acceptance Criteria of a Project based on NPV

Simplest Approach – If the investment project of Southpointe Ldp has a NPV value higher than Zero then finance managers at Southpointe Ldp can ACCEPT the project, otherwise they can reject the project. This means that project will deliver higher returns over the period of time than any alternate investment strategy.

In theory if the required rate of return or discount rate is chosen correctly by finance managers at Southpointe Ldp, then the stock price of the Southpointe Ldp should change by same amount of the NPV. In real world we know that share price also reflects various other factors that can be related to both macro and micro environment.

In the same vein – accepting the project with zero NPV should result in stagnant share price. Finance managers use discount rates as a measure of risk components in the project execution process.

Sensitivity Analysis

Project selection is often a far more complex decision than just choosing it based on the NPV number. Finance managers at Southpointe Ldp should conduct a sensitivity analysis to better understand not only the inherent risk of the projects but also how those risks can be either factored in or mitigated during the project execution. Sensitivity analysis helps in –

What can impact the cash flow of the project.

Understanding of risks involved in the project.

What are the uncertainties surrounding the project Initial Cash Outlay (ICO’s). ICO’s often have several different components such as land, machinery, building, and other equipment.

What will be a multi year spillover effect of various taxation regulations.

What are the key aspects of the projects that need to be monitored, refined, and retuned for continuous delivery of projected cash flows.

Some of the assumptions while using the Discounted Cash Flow Methods –

Projects are assumed to be Mutually Exclusive – This is seldom the came in modern day giant organizations where projects are often inter-related and rejecting a project solely based on NPV can result in sunk cost from a related project.

Independent projects have independent cash flows – As explained in the marketing project – though the project may look independent but in reality it is not as the brand awareness project can be closely associated with the spending on sales promotions and product specific advertising.






Negotiation Strategy of Southpointe Corporation-Key Experiences

References & Further Readings

Mark E. Haskins (2018), "Southpointe Corporation-Key Experiences Harvard Business Review Case Study. Published by HBR Publications.


Ensign Energy Services SWOT Analysis / TOWS Matrix

Energy , Oil Well Services & Equipment


Rexel SWOT Analysis / TOWS Matrix

Technology , Electronic Instr. & Controls


Yasha Decoration A SWOT Analysis / TOWS Matrix

Capital Goods , Construction Services


Shofu Inc SWOT Analysis / TOWS Matrix

Healthcare , Medical Equipment & Supplies


Econach Holdings SWOT Analysis / TOWS Matrix

Consumer/Non-Cyclical , Personal & Household Prods.


GTN Textiles Ltd SWOT Analysis / TOWS Matrix

Consumer Cyclical , Apparel/Accessories


Homes Holiday SWOT Analysis / TOWS Matrix

Services , Real Estate Operations


Bio Osmo SWOT Analysis / TOWS Matrix

Consumer/Non-Cyclical , Beverages (Nonalcoholic)


Zhongnan Cons A SWOT Analysis / TOWS Matrix

Capital Goods , Construction Services


Zhejiang Yonggui Electric SWOT Analysis / TOWS Matrix

Technology , Electronic Instr. & Controls