Haskayne School of Business Student Orientation Barbecue Net Present Value (NPV) / MBA Resources

Introduction to Net Present Value (NPV) - What is Net Present Value (NPV) ? How it impacts financial decisions regarding project management?

NPV solution for Haskayne School of Business Student Orientation Barbecue case study


At Oak Spring University, we provide corporate level professional Net Present Value (NPV) case study solution. Haskayne School of Business Student Orientation Barbecue case study is a Harvard Business School (HBR) case study written by Frank W. Thirkettle, Norm Althouse. The Haskayne School of Business Student Orientation Barbecue (referred as “Barbecue Haskayne” from here on) case study provides evaluation & decision scenario in field of Leadership & Managing People. It also touches upon business topics such as - Value proposition, Ethics, Strategic planning.

The net present value (NPV) of an investment proposal is the present value of the proposal’s net cash flows less the proposal’s initial cash outflow. If a project’s NPV is greater than or equal to zero, the project should be accepted.

NPV = Present Value of Future Cash Flows LESS Project’s Initial Investment






Case Description of Haskayne School of Business Student Orientation Barbecue Case Study


The president of The Social Exchange at the Haskayne School of Business has only one chance. In his last year before graduating, he wants to host an ambitious event that will be remembered positively. The Friday prior to the commencement of the fall term is the date for the student orientation barbecue and many first impressions are at stake. Everything has to go well. On the morning of the event, the president cautiously reviews his plans and worries that he many have missed a vital detail.


Case Authors : Frank W. Thirkettle, Norm Althouse

Topic : Leadership & Managing People

Related Areas : Ethics, Strategic planning




Calculating Net Present Value (NPV) at 6% for Haskayne School of Business Student Orientation Barbecue Case Study


Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 6 %
Discounted
Cash Flows
Year 0 (10026096) -10026096 - -
Year 1 3457615 -6568481 3457615 0.9434 3261901
Year 2 3978803 -2589678 7436418 0.89 3541121
Year 3 3938370 1348692 11374788 0.8396 3306731
Year 4 3225202 4573894 14599990 0.7921 2554662
TOTAL 14599990 12664415




The Net Present Value at 6% discount rate is 2638319

In isolation the NPV number doesn't mean much but put in right context then it is one of the best method to evaluate project returns. In this article we will cover -

Different methods of capital budgeting


What is NPV & Formula of NPV,
How it is calculated,
How to use NPV number for project evaluation, and
Scenario Planning given risks and management priorities.




Capital Budgeting Approaches

Methods of Capital Budgeting


There are four types of capital budgeting techniques that are widely used in the corporate world –

1. Profitability Index
2. Internal Rate of Return
3. Payback Period
4. Net Present Value

Apart from the Payback period method which is an additive method, rest of the methods are based on Discounted Cash Flow technique. Even though cash flow can be calculated based on the nature of the project, for the simplicity of the article we are assuming that all the expected cash flows are realized at the end of the year.

Discounted Cash Flow approaches provide a more objective basis for evaluating and selecting investment projects. They take into consideration both –

1. Timing of the expected cash flows – stockholders of Barbecue Haskayne have higher preference for cash returns over 4-5 years rather than 10-15 years given the nature of the volatility in the industry.
2. Magnitude of both incoming and outgoing cash flows – Projects can be capital intensive, time intensive, or both. Barbecue Haskayne shareholders have preference for diversified projects investment rather than prospective high income from a single capital intensive project.






Formula and Steps to Calculate Net Present Value (NPV) of Haskayne School of Business Student Orientation Barbecue

NPV = Net Cash In Flowt1 / (1+r)t1 + Net Cash In Flowt2 / (1+r)t2 + … Net Cash In Flowtn / (1+r)tn
Less Net Cash Out Flowt0 / (1+r)t0

Where t = time period, in this case year 1, year 2 and so on.
r = discount rate or return that could be earned using other safe proposition such as fixed deposit or treasury bond rate. Net Cash In Flow – What the firm will get each year.
Net Cash Out Flow – What the firm needs to invest initially in the project.

Step 1 – Understand the nature of the project and calculate cash flow for each year.
Step 2 – Discount those cash flow based on the discount rate.
Step 3 – Add all the discounted cash flow.
Step 4 – Selection of the project

Why Leadership & Managing People Managers need to know Financial Tools such as Net Present Value (NPV)?

In our daily workplace we often come across people and colleagues who are just focused on their core competency and targets they have to deliver. For example marketing managers at Barbecue Haskayne often design programs whose objective is to drive brand awareness and customer reach. But how that 30 point increase in brand awareness or 10 point increase in customer touch points will result into shareholders’ value is not specified.

To overcome such scenarios managers at Barbecue Haskayne needs to not only know the financial aspect of project management but also needs to have tools to integrate them into part of the project development and monitoring plan.

Calculating Net Present Value (NPV) at 15%

After working through various assumptions we reached a conclusion that risk is far higher than 6%. In a reasonably stable industry with weak competition - 15% discount rate can be a good benchmark.



Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 15 %
Discounted
Cash Flows
Year 0 (10026096) -10026096 - -
Year 1 3457615 -6568481 3457615 0.8696 3006622
Year 2 3978803 -2589678 7436418 0.7561 3008547
Year 3 3938370 1348692 11374788 0.6575 2589542
Year 4 3225202 4573894 14599990 0.5718 1844020
TOTAL 10448730


The Net NPV after 4 years is 422634

(10448730 - 10026096 )








Calculating Net Present Value (NPV) at 20%


If the risk component is high in the industry then we should go for a higher hurdle rate / discount rate of 20%.

Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 20 %
Discounted
Cash Flows
Year 0 (10026096) -10026096 - -
Year 1 3457615 -6568481 3457615 0.8333 2881346
Year 2 3978803 -2589678 7436418 0.6944 2763058
Year 3 3938370 1348692 11374788 0.5787 2279149
Year 4 3225202 4573894 14599990 0.4823 1555364
TOTAL 9478916


The Net NPV after 4 years is -547180

At 20% discount rate the NPV is negative (9478916 - 10026096 ) so ideally we can't select the project if macro and micro factors don't allow financial managers of Barbecue Haskayne to discount cash flow at lower discount rates such as 15%.





Acceptance Criteria of a Project based on NPV

Simplest Approach – If the investment project of Barbecue Haskayne has a NPV value higher than Zero then finance managers at Barbecue Haskayne can ACCEPT the project, otherwise they can reject the project. This means that project will deliver higher returns over the period of time than any alternate investment strategy.

In theory if the required rate of return or discount rate is chosen correctly by finance managers at Barbecue Haskayne, then the stock price of the Barbecue Haskayne should change by same amount of the NPV. In real world we know that share price also reflects various other factors that can be related to both macro and micro environment.

In the same vein – accepting the project with zero NPV should result in stagnant share price. Finance managers use discount rates as a measure of risk components in the project execution process.

Sensitivity Analysis

Project selection is often a far more complex decision than just choosing it based on the NPV number. Finance managers at Barbecue Haskayne should conduct a sensitivity analysis to better understand not only the inherent risk of the projects but also how those risks can be either factored in or mitigated during the project execution. Sensitivity analysis helps in –

What can impact the cash flow of the project.

What are the key aspects of the projects that need to be monitored, refined, and retuned for continuous delivery of projected cash flows.

Understanding of risks involved in the project.

What will be a multi year spillover effect of various taxation regulations.

What are the uncertainties surrounding the project Initial Cash Outlay (ICO’s). ICO’s often have several different components such as land, machinery, building, and other equipment.

Some of the assumptions while using the Discounted Cash Flow Methods –

Projects are assumed to be Mutually Exclusive – This is seldom the came in modern day giant organizations where projects are often inter-related and rejecting a project solely based on NPV can result in sunk cost from a related project.

Independent projects have independent cash flows – As explained in the marketing project – though the project may look independent but in reality it is not as the brand awareness project can be closely associated with the spending on sales promotions and product specific advertising.






Negotiation Strategy of Haskayne School of Business Student Orientation Barbecue

References & Further Readings

Frank W. Thirkettle, Norm Althouse (2018), "Haskayne School of Business Student Orientation Barbecue Harvard Business Review Case Study. Published by HBR Publications.


Paras Petrofils Ltd SWOT Analysis / TOWS Matrix

Consumer Cyclical , Textiles - Non Apparel


Qualcomm SWOT Analysis / TOWS Matrix

Technology , Communications Equipment


Spring Real Estate SWOT Analysis / TOWS Matrix

Financial , Misc. Financial Services


Sekisui House SWOT Analysis / TOWS Matrix

Capital Goods , Construction Services


Eidos Therapeutics SWOT Analysis / TOWS Matrix

Healthcare , Biotechnology & Drugs


Yamane Medical SWOT Analysis / TOWS Matrix

Healthcare , Healthcare Facilities


Azplanning SWOT Analysis / TOWS Matrix

Services , Real Estate Operations


Hill&Smith SWOT Analysis / TOWS Matrix

Basic Materials , Iron & Steel


Lian Beng Group Ltd SWOT Analysis / TOWS Matrix

Capital Goods , Construction Services


Dolomite Corp SWOT Analysis / TOWS Matrix

Capital Goods , Construction - Raw Materials


Aker Solutions OL SWOT Analysis / TOWS Matrix

Energy , Oil Well Services & Equipment