Process Completeness: Strategies for Aligning Service Systems with Customers' Service Needs Net Present Value (NPV) / MBA Resources

Introduction to Net Present Value (NPV) - What is Net Present Value (NPV) ? How it impacts financial decisions regarding project management?

NPV solution for Process Completeness: Strategies for Aligning Service Systems with Customers' Service Needs case study


At Oak Spring University, we provide corporate level professional Net Present Value (NPV) case study solution. Process Completeness: Strategies for Aligning Service Systems with Customers' Service Needs case study is a Harvard Business School (HBR) case study written by Gabriele Piccoli, Kathryn Brohman, Richard T. Watson, A Parasuraman. The Process Completeness: Strategies for Aligning Service Systems with Customers' Service Needs (referred as “Completeness Service” from here on) case study provides evaluation & decision scenario in field of Technology & Operations. It also touches upon business topics such as - Value proposition, Customer service, Customers, Joint ventures, Supply chain.

The net present value (NPV) of an investment proposal is the present value of the proposal’s net cash flows less the proposal’s initial cash outflow. If a project’s NPV is greater than or equal to zero, the project should be accepted.

NPV = Present Value of Future Cash Flows LESS Project’s Initial Investment






Case Description of Process Completeness: Strategies for Aligning Service Systems with Customers' Service Needs Case Study


Increasingly, customers are expecting more and better service. As such, enterprises need guidelines and frameworks for addressing these expanding requirements. The concept of process completeness helps us to consider service from the customer's viewpoint; arguably, the only perspective to take. Process completeness is achieved when a firm's service delivery system matches the typical customer's breadth of expectations. While customers think in sets of services (e.g., I need a flight, a hotel, airport parking, wireless Internet), firms think in terms of single services (e.g., we can provide a flight). There are four basic service systems: (1) transaction-execute a basic request and nothing else, (2) process-handling all firm related service requests through one touch point, (3) alliance-handling service requests through a single touch point via stitching together a static firm-selected alliance of service partners, and (4) agility-handling service requests through a single touch point via stitching together a dynamic customer-selected alliance of service partners. In addition to exploring the four service systems, this article guides executives regarding the selection and implementation of the appropriate service strategy that meets their typical customer's process completeness expectations.


Case Authors : Gabriele Piccoli, Kathryn Brohman, Richard T. Watson, A Parasuraman

Topic : Technology & Operations

Related Areas : Customer service, Customers, Joint ventures, Supply chain




Calculating Net Present Value (NPV) at 6% for Process Completeness: Strategies for Aligning Service Systems with Customers' Service Needs Case Study


Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 6 %
Discounted
Cash Flows
Year 0 (10005911) -10005911 - -
Year 1 3453940 -6551971 3453940 0.9434 3258434
Year 2 3978174 -2573797 7432114 0.89 3540561
Year 3 3964941 1391144 11397055 0.8396 3329041
Year 4 3240636 4631780 14637691 0.7921 2566887
TOTAL 14637691 12694923




The Net Present Value at 6% discount rate is 2689012

In isolation the NPV number doesn't mean much but put in right context then it is one of the best method to evaluate project returns. In this article we will cover -

Different methods of capital budgeting


What is NPV & Formula of NPV,
How it is calculated,
How to use NPV number for project evaluation, and
Scenario Planning given risks and management priorities.




Capital Budgeting Approaches

Methods of Capital Budgeting


There are four types of capital budgeting techniques that are widely used in the corporate world –

1. Net Present Value
2. Profitability Index
3. Internal Rate of Return
4. Payback Period

Apart from the Payback period method which is an additive method, rest of the methods are based on Discounted Cash Flow technique. Even though cash flow can be calculated based on the nature of the project, for the simplicity of the article we are assuming that all the expected cash flows are realized at the end of the year.

Discounted Cash Flow approaches provide a more objective basis for evaluating and selecting investment projects. They take into consideration both –

1. Timing of the expected cash flows – stockholders of Completeness Service have higher preference for cash returns over 4-5 years rather than 10-15 years given the nature of the volatility in the industry.
2. Magnitude of both incoming and outgoing cash flows – Projects can be capital intensive, time intensive, or both. Completeness Service shareholders have preference for diversified projects investment rather than prospective high income from a single capital intensive project.






Formula and Steps to Calculate Net Present Value (NPV) of Process Completeness: Strategies for Aligning Service Systems with Customers' Service Needs

NPV = Net Cash In Flowt1 / (1+r)t1 + Net Cash In Flowt2 / (1+r)t2 + … Net Cash In Flowtn / (1+r)tn
Less Net Cash Out Flowt0 / (1+r)t0

Where t = time period, in this case year 1, year 2 and so on.
r = discount rate or return that could be earned using other safe proposition such as fixed deposit or treasury bond rate. Net Cash In Flow – What the firm will get each year.
Net Cash Out Flow – What the firm needs to invest initially in the project.

Step 1 – Understand the nature of the project and calculate cash flow for each year.
Step 2 – Discount those cash flow based on the discount rate.
Step 3 – Add all the discounted cash flow.
Step 4 – Selection of the project

Why Technology & Operations Managers need to know Financial Tools such as Net Present Value (NPV)?

In our daily workplace we often come across people and colleagues who are just focused on their core competency and targets they have to deliver. For example marketing managers at Completeness Service often design programs whose objective is to drive brand awareness and customer reach. But how that 30 point increase in brand awareness or 10 point increase in customer touch points will result into shareholders’ value is not specified.

To overcome such scenarios managers at Completeness Service needs to not only know the financial aspect of project management but also needs to have tools to integrate them into part of the project development and monitoring plan.

Calculating Net Present Value (NPV) at 15%

After working through various assumptions we reached a conclusion that risk is far higher than 6%. In a reasonably stable industry with weak competition - 15% discount rate can be a good benchmark.



Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 15 %
Discounted
Cash Flows
Year 0 (10005911) -10005911 - -
Year 1 3453940 -6551971 3453940 0.8696 3003426
Year 2 3978174 -2573797 7432114 0.7561 3008071
Year 3 3964941 1391144 11397055 0.6575 2607013
Year 4 3240636 4631780 14637691 0.5718 1852844
TOTAL 10471354


The Net NPV after 4 years is 465443

(10471354 - 10005911 )








Calculating Net Present Value (NPV) at 20%


If the risk component is high in the industry then we should go for a higher hurdle rate / discount rate of 20%.

Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 20 %
Discounted
Cash Flows
Year 0 (10005911) -10005911 - -
Year 1 3453940 -6551971 3453940 0.8333 2878283
Year 2 3978174 -2573797 7432114 0.6944 2762621
Year 3 3964941 1391144 11397055 0.5787 2294526
Year 4 3240636 4631780 14637691 0.4823 1562807
TOTAL 9498237


The Net NPV after 4 years is -507674

At 20% discount rate the NPV is negative (9498237 - 10005911 ) so ideally we can't select the project if macro and micro factors don't allow financial managers of Completeness Service to discount cash flow at lower discount rates such as 15%.





Acceptance Criteria of a Project based on NPV

Simplest Approach – If the investment project of Completeness Service has a NPV value higher than Zero then finance managers at Completeness Service can ACCEPT the project, otherwise they can reject the project. This means that project will deliver higher returns over the period of time than any alternate investment strategy.

In theory if the required rate of return or discount rate is chosen correctly by finance managers at Completeness Service, then the stock price of the Completeness Service should change by same amount of the NPV. In real world we know that share price also reflects various other factors that can be related to both macro and micro environment.

In the same vein – accepting the project with zero NPV should result in stagnant share price. Finance managers use discount rates as a measure of risk components in the project execution process.

Sensitivity Analysis

Project selection is often a far more complex decision than just choosing it based on the NPV number. Finance managers at Completeness Service should conduct a sensitivity analysis to better understand not only the inherent risk of the projects but also how those risks can be either factored in or mitigated during the project execution. Sensitivity analysis helps in –

What are the key aspects of the projects that need to be monitored, refined, and retuned for continuous delivery of projected cash flows.

What are the uncertainties surrounding the project Initial Cash Outlay (ICO’s). ICO’s often have several different components such as land, machinery, building, and other equipment.

Understanding of risks involved in the project.

What can impact the cash flow of the project.

What will be a multi year spillover effect of various taxation regulations.

Some of the assumptions while using the Discounted Cash Flow Methods –

Projects are assumed to be Mutually Exclusive – This is seldom the came in modern day giant organizations where projects are often inter-related and rejecting a project solely based on NPV can result in sunk cost from a related project.

Independent projects have independent cash flows – As explained in the marketing project – though the project may look independent but in reality it is not as the brand awareness project can be closely associated with the spending on sales promotions and product specific advertising.






Negotiation Strategy of Process Completeness: Strategies for Aligning Service Systems with Customers' Service Needs

References & Further Readings

Gabriele Piccoli, Kathryn Brohman, Richard T. Watson, A Parasuraman (2018), "Process Completeness: Strategies for Aligning Service Systems with Customers' Service Needs Harvard Business Review Case Study. Published by HBR Publications.


Legal & General SWOT Analysis / TOWS Matrix

Financial , Investment Services


S&T Holdings SWOT Analysis / TOWS Matrix

Consumer Cyclical , Auto & Truck Parts


Fusion Pharm Inc SWOT Analysis / TOWS Matrix

Financial , Consumer Financial Services


Apar Industries Ltd SWOT Analysis / TOWS Matrix

Technology , Electronic Instr. & Controls


AI Inc SWOT Analysis / TOWS Matrix

Technology , Software & Programming


Zero to Seven SWOT Analysis / TOWS Matrix

Consumer Cyclical , Apparel/Accessories


Dundee Corp SWOT Analysis / TOWS Matrix

Services , Real Estate Operations


Meiwa Corp SWOT Analysis / TOWS Matrix

Basic Materials , Chemical Manufacturing


Beneteau SWOT Analysis / TOWS Matrix

Consumer Cyclical , Recreational Products


Jaguar Health SWOT Analysis / TOWS Matrix

Healthcare , Biotechnology & Drugs