Sustainable Growth at TerraCycle: Should Manufacturing Be Moved? Net Present Value (NPV) / MBA Resources

Introduction to Net Present Value (NPV) - What is Net Present Value (NPV) ? How it impacts financial decisions regarding project management?

NPV solution for Sustainable Growth at TerraCycle: Should Manufacturing Be Moved? case study


At Oak Spring University, we provide corporate level professional Net Present Value (NPV) case study solution. Sustainable Growth at TerraCycle: Should Manufacturing Be Moved? case study is a Harvard Business School (HBR) case study written by Diane Phillips, Jason Keith Phillips. The Sustainable Growth at TerraCycle: Should Manufacturing Be Moved? (referred as “Terracycle Phillips” from here on) case study provides evaluation & decision scenario in field of Leadership & Managing People. It also touches upon business topics such as - Value proposition, International business, Manufacturing, Marketing, Sustainability.

The net present value (NPV) of an investment proposal is the present value of the proposal’s net cash flows less the proposal’s initial cash outflow. If a project’s NPV is greater than or equal to zero, the project should be accepted.

NPV = Present Value of Future Cash Flows LESS Project’s Initial Investment






Case Description of Sustainable Growth at TerraCycle: Should Manufacturing Be Moved? Case Study


As of April 2012, TerraCycle had witnessed exponential growth over the past few years due to its unique value proposition of creating a line of consumer products out of trash. With continued global expansion, the firm's biggest challenge was how to move forward while staying true to its mission to eliminate as much waste as possible from landfills, make fun products that consumers liked, and turn a profit. Operationally, TerraCycle was losing money on every domestically manufactured product and was regularly late on delivering its shipments to a major retail customer. All signs indicated that the company should move some of its manufacturing to an offshore location; however, TerraCycle had built its reputation on its strict adherence to the principles of sustainability, and such a move could cause a significant public-relations problem. There was little time to act, as orders from Walmart and Target were piling up. Should the CEO move some of TerraCycle's production to China? Diane M. Phillips is affiliated with Saint Joseph's University. Jason Keith Phillips is affiliated with West Chester University.


Case Authors : Diane Phillips, Jason Keith Phillips

Topic : Leadership & Managing People

Related Areas : International business, Manufacturing, Marketing, Sustainability




Calculating Net Present Value (NPV) at 6% for Sustainable Growth at TerraCycle: Should Manufacturing Be Moved? Case Study


Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 6 %
Discounted
Cash Flows
Year 0 (10012952) -10012952 - -
Year 1 3449154 -6563798 3449154 0.9434 3253919
Year 2 3977559 -2586239 7426713 0.89 3540013
Year 3 3940183 1353944 11366896 0.8396 3308254
Year 4 3223469 4577413 14590365 0.7921 2553289
TOTAL 14590365 12655475




The Net Present Value at 6% discount rate is 2642523

In isolation the NPV number doesn't mean much but put in right context then it is one of the best method to evaluate project returns. In this article we will cover -

Different methods of capital budgeting


What is NPV & Formula of NPV,
How it is calculated,
How to use NPV number for project evaluation, and
Scenario Planning given risks and management priorities.




Capital Budgeting Approaches

Methods of Capital Budgeting


There are four types of capital budgeting techniques that are widely used in the corporate world –

1. Payback Period
2. Internal Rate of Return
3. Profitability Index
4. Net Present Value

Apart from the Payback period method which is an additive method, rest of the methods are based on Discounted Cash Flow technique. Even though cash flow can be calculated based on the nature of the project, for the simplicity of the article we are assuming that all the expected cash flows are realized at the end of the year.

Discounted Cash Flow approaches provide a more objective basis for evaluating and selecting investment projects. They take into consideration both –

1. Timing of the expected cash flows – stockholders of Terracycle Phillips have higher preference for cash returns over 4-5 years rather than 10-15 years given the nature of the volatility in the industry.
2. Magnitude of both incoming and outgoing cash flows – Projects can be capital intensive, time intensive, or both. Terracycle Phillips shareholders have preference for diversified projects investment rather than prospective high income from a single capital intensive project.






Formula and Steps to Calculate Net Present Value (NPV) of Sustainable Growth at TerraCycle: Should Manufacturing Be Moved?

NPV = Net Cash In Flowt1 / (1+r)t1 + Net Cash In Flowt2 / (1+r)t2 + … Net Cash In Flowtn / (1+r)tn
Less Net Cash Out Flowt0 / (1+r)t0

Where t = time period, in this case year 1, year 2 and so on.
r = discount rate or return that could be earned using other safe proposition such as fixed deposit or treasury bond rate. Net Cash In Flow – What the firm will get each year.
Net Cash Out Flow – What the firm needs to invest initially in the project.

Step 1 – Understand the nature of the project and calculate cash flow for each year.
Step 2 – Discount those cash flow based on the discount rate.
Step 3 – Add all the discounted cash flow.
Step 4 – Selection of the project

Why Leadership & Managing People Managers need to know Financial Tools such as Net Present Value (NPV)?

In our daily workplace we often come across people and colleagues who are just focused on their core competency and targets they have to deliver. For example marketing managers at Terracycle Phillips often design programs whose objective is to drive brand awareness and customer reach. But how that 30 point increase in brand awareness or 10 point increase in customer touch points will result into shareholders’ value is not specified.

To overcome such scenarios managers at Terracycle Phillips needs to not only know the financial aspect of project management but also needs to have tools to integrate them into part of the project development and monitoring plan.

Calculating Net Present Value (NPV) at 15%

After working through various assumptions we reached a conclusion that risk is far higher than 6%. In a reasonably stable industry with weak competition - 15% discount rate can be a good benchmark.



Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 15 %
Discounted
Cash Flows
Year 0 (10012952) -10012952 - -
Year 1 3449154 -6563798 3449154 0.8696 2999264
Year 2 3977559 -2586239 7426713 0.7561 3007606
Year 3 3940183 1353944 11366896 0.6575 2590734
Year 4 3223469 4577413 14590365 0.5718 1843029
TOTAL 10440634


The Net NPV after 4 years is 427682

(10440634 - 10012952 )








Calculating Net Present Value (NPV) at 20%


If the risk component is high in the industry then we should go for a higher hurdle rate / discount rate of 20%.

Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 20 %
Discounted
Cash Flows
Year 0 (10012952) -10012952 - -
Year 1 3449154 -6563798 3449154 0.8333 2874295
Year 2 3977559 -2586239 7426713 0.6944 2762194
Year 3 3940183 1353944 11366896 0.5787 2280198
Year 4 3223469 4577413 14590365 0.4823 1554528
TOTAL 9471215


The Net NPV after 4 years is -541737

At 20% discount rate the NPV is negative (9471215 - 10012952 ) so ideally we can't select the project if macro and micro factors don't allow financial managers of Terracycle Phillips to discount cash flow at lower discount rates such as 15%.





Acceptance Criteria of a Project based on NPV

Simplest Approach – If the investment project of Terracycle Phillips has a NPV value higher than Zero then finance managers at Terracycle Phillips can ACCEPT the project, otherwise they can reject the project. This means that project will deliver higher returns over the period of time than any alternate investment strategy.

In theory if the required rate of return or discount rate is chosen correctly by finance managers at Terracycle Phillips, then the stock price of the Terracycle Phillips should change by same amount of the NPV. In real world we know that share price also reflects various other factors that can be related to both macro and micro environment.

In the same vein – accepting the project with zero NPV should result in stagnant share price. Finance managers use discount rates as a measure of risk components in the project execution process.

Sensitivity Analysis

Project selection is often a far more complex decision than just choosing it based on the NPV number. Finance managers at Terracycle Phillips should conduct a sensitivity analysis to better understand not only the inherent risk of the projects but also how those risks can be either factored in or mitigated during the project execution. Sensitivity analysis helps in –

What can impact the cash flow of the project.

What will be a multi year spillover effect of various taxation regulations.

Understanding of risks involved in the project.

What are the uncertainties surrounding the project Initial Cash Outlay (ICO’s). ICO’s often have several different components such as land, machinery, building, and other equipment.

What are the key aspects of the projects that need to be monitored, refined, and retuned for continuous delivery of projected cash flows.

Some of the assumptions while using the Discounted Cash Flow Methods –

Projects are assumed to be Mutually Exclusive – This is seldom the came in modern day giant organizations where projects are often inter-related and rejecting a project solely based on NPV can result in sunk cost from a related project.

Independent projects have independent cash flows – As explained in the marketing project – though the project may look independent but in reality it is not as the brand awareness project can be closely associated with the spending on sales promotions and product specific advertising.






Negotiation Strategy of Sustainable Growth at TerraCycle: Should Manufacturing Be Moved?

References & Further Readings

Diane Phillips, Jason Keith Phillips (2018), "Sustainable Growth at TerraCycle: Should Manufacturing Be Moved? Harvard Business Review Case Study. Published by HBR Publications.


Zhe Jiang Dong Ri SWOT Analysis / TOWS Matrix

Capital Goods , Construction Services


SingHaiyi Group Ltd SWOT Analysis / TOWS Matrix

Services , Real Estate Operations


Airport City SWOT Analysis / TOWS Matrix

Services , Real Estate Operations


Poalim Ibi SWOT Analysis / TOWS Matrix

Financial , Investment Services


Idox SWOT Analysis / TOWS Matrix

Technology , Software & Programming


Ram-On Investments SWOT Analysis / TOWS Matrix

Basic Materials , Chemicals - Plastics & Rubber


Acacia Com SWOT Analysis / TOWS Matrix

Technology , Communications Equipment


Zuiko SWOT Analysis / TOWS Matrix

Capital Goods , Misc. Capital Goods


Evraz SWOT Analysis / TOWS Matrix

Basic Materials , Iron & Steel


Hancock Jaffe Labs SWOT Analysis / TOWS Matrix

Healthcare , Biotechnology & Drugs