Introduction to Net Present Value (NPV) - What is Net Present Value (NPV) ? How it impacts financial decisions regarding project management?

NPV solution for Lincoln Industries case study


At Oak Spring University, we provide corporate level professional Net Present Value (NPV) case study solution. Lincoln Industries case study is a Harvard Business School (HBR) case study written by S. Venkataraman, Alexander Horniman. The Lincoln Industries (referred as “Lincoln Successors” from here on) case study provides evaluation & decision scenario in field of Leadership & Managing People. It also touches upon business topics such as - Value proposition, Leadership, Organizational culture, Strategy, Succession planning.

The net present value (NPV) of an investment proposal is the present value of the proposal’s net cash flows less the proposal’s initial cash outflow. If a project’s NPV is greater than or equal to zero, the project should be accepted.

NPV = Present Value of Future Cash Flows LESS Project’s Initial Investment






Case Description of Lincoln Industries Case Study


This is a Darden case study.What are the differences between being a good tactical leader and being a good strategic leader? As he nears retirement, Robert Lincoln muses about his successor at Lincoln Industries. The case describes the backgrounds of four potential successors, all of whom are tactically astute and very competent general managers. Lincoln realizes that the company is at a crossroads and wonders what it would take for his potential successors to graduate from being good tactical leaders to effective strategic leaders.


Case Authors : S. Venkataraman, Alexander Horniman

Topic : Leadership & Managing People

Related Areas : Leadership, Organizational culture, Strategy, Succession planning




Calculating Net Present Value (NPV) at 6% for Lincoln Industries Case Study


Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 6 %
Discounted
Cash Flows
Year 0 (10012208) -10012208 - -
Year 1 3471829 -6540379 3471829 0.9434 3275310
Year 2 3957633 -2582746 7429462 0.89 3522279
Year 3 3940907 1358161 11370369 0.8396 3308862
Year 4 3251098 4609259 14621467 0.7921 2575174
TOTAL 14621467 12681625




The Net Present Value at 6% discount rate is 2669417

In isolation the NPV number doesn't mean much but put in right context then it is one of the best method to evaluate project returns. In this article we will cover -

Different methods of capital budgeting


What is NPV & Formula of NPV,
How it is calculated,
How to use NPV number for project evaluation, and
Scenario Planning given risks and management priorities.




Capital Budgeting Approaches

Methods of Capital Budgeting


There are four types of capital budgeting techniques that are widely used in the corporate world –

1. Payback Period
2. Internal Rate of Return
3. Profitability Index
4. Net Present Value

Apart from the Payback period method which is an additive method, rest of the methods are based on Discounted Cash Flow technique. Even though cash flow can be calculated based on the nature of the project, for the simplicity of the article we are assuming that all the expected cash flows are realized at the end of the year.

Discounted Cash Flow approaches provide a more objective basis for evaluating and selecting investment projects. They take into consideration both –

1. Timing of the expected cash flows – stockholders of Lincoln Successors have higher preference for cash returns over 4-5 years rather than 10-15 years given the nature of the volatility in the industry.
2. Magnitude of both incoming and outgoing cash flows – Projects can be capital intensive, time intensive, or both. Lincoln Successors shareholders have preference for diversified projects investment rather than prospective high income from a single capital intensive project.






Formula and Steps to Calculate Net Present Value (NPV) of Lincoln Industries

NPV = Net Cash In Flowt1 / (1+r)t1 + Net Cash In Flowt2 / (1+r)t2 + … Net Cash In Flowtn / (1+r)tn
Less Net Cash Out Flowt0 / (1+r)t0

Where t = time period, in this case year 1, year 2 and so on.
r = discount rate or return that could be earned using other safe proposition such as fixed deposit or treasury bond rate. Net Cash In Flow – What the firm will get each year.
Net Cash Out Flow – What the firm needs to invest initially in the project.

Step 1 – Understand the nature of the project and calculate cash flow for each year.
Step 2 – Discount those cash flow based on the discount rate.
Step 3 – Add all the discounted cash flow.
Step 4 – Selection of the project

Why Leadership & Managing People Managers need to know Financial Tools such as Net Present Value (NPV)?

In our daily workplace we often come across people and colleagues who are just focused on their core competency and targets they have to deliver. For example marketing managers at Lincoln Successors often design programs whose objective is to drive brand awareness and customer reach. But how that 30 point increase in brand awareness or 10 point increase in customer touch points will result into shareholders’ value is not specified.

To overcome such scenarios managers at Lincoln Successors needs to not only know the financial aspect of project management but also needs to have tools to integrate them into part of the project development and monitoring plan.

Calculating Net Present Value (NPV) at 15%

After working through various assumptions we reached a conclusion that risk is far higher than 6%. In a reasonably stable industry with weak competition - 15% discount rate can be a good benchmark.



Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 15 %
Discounted
Cash Flows
Year 0 (10012208) -10012208 - -
Year 1 3471829 -6540379 3471829 0.8696 3018982
Year 2 3957633 -2582746 7429462 0.7561 2992539
Year 3 3940907 1358161 11370369 0.6575 2591210
Year 4 3251098 4609259 14621467 0.5718 1858826
TOTAL 10461557


The Net NPV after 4 years is 449349

(10461557 - 10012208 )








Calculating Net Present Value (NPV) at 20%


If the risk component is high in the industry then we should go for a higher hurdle rate / discount rate of 20%.

Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 20 %
Discounted
Cash Flows
Year 0 (10012208) -10012208 - -
Year 1 3471829 -6540379 3471829 0.8333 2893191
Year 2 3957633 -2582746 7429462 0.6944 2748356
Year 3 3940907 1358161 11370369 0.5787 2280617
Year 4 3251098 4609259 14621467 0.4823 1567852
TOTAL 9490017


The Net NPV after 4 years is -522191

At 20% discount rate the NPV is negative (9490017 - 10012208 ) so ideally we can't select the project if macro and micro factors don't allow financial managers of Lincoln Successors to discount cash flow at lower discount rates such as 15%.





Acceptance Criteria of a Project based on NPV

Simplest Approach – If the investment project of Lincoln Successors has a NPV value higher than Zero then finance managers at Lincoln Successors can ACCEPT the project, otherwise they can reject the project. This means that project will deliver higher returns over the period of time than any alternate investment strategy.

In theory if the required rate of return or discount rate is chosen correctly by finance managers at Lincoln Successors, then the stock price of the Lincoln Successors should change by same amount of the NPV. In real world we know that share price also reflects various other factors that can be related to both macro and micro environment.

In the same vein – accepting the project with zero NPV should result in stagnant share price. Finance managers use discount rates as a measure of risk components in the project execution process.

Sensitivity Analysis

Project selection is often a far more complex decision than just choosing it based on the NPV number. Finance managers at Lincoln Successors should conduct a sensitivity analysis to better understand not only the inherent risk of the projects but also how those risks can be either factored in or mitigated during the project execution. Sensitivity analysis helps in –

What will be a multi year spillover effect of various taxation regulations.

What are the key aspects of the projects that need to be monitored, refined, and retuned for continuous delivery of projected cash flows.

What can impact the cash flow of the project.

Understanding of risks involved in the project.

What are the uncertainties surrounding the project Initial Cash Outlay (ICO’s). ICO’s often have several different components such as land, machinery, building, and other equipment.

Some of the assumptions while using the Discounted Cash Flow Methods –

Projects are assumed to be Mutually Exclusive – This is seldom the came in modern day giant organizations where projects are often inter-related and rejecting a project solely based on NPV can result in sunk cost from a related project.

Independent projects have independent cash flows – As explained in the marketing project – though the project may look independent but in reality it is not as the brand awareness project can be closely associated with the spending on sales promotions and product specific advertising.






Negotiation Strategy of Lincoln Industries

References & Further Readings

S. Venkataraman, Alexander Horniman (2018), "Lincoln Industries Harvard Business Review Case Study. Published by HBR Publications.


Ujaas Energy Ltd SWOT Analysis / TOWS Matrix

Technology , Electronic Instr. & Controls


Atlantia SWOT Analysis / TOWS Matrix

Transportation , Misc. Transportation


ADDvantage SWOT Analysis / TOWS Matrix

Technology , Electronic Instr. & Controls


Systems Design SWOT Analysis / TOWS Matrix

Technology , Software & Programming


Reven Housing Reit SWOT Analysis / TOWS Matrix

Services , Real Estate Operations


Timah Persero SWOT Analysis / TOWS Matrix

Basic Materials , Metal Mining


ANG Industries Ltd SWOT Analysis / TOWS Matrix

Consumer Cyclical , Auto & Truck Parts


COSCO Shipping Energy SWOT Analysis / TOWS Matrix

Transportation , Water Transportation


First Trust Energy SWOT Analysis / TOWS Matrix

Financial , Misc. Financial Services


Iomart SWOT Analysis / TOWS Matrix

Technology , Computer Services