Introduction to Net Present Value (NPV) - What is Net Present Value (NPV) ? How it impacts financial decisions regarding project management?
At Oak Spring University, we provide corporate level professional Net Present Value (NPV) case study solution. Shriram Transport Finance case study is a Harvard Business School (HBR) case study written by Gennaro Bernile, Anand Shankar, Rahul Rajani. The Shriram Transport Finance (referred as “Exit Tpg” from here on) case study provides evaluation & decision scenario in field of Finance & Accounting. It also touches upon business topics such as - Value proposition, Financial management, International business.
The net present value (NPV) of an investment proposal is the present value of the proposal’s net cash flows less the proposal’s initial cash outflow. If a project’s NPV is greater than or equal to zero, the project should be accepted.
In December 2012, the stock of Shriram Transport Finance Company (STFC) had just breached the a‚¹750 mark, signifying an appreciation of close to 80 per cent for the calendar year of 2012. Texas Pacific Group (TPG), the global private equity firm, had invested in STFC at a time when the share price was hovering around a‚¹100. As was the case with most private equity firms, a successful exit from an investment was of paramount importance for TPG in order to reap handsome returns. In the course of charting the exit path from an investment, private equity firms had to consider several critical issues including exit structure, timeline for exit, and regulatory hurdles. There were three usual choices of exit routes: initial public offering, trade sale, or secondary sale. Each of the exit routes had its own advantages and disadvantages. Was this the right time for TPG to exit STFC? If yes, which option should TPG pursue? Gennaro Bernile is affiliated with Singapore Management University. Anand Shankar is affiliated with Singapore Management University. Rahul Rajani is affiliated with Singapore Management University.
Years | Cash Flow | Net Cash Flow | Cumulative Cash Flow |
Discount Rate @ 6 % |
Discounted Cash Flows |
---|---|---|---|---|---|
Year 0 | (10029100) | -10029100 | - | - | |
Year 1 | 3467349 | -6561751 | 3467349 | 0.9434 | 3271084 |
Year 2 | 3953474 | -2608277 | 7420823 | 0.89 | 3518578 |
Year 3 | 3953344 | 1345067 | 11374167 | 0.8396 | 3319304 |
Year 4 | 3239310 | 4584377 | 14613477 | 0.7921 | 2565837 |
TOTAL | 14613477 | 12674803 |
In isolation the NPV number doesn't mean much but put in right context then it is one of the best method to evaluate project returns. In this article we will cover -
Capital Budgeting Approaches
There are four types of capital budgeting techniques that are widely used in the corporate world –
1. Internal Rate of Return
2. Profitability Index
3. Net Present Value
4. Payback Period
Apart from the Payback period method which is an additive method, rest of the methods are based on
Discounted Cash Flow
technique. Even though cash flow can be calculated based on the nature of the project, for the simplicity of the article we are assuming that all the expected cash flows are realized at the end of the year.
Discounted Cash Flow approaches provide a more objective basis for evaluating and selecting investment projects. They take into consideration both –
1. Timing of the expected cash flows – stockholders of Exit Tpg have higher preference for cash returns over 4-5 years rather than 10-15 years given the nature of the volatility in the industry.
2. Magnitude of both incoming and outgoing cash flows – Projects can be capital intensive, time intensive, or both. Exit Tpg shareholders have preference for diversified projects investment rather than prospective high income from a single capital intensive project.
NPV = Net Cash In Flowt1 / (1+r)t1 + Net Cash In Flowt2 / (1+r)t2 + … Net Cash In Flowtn / (1+r)tn
Less Net Cash Out Flowt0 / (1+r)t0
Where t = time period, in this case year 1, year 2 and so on.
r = discount rate or return that could be earned using other safe proposition such as fixed deposit or treasury bond rate.
Net Cash In Flow – What the firm will get each year.
Net Cash Out Flow – What the firm needs to invest initially in the project.
Step 1 – Understand the nature of the project and calculate cash flow for each year.
Step 2 – Discount those cash flow based on the discount rate.
Step 3 – Add all the discounted cash flow.
Step 4 – Selection of the project
In our daily workplace we often come across people and colleagues who are just focused on their core competency and targets they have to deliver. For example marketing managers at Exit Tpg often design programs whose objective is to drive brand awareness and customer reach. But how that 30 point increase in brand awareness or 10 point increase in customer touch points will result into shareholders’ value is not specified.
To overcome such scenarios managers at Exit Tpg needs to not only know the financial aspect of project management but also needs to have tools to integrate them into part of the project development and monitoring plan.
After working through various assumptions we reached a conclusion that risk is far higher than 6%. In a reasonably stable industry with weak competition - 15% discount rate can be a good benchmark.
Years | Cash Flow | Net Cash Flow | Cumulative Cash Flow |
Discount Rate @ 15 % |
Discounted Cash Flows |
---|---|---|---|---|---|
Year 0 | (10029100) | -10029100 | - | - | |
Year 1 | 3467349 | -6561751 | 3467349 | 0.8696 | 3015086 |
Year 2 | 3953474 | -2608277 | 7420823 | 0.7561 | 2989394 |
Year 3 | 3953344 | 1345067 | 11374167 | 0.6575 | 2599388 |
Year 4 | 3239310 | 4584377 | 14613477 | 0.5718 | 1852086 |
TOTAL | 10455954 |
(10455954 - 10029100 )
If the risk component is high in the industry then we should go for a higher hurdle rate / discount rate of 20%.
Years | Cash Flow | Net Cash Flow | Cumulative Cash Flow |
Discount Rate @ 20 % |
Discounted Cash Flows |
---|---|---|---|---|---|
Year 0 | (10029100) | -10029100 | - | - | |
Year 1 | 3467349 | -6561751 | 3467349 | 0.8333 | 2889458 |
Year 2 | 3953474 | -2608277 | 7420823 | 0.6944 | 2745468 |
Year 3 | 3953344 | 1345067 | 11374167 | 0.5787 | 2287815 |
Year 4 | 3239310 | 4584377 | 14613477 | 0.4823 | 1562167 |
TOTAL | 9484908 |
At 20% discount rate the NPV is negative (9484908 - 10029100 ) so ideally we can't select the project if macro and micro factors don't allow financial managers of Exit Tpg to discount cash flow at lower discount rates such as 15%.
Simplest Approach – If the investment project of Exit Tpg has a NPV value higher than Zero then finance managers at Exit Tpg can ACCEPT the project, otherwise they can reject the project. This means that project will deliver higher returns over the period of time than any alternate investment strategy.
In theory if the required rate of return or discount rate is chosen correctly by finance managers at Exit Tpg, then the stock price of the Exit Tpg should change by same amount of the NPV. In real world we know that share price also reflects various other factors that can be related to both macro and micro environment.
In the same vein – accepting the project with zero NPV should result in stagnant share price. Finance managers use discount rates as a measure of risk components in the project execution process.
Project selection is often a far more complex decision than just choosing it based on the NPV number. Finance managers at Exit Tpg should conduct a sensitivity analysis to better understand not only the inherent risk of the projects but also how those risks can be either factored in or mitigated during the project execution. Sensitivity analysis helps in –
What will be a multi year spillover effect of various taxation regulations.
What are the uncertainties surrounding the project Initial Cash Outlay (ICO’s). ICO’s often have several different components such as land, machinery, building, and other equipment.
What can impact the cash flow of the project.
What are the key aspects of the projects that need to be monitored, refined, and retuned for continuous delivery of projected cash flows.
Understanding of risks involved in the project.
Projects are assumed to be Mutually Exclusive – This is seldom the came in modern day giant organizations where projects are often inter-related and rejecting a project solely based on NPV can result in sunk cost from a related project.
Independent projects have independent cash flows – As explained in the marketing project – though the project may look independent but in reality it is not as the brand awareness project can be closely associated with the spending on sales promotions and product specific advertising.
Gennaro Bernile, Anand Shankar, Rahul Rajani (2018), "Shriram Transport Finance Harvard Business Review Case Study. Published by HBR Publications.
Feel free to connect with us if you need business research.
You can download Excel Template of Case Study Solution & Analysis of Shriram Transport Finance
Consumer Cyclical , Auto & Truck Parts
Services , Rental & Leasing
Services , Business Services
Services , Real Estate Operations
Transportation , Misc. Transportation
Transportation , Water Transportation
Capital Goods , Misc. Capital Goods
Technology , Communications Equipment
Technology , Computer Services
Financial , Misc. Financial Services
Financial , Misc. Financial Services
Services , Communications Services