Introduction to Net Present Value (NPV) - What is Net Present Value (NPV) ? How it impacts financial decisions regarding project management?
At Oak Spring University, we provide corporate level professional Net Present Value (NPV) case study solution. Walter Reed National Military Medical Center (Epilogue): JTF CapMed: Three Years Later case study is a Harvard Business School (HBR) case study written by Linda Bilmes, Matt Mabe. The Walter Reed National Military Medical Center (Epilogue): JTF CapMed: Three Years Later (referred as “Mateczun Walter” from here on) case study provides evaluation & decision scenario in field of Leadership & Managing People. It also touches upon business topics such as - Value proposition, Government, Leadership, Mergers & acquisitions.
The net present value (NPV) of an investment proposal is the present value of the proposal’s net cash flows less the proposal’s initial cash outflow. If a project’s NPV is greater than or equal to zero, the project should be accepted.
This case is part of a four part series that examines the merger of the Walter Reed Army Medical Center and the National Naval Military Center at Bethesda - the most expensive, controversial and largest hospital merger in US history. The series includes: A case + A teaching note (Leadership of VADM Mateczun); B case + B teaching note (Army/Navy cultural issues); Epilogue (short conclusion); Film - award winning short documentary. The A case focuses on the leadership of Vice Admiral Dr. John Mateczun, a three-star Navy admiral who led the merger. Mateczun achieved what many considered to be a minor miracle - integrating Walter Reed and Bethesda Naval in the face of fierce institutional resistance. But in his drive to see the plan through, Mateczun stretched the limit of military authority, expended his political capital and alienated friends and colleagues. The case allows discussion of leadership styles and the importance of persuasion, negotiation, communication issues, and personal character. There are two companion cases and a 17-minute film. The film shows a brief history of the hospitals, explains the BRAC (Base Closure Commission), and shows the intensity and urgency of the medical needs of patients being cared for at Walter Reed during the height of the Iraq and Afghanistan wars. The B Case focuses on the difficulties of merging organizations with significant cultural differences. It may be taught together with the (A) case or on its own with the video. The short Epilogue looks at the outcome in 2014, 3 years after the merger. Case number 2035.0
Years | Cash Flow | Net Cash Flow | Cumulative Cash Flow |
Discount Rate @ 6 % |
Discounted Cash Flows |
---|---|---|---|---|---|
Year 0 | (10005691) | -10005691 | - | - | |
Year 1 | 3469879 | -6535812 | 3469879 | 0.9434 | 3273471 |
Year 2 | 3962966 | -2572846 | 7432845 | 0.89 | 3527026 |
Year 3 | 3959392 | 1386546 | 11392237 | 0.8396 | 3324382 |
Year 4 | 3243666 | 4630212 | 14635903 | 0.7921 | 2569287 |
TOTAL | 14635903 | 12694166 |
In isolation the NPV number doesn't mean much but put in right context then it is one of the best method to evaluate project returns. In this article we will cover -
Capital Budgeting Approaches
There are four types of capital budgeting techniques that are widely used in the corporate world –
1. Net Present Value
2. Profitability Index
3. Payback Period
4. Internal Rate of Return
Apart from the Payback period method which is an additive method, rest of the methods are based on
Discounted Cash Flow
technique. Even though cash flow can be calculated based on the nature of the project, for the simplicity of the article we are assuming that all the expected cash flows are realized at the end of the year.
Discounted Cash Flow approaches provide a more objective basis for evaluating and selecting investment projects. They take into consideration both –
1. Timing of the expected cash flows – stockholders of Mateczun Walter have higher preference for cash returns over 4-5 years rather than 10-15 years given the nature of the volatility in the industry.
2. Magnitude of both incoming and outgoing cash flows – Projects can be capital intensive, time intensive, or both. Mateczun Walter shareholders have preference for diversified projects investment rather than prospective high income from a single capital intensive project.
NPV = Net Cash In Flowt1 / (1+r)t1 + Net Cash In Flowt2 / (1+r)t2 + … Net Cash In Flowtn / (1+r)tn
Less Net Cash Out Flowt0 / (1+r)t0
Where t = time period, in this case year 1, year 2 and so on.
r = discount rate or return that could be earned using other safe proposition such as fixed deposit or treasury bond rate.
Net Cash In Flow – What the firm will get each year.
Net Cash Out Flow – What the firm needs to invest initially in the project.
Step 1 – Understand the nature of the project and calculate cash flow for each year.
Step 2 – Discount those cash flow based on the discount rate.
Step 3 – Add all the discounted cash flow.
Step 4 – Selection of the project
In our daily workplace we often come across people and colleagues who are just focused on their core competency and targets they have to deliver. For example marketing managers at Mateczun Walter often design programs whose objective is to drive brand awareness and customer reach. But how that 30 point increase in brand awareness or 10 point increase in customer touch points will result into shareholders’ value is not specified.
To overcome such scenarios managers at Mateczun Walter needs to not only know the financial aspect of project management but also needs to have tools to integrate them into part of the project development and monitoring plan.
After working through various assumptions we reached a conclusion that risk is far higher than 6%. In a reasonably stable industry with weak competition - 15% discount rate can be a good benchmark.
Years | Cash Flow | Net Cash Flow | Cumulative Cash Flow |
Discount Rate @ 15 % |
Discounted Cash Flows |
---|---|---|---|---|---|
Year 0 | (10005691) | -10005691 | - | - | |
Year 1 | 3469879 | -6535812 | 3469879 | 0.8696 | 3017286 |
Year 2 | 3962966 | -2572846 | 7432845 | 0.7561 | 2996572 |
Year 3 | 3959392 | 1386546 | 11392237 | 0.6575 | 2603365 |
Year 4 | 3243666 | 4630212 | 14635903 | 0.5718 | 1854577 |
TOTAL | 10471799 |
(10471799 - 10005691 )
If the risk component is high in the industry then we should go for a higher hurdle rate / discount rate of 20%.
Years | Cash Flow | Net Cash Flow | Cumulative Cash Flow |
Discount Rate @ 20 % |
Discounted Cash Flows |
---|---|---|---|---|---|
Year 0 | (10005691) | -10005691 | - | - | |
Year 1 | 3469879 | -6535812 | 3469879 | 0.8333 | 2891566 |
Year 2 | 3962966 | -2572846 | 7432845 | 0.6944 | 2752060 |
Year 3 | 3959392 | 1386546 | 11392237 | 0.5787 | 2291315 |
Year 4 | 3243666 | 4630212 | 14635903 | 0.4823 | 1564268 |
TOTAL | 9499208 |
At 20% discount rate the NPV is negative (9499208 - 10005691 ) so ideally we can't select the project if macro and micro factors don't allow financial managers of Mateczun Walter to discount cash flow at lower discount rates such as 15%.
Simplest Approach – If the investment project of Mateczun Walter has a NPV value higher than Zero then finance managers at Mateczun Walter can ACCEPT the project, otherwise they can reject the project. This means that project will deliver higher returns over the period of time than any alternate investment strategy.
In theory if the required rate of return or discount rate is chosen correctly by finance managers at Mateczun Walter, then the stock price of the Mateczun Walter should change by same amount of the NPV. In real world we know that share price also reflects various other factors that can be related to both macro and micro environment.
In the same vein – accepting the project with zero NPV should result in stagnant share price. Finance managers use discount rates as a measure of risk components in the project execution process.
Project selection is often a far more complex decision than just choosing it based on the NPV number. Finance managers at Mateczun Walter should conduct a sensitivity analysis to better understand not only the inherent risk of the projects but also how those risks can be either factored in or mitigated during the project execution. Sensitivity analysis helps in –
What are the key aspects of the projects that need to be monitored, refined, and retuned for continuous delivery of projected cash flows.
What will be a multi year spillover effect of various taxation regulations.
Understanding of risks involved in the project.
What are the uncertainties surrounding the project Initial Cash Outlay (ICO’s). ICO’s often have several different components such as land, machinery, building, and other equipment.
What can impact the cash flow of the project.
Projects are assumed to be Mutually Exclusive – This is seldom the came in modern day giant organizations where projects are often inter-related and rejecting a project solely based on NPV can result in sunk cost from a related project.
Independent projects have independent cash flows – As explained in the marketing project – though the project may look independent but in reality it is not as the brand awareness project can be closely associated with the spending on sales promotions and product specific advertising.
Linda Bilmes, Matt Mabe (2018), "Walter Reed National Military Medical Center (Epilogue): JTF CapMed: Three Years Later Harvard Business Review Case Study. Published by HBR Publications.
Feel free to connect with us if you need business research.
You can download Excel Template of Case Study Solution & Analysis of Walter Reed National Military Medical Center (Epilogue): JTF CapMed: Three Years Later
Capital Goods , Misc. Capital Goods
Capital Goods , Misc. Capital Goods
Financial , Misc. Financial Services
Financial , Investment Services
Financial , Regional Banks
Financial , Insurance (Life)
Technology , Software & Programming
Energy , Oil & Gas Operations
Basic Materials , Gold & Silver