Ashmark Corporation: Dealing with a Supply Disruption Net Present Value (NPV) / MBA Resources

Introduction to Net Present Value (NPV) - What is Net Present Value (NPV) ? How it impacts financial decisions regarding project management?

NPV solution for Ashmark Corporation: Dealing with a Supply Disruption case study


At Oak Spring University, we provide corporate level professional Net Present Value (NPV) case study solution. Ashmark Corporation: Dealing with a Supply Disruption case study is a Harvard Business School (HBR) case study written by Brent B. Moritz, Christopher W. Craighead. The Ashmark Corporation: Dealing with a Supply Disruption (referred as “Ashmark Red” from here on) case study provides evaluation & decision scenario in field of Leadership & Managing People. It also touches upon business topics such as - Value proposition, Supply chain.

The net present value (NPV) of an investment proposal is the present value of the proposal’s net cash flows less the proposal’s initial cash outflow. If a project’s NPV is greater than or equal to zero, the project should be accepted.

NPV = Present Value of Future Cash Flows LESS Project’s Initial Investment






Case Description of Ashmark Corporation: Dealing with a Supply Disruption Case Study


When Ashmark Corporation's largest supplier, Red Star Castings (Red Star), was forced to declare bankruptcy, Ashmark had to develop and implement a contingency plan, while also appeasing its customers, who were growing increasingly impatient for their parts to arrive. Since Red Star closed, Ashmark had been late on 200 units of production due to missing components. Although this figure represented less than 1 per cent of the company's total monthly shipments, things were likely to get more difficult, especially with the loss of key employees due to the stressful situation. In addition, the new supplier was having trouble bringing the tooling online, there were delays in the qualification and testing process, and the modest amount of inventory built up in advance of the bankruptcy had diminished. As Ashmark looked to move forwards, it would need to develop a much better sense of how to manage supply chain risk. Brent B. Moritz is affiliated with Pennsylvania State University. Christopher W. Craighead is affiliated with University of Tennessee.


Case Authors : Brent B. Moritz, Christopher W. Craighead

Topic : Leadership & Managing People

Related Areas : Supply chain




Calculating Net Present Value (NPV) at 6% for Ashmark Corporation: Dealing with a Supply Disruption Case Study


Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 6 %
Discounted
Cash Flows
Year 0 (10003348) -10003348 - -
Year 1 3459236 -6544112 3459236 0.9434 3263430
Year 2 3968486 -2575626 7427722 0.89 3531938
Year 3 3969461 1393835 11397183 0.8396 3332836
Year 4 3240432 4634267 14637615 0.7921 2566726
TOTAL 14637615 12694930




The Net Present Value at 6% discount rate is 2691582

In isolation the NPV number doesn't mean much but put in right context then it is one of the best method to evaluate project returns. In this article we will cover -

Different methods of capital budgeting


What is NPV & Formula of NPV,
How it is calculated,
How to use NPV number for project evaluation, and
Scenario Planning given risks and management priorities.




Capital Budgeting Approaches

Methods of Capital Budgeting


There are four types of capital budgeting techniques that are widely used in the corporate world –

1. Payback Period
2. Net Present Value
3. Profitability Index
4. Internal Rate of Return

Apart from the Payback period method which is an additive method, rest of the methods are based on Discounted Cash Flow technique. Even though cash flow can be calculated based on the nature of the project, for the simplicity of the article we are assuming that all the expected cash flows are realized at the end of the year.

Discounted Cash Flow approaches provide a more objective basis for evaluating and selecting investment projects. They take into consideration both –

1. Timing of the expected cash flows – stockholders of Ashmark Red have higher preference for cash returns over 4-5 years rather than 10-15 years given the nature of the volatility in the industry.
2. Magnitude of both incoming and outgoing cash flows – Projects can be capital intensive, time intensive, or both. Ashmark Red shareholders have preference for diversified projects investment rather than prospective high income from a single capital intensive project.






Formula and Steps to Calculate Net Present Value (NPV) of Ashmark Corporation: Dealing with a Supply Disruption

NPV = Net Cash In Flowt1 / (1+r)t1 + Net Cash In Flowt2 / (1+r)t2 + … Net Cash In Flowtn / (1+r)tn
Less Net Cash Out Flowt0 / (1+r)t0

Where t = time period, in this case year 1, year 2 and so on.
r = discount rate or return that could be earned using other safe proposition such as fixed deposit or treasury bond rate. Net Cash In Flow – What the firm will get each year.
Net Cash Out Flow – What the firm needs to invest initially in the project.

Step 1 – Understand the nature of the project and calculate cash flow for each year.
Step 2 – Discount those cash flow based on the discount rate.
Step 3 – Add all the discounted cash flow.
Step 4 – Selection of the project

Why Leadership & Managing People Managers need to know Financial Tools such as Net Present Value (NPV)?

In our daily workplace we often come across people and colleagues who are just focused on their core competency and targets they have to deliver. For example marketing managers at Ashmark Red often design programs whose objective is to drive brand awareness and customer reach. But how that 30 point increase in brand awareness or 10 point increase in customer touch points will result into shareholders’ value is not specified.

To overcome such scenarios managers at Ashmark Red needs to not only know the financial aspect of project management but also needs to have tools to integrate them into part of the project development and monitoring plan.

Calculating Net Present Value (NPV) at 15%

After working through various assumptions we reached a conclusion that risk is far higher than 6%. In a reasonably stable industry with weak competition - 15% discount rate can be a good benchmark.



Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 15 %
Discounted
Cash Flows
Year 0 (10003348) -10003348 - -
Year 1 3459236 -6544112 3459236 0.8696 3008031
Year 2 3968486 -2575626 7427722 0.7561 3000746
Year 3 3969461 1393835 11397183 0.6575 2609985
Year 4 3240432 4634267 14637615 0.5718 1852728
TOTAL 10471489


The Net NPV after 4 years is 468141

(10471489 - 10003348 )








Calculating Net Present Value (NPV) at 20%


If the risk component is high in the industry then we should go for a higher hurdle rate / discount rate of 20%.

Years              Cash Flow     Net Cash Flow     Cumulative    
Cash Flow
Discount Rate
@ 20 %
Discounted
Cash Flows
Year 0 (10003348) -10003348 - -
Year 1 3459236 -6544112 3459236 0.8333 2882697
Year 2 3968486 -2575626 7427722 0.6944 2755893
Year 3 3969461 1393835 11397183 0.5787 2297142
Year 4 3240432 4634267 14637615 0.4823 1562708
TOTAL 9498440


The Net NPV after 4 years is -504908

At 20% discount rate the NPV is negative (9498440 - 10003348 ) so ideally we can't select the project if macro and micro factors don't allow financial managers of Ashmark Red to discount cash flow at lower discount rates such as 15%.





Acceptance Criteria of a Project based on NPV

Simplest Approach – If the investment project of Ashmark Red has a NPV value higher than Zero then finance managers at Ashmark Red can ACCEPT the project, otherwise they can reject the project. This means that project will deliver higher returns over the period of time than any alternate investment strategy.

In theory if the required rate of return or discount rate is chosen correctly by finance managers at Ashmark Red, then the stock price of the Ashmark Red should change by same amount of the NPV. In real world we know that share price also reflects various other factors that can be related to both macro and micro environment.

In the same vein – accepting the project with zero NPV should result in stagnant share price. Finance managers use discount rates as a measure of risk components in the project execution process.

Sensitivity Analysis

Project selection is often a far more complex decision than just choosing it based on the NPV number. Finance managers at Ashmark Red should conduct a sensitivity analysis to better understand not only the inherent risk of the projects but also how those risks can be either factored in or mitigated during the project execution. Sensitivity analysis helps in –

What will be a multi year spillover effect of various taxation regulations.

Understanding of risks involved in the project.

What can impact the cash flow of the project.

What are the key aspects of the projects that need to be monitored, refined, and retuned for continuous delivery of projected cash flows.

What are the uncertainties surrounding the project Initial Cash Outlay (ICO’s). ICO’s often have several different components such as land, machinery, building, and other equipment.

Some of the assumptions while using the Discounted Cash Flow Methods –

Projects are assumed to be Mutually Exclusive – This is seldom the came in modern day giant organizations where projects are often inter-related and rejecting a project solely based on NPV can result in sunk cost from a related project.

Independent projects have independent cash flows – As explained in the marketing project – though the project may look independent but in reality it is not as the brand awareness project can be closely associated with the spending on sales promotions and product specific advertising.






Negotiation Strategy of Ashmark Corporation: Dealing with a Supply Disruption

References & Further Readings

Brent B. Moritz, Christopher W. Craighead (2018), "Ashmark Corporation: Dealing with a Supply Disruption Harvard Business Review Case Study. Published by HBR Publications.


Dynic Corp SWOT Analysis / TOWS Matrix

Consumer Cyclical , Photography


Tata Consultancy SWOT Analysis / TOWS Matrix

Technology , Software & Programming


Mehadrin SWOT Analysis / TOWS Matrix

Consumer/Non-Cyclical , Crops


SSR Mining SWOT Analysis / TOWS Matrix

Basic Materials , Gold & Silver


Encounter Technologi SWOT Analysis / TOWS Matrix

Technology , Software & Programming


Urja Global SWOT Analysis / TOWS Matrix

Utilities , Electric Utilities


Asuransi Ramayana SWOT Analysis / TOWS Matrix

Financial , Insurance (Prop. & Casualty)


Shenzhen Kaifa A SWOT Analysis / TOWS Matrix

Technology , Computer Storage Devices